B. Report on the Progress of Each Highway Construction Project of $10 million or More as Required by A.C.A § 27-65-107(a)(19) [Exhibit B] - Randy Ort, Deputy D… 4:07
Randy Ort, Deputy Director and COO of ARDOT, delivered the quarterly report on all highway projects costing $10 million or more and fielded numerous questions about project status, delays and costs, including the I-30 Saline County contract where he explained that the work is about 45 % complete, two time-extension appeals are pending and no damages have yet been assessed.
[5:04][5:11][5:20][5:28][5:41][5:45][5:51][5:55][6:00][6:10][6:16][6:29][6:51][7:11][7:23]
No formal motions or votes were taken; the committee simply recorded the information and indicated it would follow up on the specific data requests (e.g., second-bid amount, utility relocation schedules).
[11:27][11:45][11:52][12:18][12:45][12:51]
C. Review of April 2022 Monthly Update of the ALC Efficiency Study Recommendations Rules for Implementation [Exhibit C] - Randy Ort, Deputy Director and Chief … 31:27
Randy Ort presented the April 2022 monthly update on the ALC Efficiency Study implementation rules, noting that the draft rules were first shown at the September 15 meeting, opened for public comment (receiving two comments on recommendation 6), and that the contractor-performance evaluation committee will now include two industry representatives while not evaluating contractors themselves.
[31:29][32:01][32:33][33:07]
He walked the committee through the report format-highlighting new items in green that will turn black in future releases-and answered Senator Linda Chesterfield’s questions about the staffing structure, confirming four assistant chiefs overseeing the various recommendation areas.
[36:34][36:52][36:59][37:24][37:32][37:49][38:03][38:13]
Representative Lanny Fite used the opportunity to reiterate the I-30 bid figures and liquidated-damage estimate, and the committee acknowledged the explanation and closed the item without further action.
[38:40][39:04][39:14][39:44][39:47]
This is the quorum of the Highway Commission Review and Advisory Committee. We will begin with a report on the progress of each highway under construction for $10 million or more. If you would, state your name and who you're with, and you're welcome to proceed. Thank you, Mr. Chairman, committee members.
I'm Randy Ortt. I'm Deputy Director, Chief Operating Officer for the Department of Transportation. I bring regrets from our Director, Lori Tudor, who is out of state today, not able to be here, or else, as you all know, she would be here in front of you today. So with that being said, we submitted to you our quarterly report of projects that are under construction, that are $10 million or greater, and be happy to entertain any questions or comments you have. Any questions from members? Senator
Hammer. Afternoon, Randy. Can you tell me, on the I-30 project down there in Saline County, can you tell me where the contractor is as far as the calendar dates or where is it in the report? Is that one in here? Oh, yes,
Well, the behind arrow just shows that they are, they've been assessed 75 percent of the the time allotted to the project and have completed approximately 45% of the work. I'm
over here by the post. Okay, there you are. Sorry. Thank you. I know that's a difficult project. We've had two or three meetings on it down there, I understand that. What about the damages that are assessed and are they going to be awarded any additional dates to the contract, are they going to be awarded any more time to the contract dates?
There are, I believe, two appeals that they have under consideration right now, but we're still looking at the, if they're legitimate appeals or not, that they're, the ones that they have submitted for additional time have been denied. Have been denied?
Yes. Okay. And do you know what the, you know what their current total damages are as far as any damages that have been assessed because of delays on their part?
They have not been. We don't assess damages until they actually reach the estimated completion date. So they have not been assessed damages to date. So we won't, until toward the end of the project before they are actually assessed damages. And we'll begin, at that point, we begin to withhold payments. Okay. All right. Thank you. Yes, sir. Senator
Mark Johnson. Thank you, Mr. Chairman. Mr. Hort, this is kind of a similar situation question as what Senator Hammer asked, but this is about the Highway 10 just west of 430. Someone wrote into the Mahatma and the Democrat Gazette and described going through that area as an autocross. And I actually, 50 years or so ago, I actually did autocross, so I can tell you it was not as challenging as going through that area. And I understand sometimes y'all have to create things like that, but about how much longer are we looking in that area between 4.30 and, say, I guess that's a Rodney Parham light there. And I know construction goes further out than that, but that's the very circuitous, snake-like, confusing area. So can you give us a ballpark on that one and how it's coming? All right. Thank you. For those of
you who want to follow along, we're on page 32 in the document here. As you can see, we've already accepted about 60% of the work, and they've used just over 50% of the time. So from that perspective, they're progressing quite well. Now, there will be more traffic pattern changes coming up as the job progresses, so we'll be changing the road course over there, if you want to use that autocross dialogue. But that project is actually going quite well. That is one of our alternative delivery projects. It's a construction manager, general contractor, CMGC job, and it has got about one year left, a little over a year left, before it's totally completed.
So maybe summer of 23 we'll see it completed. Okay. Well, I know it's going to be great because that's been a serious traffic area. It's just it keeps getting bigger and bigger, but this one is a little – I mean, I feel for Senator Hammer's constituents down on I-30. That one sometimes is scary. This one is more annoying, but I appreciate the fact that we're coming along. So thank you very much. Thank you,
Mr. Chairman. Thank you, Senator. Senator Rice. Thank you, Mr. Chair. Randy, I'm just wondering, because surcharges and transportation costs and anything related to oil is affecting everything, I haven't heard anything. How is that affecting your construction projects? And also, how is it affecting your agency? Do you have kind of an
up significantly. Yes, it is. Obviously, the projects that we already have under construction, it has less of an impact on those because we have signed contracts in place. We are concerned about upcoming projects. Prices are escalating. That will affect how much money we have to spend to get the proper amount of work done. As for the agency itself, obviously with the size of the fleet that we have, we do burn quite a bit of gasoline and diesel on our own. And we buy that fuel in bulk and we are seeing, I forget, Annie Keene, our equipment procurement division head, gave a report to us here just a few weeks ago on that. And I forget the percentage increase that he quoted at that time, but it is a rather significant increase that we're seeing. So the cost of doing business is definitely going
Thank you, Mr. Chair. Back on I-30, the bid on that was $187 million. What was the second bid on that, the second lowest bid? Representative, we'll have to get back with you on that.
here. Maybe we can have it before the end of the meeting. Okay. Okay. My next question is the liquidated damages is around $77,000 a day. Is that correct? Yes, sir. That's once they exceed the contract time. Okay. And if they finish early, it's $77,000 a day. Is that correct? Is that the same incentive? Yes, sir. Okay. And if you can find that out on the second bid, I'd appreciate that. If you'll indulge me, Mr. Chair, I have another question on the Highway 5 183 project that is two years behind right now. And I noticed that it's only 3% change orders in that project right there. And utilities, I am relocating utilities, is the main cost of this two-year delay in this? Would that be proper in saying that? Yes, sir. I think there were some
Do the utilities meet at the beginning of the contract and give dates in which they will move out of the, have those utilities relocated? Yes, sir. Is there anything that binds them to have it done in that time period that they say? No, sir. Okay. Thank you,
Mr. Chairman. Randy, I'm going to take off candidate hat and put Senator hat on. Page 45. I think I'm dealing with an easement situation. Is the lag that's going on on 253 predominantly? Can you update me on that for my constituents? Do you have information on that? Page 45. I'm sorry, what was the question? Well, we're so far behind. I mean, we're 6%, and we've used over 50, almost 55% of the time. And I think the meetings I've been in, it's been an easement situation that was part of the delay, but I want to verify that for constituents who might be wandering, mayors and other road
departments. One thing we have done, though, there was another project that was scheduled to follow this project, and I believe we're going to change order that work actually into this contract to at least not finish this one and then begin another one. So we are going to do that, but there have been some utility issues. There's been some right-of-way issues there. We've dealt with the city on that issue. I know you're very
familiar with that situation. one we've talked with. I think my latest is you have an understanding on where that's going to go. Still not. That is correct. Senator Sample a nice light, but usable from my standpoint anyway. Right. Do we have any, are we going to see quite a bit of movement on this here in the not too distant future as far behind as it is? If it's okay, let us get some
more detailed information on that project and get with you specifically. We'll be happy to share it with the entire committee if they so desire, but let us get
Call me Senator. Give me the big head. Randy, I want to tell you from the bottom of my heart, I thank y'all for what you're doing in southeast Arkansas. I know I was county judge. Everybody wants something. Nobody ever says thanks. Y'all are paving the road in front of my house. It's so smooth. I stepped out of my car at 40 mile an hour like and broke my neck with all that sitting still. And the best part about it, the mailman, one of the construction going on, couldn't put my mail out, and they put my bills in my sister's mailbox. Thank you. I appreciate
Thank you, Mr. Chair. On the Highway 5 project, it's going to be let here. Has the Highway 5 project been let from where it finishes up and where it goes all the way into Benton, or when is that going to be let?
months from now. okay to award it at what point are you going to get the utilities involved to make sure that those are moved out of the way yes they should be involved right
I'm not mistaken, we just awarded that contract, the I-30 project from Geyer Springs to Saline County. We just awarded that contract. We'll be getting that work. That will be majority nighttime work. I'm sure you're familiar with the pavement situation there. It's a situation called ASR. It's deteriorating rapidly. It will not be a total reconstruction. It should not cause the traffic interruptions that these other projects do. And like I said, the majority of the lane closures will take place overnight.
Okay. And I was asked today, how long are you anticipating that project take place? So it's not going to be a daytime, nighttime overlay. It's just strictly going to be nighttime? It will
And I'm sure you thought about this, But a lot of times that traffic from where it is right now is backed up all the way in front of, well, it's backed up all the way to Congo Road sometimes. So just ask you to be mindful on that, please.
That's a project we've thought about for a long, long time because we've got the other I-30 project underway. We've got 30 Crossing going on downtown. It's not an ideal time to undertake something like this, but some things can't be delayed. Yeah, well, we appreciate it getting done, though.
Senator Chesterfield. Thank you, Mr. Chair. Thank you, gentlemen. I'm looking at what you're doing on 161 and also on the 30 crossing. I would be remiss if I did not at least bring up the portion that deals with my particular district on the 30 Crossing piece and the 161, which also has ramifications for my area. Could you enlighten me more on exactly where you are on 161? Are you in the McAlmont area or are you further north or south or east or west of that?
Yeah, now that's a project that's not in this book, correct? Right. That's a project that we did work through Protho Junction up to Fairfax and have that work completed, and we'll be dropping that from the state highway system, and this county will be taking it over. We have another project planned to be underway from Fairfax all the way north up the Jacksonville city limits, as you're aware. That project, we were ready to go to contract, and the county judge came in and wanted to partner with us. He wanted to do some more extensive work than we were able to do the scope of work, And so since they're going to be taking that project over, we're going to drop it from the system, and the county will be doing
that work. Oh, good. Well, I'll talk to the judge. All right, now, that's a good way to do it. Tell me more, because I had the experience of trying to access 6th Street the other
In a different town. I finally made my, I winded my way through that. But tell me a little bit more about the 9th Street Bridge, if you would, and exactly some of those challenges that we're dealing with right there so that I can update my constituents, should they
ask. Yes, a project of this magnitude requires many, many changes. And as you know, we closed down the 9th Street overpass. We tore it down one weekend. We have rebuilt it, and we have opened it back up to traffic. The same weekend, we opened 9th Street to traffic. We shut down 6th, and we tore out 6th Street. So the challenges I had were to explain to people to take a little extra time if you're going to the downtown area. I will say I'm a native of this area. It is still confusing to me if I don't follow the signs. I must commend the team that is down there. They have done some very good trailblazing to find your way around. That doesn't make it easier, but it is something, And I believe we've got about 15 months, 12, no, less than a year before we get to 6th Street opened up again. Okay. And we are on time with the project. That project is moving along quite well. It is a massive project. It's the contractor, the team that's out there stays very, very busy. Day and night, actually. The big benchmark we're looking forward to is moving traffic over onto the new bridge later this year. The bridge that you see paving taking place on right now, that's actually half of what will be there in the end. The plan is to get the new traffic, the traffic over onto that new pavement later this summer. At that point, we'll be able to remove and demolish the existing I-30 bridge and begin constructing the other half. Thank you. Thank you, Mr.
Chair. Thank you, Senator. Representative Inet. Thank you, Mr. Chair. Over here. There you are. I want to thank you all for the ninth street bridge it is pretty nice um so my constituents i live downtown so i'm talking about the i-30 project um the mcaarthur park bridge the pedestrian bridge the lights are out and i've gotten a lot of complaints about that it's a safety issue at night um can you tell me i called energy and they said it's not in their purview and i think the city of little rock is not in their purview are those lights out because of the construction you're doing on
the i-30 crossing project that is correct that's my understanding that that pedestrian overpass is illuminated through the high mass lighting which has all been disconnected for this project there will be lighting obviously once it gets done but throughout the construction there is no
high mass lighting in that area okay all right thank you all right oh i have one more question if you allow me. When do you think the Broadway exit will be finished? On the North Little Rock side? Well, I don't know the
I missed you somehow. Thank you, Mr. Chairman. As we know right now, we have record high gas prices affected nearly seeing Arkansan across the state. I know that many states, including the state of Arkansas, has discussed the suspension of the gas tax, which I believe is way too high in the state of Arkansas. It's kind of a relief to average Arkansans as they go about their day-to-day with record inflation and a number of other issues. Would any of that, if that became a reality in Arkansas, affect any of these projects, or are they already paid for? How would that happen if we did a suspension of our extremely high gas tax here in
the state of Arkansas? All right, thank you, Senator. It would impact us, there's no doubt about that. I don't know, I have not heard how it would be handled at the state level. There was discussion on suspending the federal gas tax and the proposal there was to suspend the gas tax but to replace that revenue with general revenue. So that would not have affected our federal revenue stream. I don't know how it would be handled at the state level.
Well, that's not a bad model considering Arkansas has, what, a billion-dollar surplus? I mean, if I had the reality between the state government having more money or to average our cans and get a little relief at the pump, I know what I would choose. Would that be a model that RDOT would accept if we did
move forward with spending the gas tax? I don't know if it's appropriate for me to comment on any specific model, but our consideration would be cash flow. Thank you. We would need to continue revenue. Representative Rye.
Thank you. Thank you, Mr. Chairman. AJ, for a long time now, from Lepanto to I-555, which is 135 Highway, there's two old bridges there that are in terrible condition, and we really can't put the equipment on it to fix it, but I've noticed that over on 163 that there was one lane work at a time with the red light that's temporary that can be pulled down and I sure wish we could get this fixed because all of northeast Arkansas that's actually in the Jonesboro area that's going toward Memphis is taking that road 135 to Memphis each morning and it's it's tore up very bad it's really dangerous and the school bus uses that road too. Okay yeah I'm very familiar with those bridges and the issues that
we have, especially with those concrete joints. I don't know what we're doing on 163 off the top of my head, but we can certainly look into that, and we'll get back with you. If that would be a viable option, I don't know.
Please. AJ, I'll say this much. That one lane that's being used with that red light is a perfect deal, especially for those bridges that cannot hold heavy equipment. Thank you. Thank you, Representative. Yes, sir.
Representative Carr. Thank you, Mr. Chair. So, I just have a quick question for you on Job BB0903. It's on page 28 of your handouts. So, I know this job takes place at the interchange of Highway 49 and also Walnut Road and Rogers. So, I notice it looks like it's very close to completion. I notice there's a sign there for the on-ramp. It looks like it just has sandbags on it. It looks like you guys are ready to move it and plan it permanently. I noticed on your project here you got 80% of the work accepted and almost all the times completed at 98.5%. I'm just kind of curious to know how close you are and when you all think you could get that done. I'm sorry Representative, what page did you say that was? Page 28 on the 110 pages. It's actually job BB0903. On I-49? Yes sir. Highway 71
interchange improvements. Sorry, our pages are numbered different than yours. Oh, okay. That's another one that I do know that we had right-of-way issues on. Okay. And then there were some, I'm sorry, yeah, the lots of utility issues on that one as well that, again, it came up after the fact, after the contract was awarded. We are on track to have that completed this year, so we're happy about that. And I'm sorry, I was looking for pages, and I'm not sure if I got your specific question. Oh, you did.
now. We're excited about that interchange. It's a design that's going to help traffic flow, we think, tremendously in that area. Absolutely. I sure appreciate the
Representative Carr. Representative Meeks. I'm way over here. Got you. A real easy quick question. Looks like the 4:30 bridge work is getting close to completion. Do you all have a final date on when the 4:30 bridge will wrap up?
Okay. Probably by summertime would be a... Hope so, midsummer. It's looking good, so I'm just curious how soon we might get back to normal on that one.
supply chain. Senator Hill. Over here. On page 48, Randy is where I'm at, on the Highway 367-89 in Cabot, which is 3.2 miles has taken almost, well, it will have taken three years to go 3.2 miles once this is said and done. And my concern with this one is once we get it done, I think it's going to be great, but right now it's strawberry season. I don't know if you know how serious that is in Cabot, Arkansas, and the traffic right through there. I don't know if you've heard from some of the individuals. I haven't been there. Okay. And my concern with this one now is once this is done, everything's going to be good and great is the road's getting to this road. We're going to have one heck of a road to travel on to get through there, the bypass. But it's those other roads that are connecting into that one that are really in serious need, need some help. So I'd like for you all to put that on your books to have your guys check that one out. It's Highway 321. It continues on. In fact, I was actually telling Gil earlier, when your daughter goes to work, I'd like for her to start driving
that. Thank you, sir. Seeing no other questions, nobody. All right. You okay? Okay. In Carroll County, I have a one-lane bridge. It's actually called Elk Ridge, Elk Ranch Road. And originally, I was told it would start construction on that this past November of last year. That's Elk Ridge, Elk Road Ranch. Is that a section of Highway 183?
you all right seeing no other questions we will move on to the next item it's a review of the alc efficiency study recommendation rules for implementation randy all right you are welcome all right thank you mr chair um let me back up just a little
bit and remind you kind of how we've got to this point you know following the adoption of the guide house review study by legislative council back in november 2020 the next step for RDOT was for us to develop rules on how we would implement those 13 recommendations over six focus areas. We actually presented our first draft of those rules to this committee at your September 15th meeting last year. We provided you a hard copy at the end of the meeting, so it was not a discussion topic at that meeting, but we came back to the November 17th meeting, had some discussion about our proposed rules. Following that November 17th meeting, then, we were able to go out for public comment. We advertised this and it stayed out for public comment through the majority of all of December and part of January. Through that time, we only received two public comments, both regarding recommendation number six, which is to implement a construction contractor performance measurement. If you will look on page 12 of, hopefully it's page 12 of what we provided to you. That is recommendation number six, and you will see the changes that we had there. The comments that we got, we are creating a contractor performance evaluation committee, and at first we had that entire committee made up of RDOT representatives. We received comments from the contracting community asking that they be represented on that committee, and we believe that's a good idea, and we are in the process of naming two from the contracting committee to be on the contractor performance evaluation committee. Now, this committee will not be evaluating contractors. In other words, we won't have contractors evaluating other contractors. This is the committee that oversees the development, the long-term implementation, and overall management of this recommendation. So we felt like that was an appropriate change to make. Mr. Chair, I'll be happy to pause right here to see if anybody has any questions regarding that rule change. Any questions from members? seeing none all right thank you if you'll now join with me looking at the monthly update that we submitted to you you can see the picture of the cover on the screen in front of you it's dated April 21st so now that we have the guide house study complete we have our recommendations from the study we have our rules on how we plan to implement those recommendations ALC rules for this subcommittee say that we will provide monthly updates on our progress of implementing, how we're doing implementing those rules. So if you'll turn the page, a couple of pages on that document, you'll see a table of contents that lists out all 13 recommendations over the six focus areas. Flip over, I don't know, a couple of pages. I've flipped to page three. Let's look at recommendation number two. Recommendation number two, you see, takes up the top of the page. The top of the page is right out of the recommendations from the Guidehouse report that was adopted by ALC. Strengthened knowledge management in the anticipation of increased retirement. Right below that you'll see in red where it says rules. Below that in black type is what we are proposing that we have proposed and we are using as the rules to implement that. What you will see in green is what we're going to add new each time. Now this is our first time to submit this to you so there's quite a bit of green type in this one because we've been keeping track some of these things we had in progress during the guide house study while it was going on so they've been going on but everything in green is what you see is new so
That's a very good observation because one of the things we wanted to do today was to understand if this was a good format and a good process, and if we're dealing with black and white, we need to change. We do not have the study loaded on the computer. I apologize. But we can certainly do that from now on if the committee would like that. Okay? Yes. but we will take that into consideration that what you get is a black and white version of it and we'll see if we can't delineate the new information but our plan is to submit this you know we are we will continue to do the quarterly report on projects of 10 million dollars or more and now we will begin submitting this report monthly um and and every time that we submit it the what you see in green in this report will show up as black next time and it won't go away so you can always go back to it and refer to it but anything new that's added will be shown in green each time. So that's the plan that's that's our proposal and suggestion we'd be happy to take feedback from from the committee on if there's a better way
to do it. Senator Chesterfield do you have something? As I look at page five and is it page four and five that the assistant chief seems to be doing quite a bit do you have several assistant chiefs or is it only one person no we
an assistant chief for administration so I see the assistant chief engineer for planning is dealing with the the issue of number one finalize the KPIs and implement the performance and then you have the assistant chief administration for recommendation number two and three and then you have that also for recommendation four so I'm just wondering if this is one in the same person
or the assistant chief that we do have we wanted to keep a high level of oversight on these recommendation on how the implementation is doing with the appropriate assistant chief the divisions beneath that assistant chief will be the ones implementing those recommendations. So the assistant chief for planning is Jared Wiley. He is here today. Assistant chief for administration is Kevin Thornton. He's here. So that's the way we have it structured. So that is one and the same person for
recommendations two, three, and four. We have the assistant chief for administration. That is correct. All right. And then on five, you have the deputy director and chief engineer and assistant chief administration. That is correct. All right. Does that person feel a little bit overloaded or? can they handle it that's
at the beginning I may be in trouble we have one of our highway commissioners Marie Holder from here in Little Rock here with us today so just want to make sure you all recognize that. Thank you for being with us today. I'm sorry, Mr. Chair, if I could real quick. Yes. Representative Fite, I believe, asked about the second low bid on the I-30 project. The low bid, of course, that we're going with that is underway is about $187 million. The second low bid was $303 million. Go ahead
and represent that. Yes, okay. So in that project right now, we're looking at, best I can guess, about $7 million in liquidated damages. That's the estimate. Okay, that is the estimate, current estimate. They're not there yet, but yes. It appears the number of days, if I did my math right, I did it with a calculator, so I'm confident, I think. But between that and the second bid is a pretty huge amount of money. And so did you all see any concern with that big of a divide in it right there, knowing that you could not give it to that second bid? That is correct. Every bid that we receive
on every project goes through a very thorough review to make sure that all the items, make sure the contractors bid the project properly. And there are times that the contractors make errors and they do submit a bid that they cannot fulfill. But this bid was reviewed, and it was determined to be a good bid, that it was possible, practical for them to complete that project the way they bid it.
I think. Thank you. Is there any other questions for members? If there's no question, we'll consider this item reviewed. Is there any other business to come before
B. Report on the Progress of Each Highway Construction Project of $10 million or More as Required by A.C.A § 27-65-107(a)(19) [Exhibit B] - Randy Ort, Deputy Director and Chief Operating Officer, Arkansas Department of Transportation (ARDOT)
4:07 - 31:27114 segments24 speakers
Randy Ort, Deputy Director and COO of ARDOT, delivered the quarterly report on all highway projects costing $10 million or more and fielded numerous questions about project status, delays and costs, including the I-30 Saline County contract where he explained that the work is about 45 % complete, two time-extension appeals are pending and no damages have yet been assessed.
[5:04][5:11][5:20][5:28][5:41][5:45][5:51][5:55][6:00][6:10][6:16][6:29][6:51][7:11][7:23]
No formal motions or votes were taken; the committee simply recorded the information and indicated it would follow up on the specific data requests (e.g., second-bid amount, utility relocation schedules).
[11:27][11:45][11:52][12:18][12:45][12:51]
C. Review of April 2022 Monthly Update of the ALC Efficiency Study Recommendations Rules for Implementation [Exhibit C] - Randy Ort, Deputy Director and Chief Operating Officer, ARDOT
31:27 - 40:4229 segments7 speakers1 document
Randy Ort presented the April 2022 monthly update on the ALC Efficiency Study implementation rules, noting that the draft rules were first shown at the September 15 meeting, opened for public comment (receiving two comments on recommendation 6), and that the contractor-performance evaluation committee will now include two industry representatives while not evaluating contractors themselves.
[31:29][32:01][32:33][33:07]
He walked the committee through the report format-highlighting new items in green that will turn black in future releases-and answered Senator Linda Chesterfield’s questions about the staffing structure, confirming four assistant chiefs overseeing the various recommendation areas.
[36:34][36:52][36:59][37:24][37:32][37:49][38:03][38:13]
Representative Lanny Fite used the opportunity to reiterate the I-30 bid figures and liquidated-damage estimate, and the committee acknowledged the explanation and closed the item without further action.
[38:40][39:04][39:14][39:44][39:47]