B. Update Regarding the National Electric Vehicle Infrastructure Formula Program (“NEVI Program”) [Exhibit B] - Brad McCaleb, Transportation Planning and Polic… 0:41
Brad McCaleb, Division Engineer for Transportation Planning and Policy at RDOT, presented the NEVI program, noting that Arkansas will receive $54.1 million over five years, that the state will not own or operate charging stations, and that owners must provide a 20 % match to federal funds.
[0:51][1:14][1:47][2:19][2:49][3:21][3:53]
He explained that the NEVI plan was approved by the FHWA in September, described the stakeholder groups, public-virtual session, gap-mapping of interstate corridors, and the development of a competitive procurement framework.
[6:38][7:13][7:47][8:25][8:57][9:32][10:05][10:38][11:12][11:46]
C. Update Regarding Interstate 69 - Lorie Tudor, Director, Department of Transportation 28:43
Lorie Tudor, DOT Director, briefed the committee on the I-69 corridor, stating the total project cost is $35-$40 billion, that 900 miles are already operational nationwide, and that Arkansas contains four “independent utility” segments including the Mississippi River crossing.
[29:10][29:44][30:16]
She reported that about 42 miles are currently open in Arkansas, that $4.1 billion is needed for a full build-out, highlighted recent openings such as the Monticello bypass and upcoming groundbreaking, and noted that further segments await funding.
[30:39][30:42][30:51][31:21][32:02]
Tudor also explained that the half-cent sales-tax fund provides $150 million for I-69, with prioritization and public outreach now underway.
[32:02][32:37][33:09]
E. Discussion Relating to Passenger Train Service in Arkansas 33:51
Representative Craig Christiansen introduced Amtrak officials Derek James and Ishmael Cuevas, who outlined Amtrak’s history, current service in Arkansas, and the “Amtrak Connects Us” vision to add 39 new routes, improve 25 existing ones, and seek $17 billion in federal grants for rail projects.
[34:45][35:16][35:47][35:57][36:17][39:32][40:03][40:34][41:08][41:39][42:13][42:45][43:17]
They detailed planned investments of over $12 million for Arkansas station upgrades, a request for state assistance with highway signage to stations, and the possibility of using rural bus funds to connect communities to Amtrak.
[43:50][44:21][44:55][45:26][45:57][46:09][46:15][46:30]
In the Q&A, the chair asked about onboard security, and the presenters explained Amtrak’s police presence, random TSA-style screenings, and background checks for passengers.
[45:57][46:09][46:15][46:30][46:48][47:03][47:16]
D. Adoption and Discussion of Interim Study Proposal 2021-112 by Representative Vivian Flowers – To Regulate Length of a Railroad Train Operated on a Main Line… 48:28
Representative Vivian Flowers opened the hearing by introducing the interim study proposal (House Bill 1631) that would limit train length on Arkansas main-line and branch-line tracks to 8,500 feet, emphasizing safety concerns from blocked crossings in small towns and the need for state-level regulation.
[48:37][48:42][49:19][49:50][50:24][50:57][51:40]
Committee members raised questions about possible infrastructure fixes and the proper jurisdiction, with Rep. Johnny Rye asking whether larger sidings would help, Rep. Stan Berry and others stressing that train-length limits are a federal Commerce-Clause issue, and attorney Paul Benham citing the 1945 Supreme Court decision that states cannot restrict interstate train length.
[1:16:30][1:16:52][1:17:10][1:17:25][1:17:57][1:18:31][1:18:59][1:33:06][1:33:38][1:34:19][1:34:54][1:35:32]
The transportation committee have come to order. Thank you all for being here. It's been a while since we've met. Good to see everyone. This is the best-looking committee in the whole House side, so we are going to try to move things along. If you have questions, certainly we want you to ask them, but let's try not to get repetitive. Unless you know me, I like to move the committee along, get all the information we can, but let's keep it moving. And so we're going to start with our update regarding the National Electric Vehicle Infrastructure Formula. So if our presenters will introduce yourself, and
Department of Transportation. Morning, I'm Brad McCaleb. I'm the Division Engineer for Transportation Planning and Policy at RDOT. Chairman Holcomb and committee members, thank you for the opportunity to share with you this morning the Arkansas Department of Transportation's efforts related to the National Electric Vehicle Infrastructure Program, otherwise known as NEVI. Our overall approach to this program has been to meet the federal minimum requirements while maintaining a free market perspective in order to maximize the benefits for the state of Arkansas. To that end, RDOT has determined that we will not own, operate, or maintain NEVI charging stations, nor will we place NEVI charging stations on our property. This is in compliance with the federal 23 U.S. Code, Section 111. We do not intend to use state funds for the non-federal match to implement the program, and charging station owner and operators will be required to provide at least a 20% match to the federal funds for the program. My presentation today will cover some basic information about electric vehicles, an overview of the NEVI program, a description of the Arkansas Electric Vehicle Infrastructure Deployment Plan, and the next steps in the process. There are three categories of electric vehicles and chargers. Hybrid vehicles have an engine that charges an electric motor rather than plugging into a charger or plugging into charge. Plug-in hybrids have an engine and electric motor that can be charged at a level one or level two chargers depending on the design. A level one charger uses a standard 110 volt outlet. It provides approximately a five mile range per charging hour. A level 2 charger uses a 208 to 240 volt outlet. These are the most common types of chargers in public locations, and they deliver about 25 miles of range per charging hour. Battery electric vehicles do not have an engine. In addition to the battery, they have direct drive electric motors at each axle, and they use a direct current or DC fast charger. This is the type of charger that the NEVI program is focused on implementing. These chargers deliver approximately 100 to 200 plus miles of range per 30 minutes of charge and are primarily for long-distance travel. The Infrastructure Investment and Jobs Act, or EJA, includes $7.5 billion for the alternative fuels infrastructure, and it has two components. The first component is the $5 billion NEVI formula program. Arkansas is scheduled to receive $54.1 million over the next five years, and the first approximately $8.1 million is already available. The second component includes $2.5 billion in competitive grant funding, evenly split between EV charging stations and other types of alternative fuels. NEVI program requires that interstates and designated alternative fuel corridors have a publicly accessible DC fast charging station every 50 miles and within one mile of the exit. They have to have at least four 150 kilowatt chargers that can operate at the same time and deliver up to 600 kilowatts per hour. By comparison, the average U.S. home uses less than 900 kilowatts per month. The station must have a combined charging system port, which is a specific plug configuration that is common to most vehicles. Recently, the Joint Office clarified that all of the charging stations must be operational in order for the state to achieve fully built-out status. The NEVI program also requires that 40% of the benefits from NEVI be realized by disadvantaged and rural communities. Currently, there are a total of almost 500 miles of interstates and alternative fuel corridors in Arkansas. About 63% of them pass through disadvantaged communities, and about 70% pass through rural communities in Arkansas. RDOT will engage with communities to better understand their needs, priorities, and benefits as we move forward. On September 14th, Federal Highway Administration provided an update on certain issues pertaining to the NEVI program. The Buy America waiver applies to the obligation of the NEVI funds. A full waiver is currently available for the remainder of this year but will be phased out by the end of 2023. In 2024, final assembly must be completed in the U.S., and the cost of U.S. manufactured parts must exceed 55 percent of the total component cost. There are currently requests for comments on these rules, and so that could change. We'll have to wait for the final rules to be established. The Title VI of the Civil Rights Act of 1964 applies to the projects funded under the NEVI program. The Disadvantaged Business Enterprise Program does not apply to NEVI funds and states may not establish DBE goals. This is a result of the section under which the federal code that the bill was passed. Accessibility guidance for charging stations. States have been encouraged to consider application of the U.S. Access Board's technical assistance to assure that all citizens have access to the charging stations. We started development of our plan in May. We submitted the plan to the Joint Office of the Federal Highway Administration and the Department of Energy on July 29th. Our plan was approved by the Federal Highway Administration on September 14th. The reviewers commented that our plan was concise and easy to read. They noted that we engaged in strong coordination and made great use of graphics to help explain the plan. Additionally, they submitted our table of known risks and challenges to the Federal Highway Administration's headquarters as a best practices example. Federal Highway's initial 90-day guidance that was released in June for use in the development of the plan outlined a formal plan template, which included this guidance, and we were required to address each of these topics in our plan. The first step in our plan development process was to form a project management team which consisted of staff from RDOT, staff from Energy and Environment, and Arkansas's Clean Cities Coalition. We meet weekly to coordinate on the plan development. Next, we brought in HNTB, a national architecture and engineering firm that has worked with RDOT on a number of projects to provide us with assistance. A major component of our stakeholder coordination was the formation of the Arkansas Electrification Working Group. The working group members assisted with strategic decisions and reviewed draft plans or drafts of the plan components, and we will continue to utilize both the project management team and the electrification working group moving forward. To engage with the general public, we hosted a virtual public involvement session on June the 21st. There are 84 participants that attended, and after a formal presentation, project management team members addressed questions that were posted by the attendees. A recording of the event was posted on our NEVI website for public viewing, along with additional information, fact sheets, and frequently asked questions. Our approved plan is also currently posted on the website. We've also engaged in initial coordination with efforts with our neighboring states and their departments of transportation to understand where key gaps in the charging station network may exist on our borders. Because our neighboring states are also in the process of developing their competitive procurement process, we don't know exactly where the charging stations will be located at this time. We do intend to continue coordination with our neighbors throughout the remainder of the process. Our objective is to fully build out 100% of Arkansas's interstates and designated alternative fuel corridors until we achieve the fully built out status to the NEVI program standards. Our strategy for accomplishing this is to spur investment in EV charging stations through a competitive procurement program for potential owner-operators. Once we are certified as fully built out, the next phase will be to move to other routes of significance, likely U.S. and state routes with high average daily traffic. If funding remains after providing sufficient regional coverage, RDOT will use feedback from our ongoing public and stakeholder engagement to determine additional priorities. NEVI funds will be awarded through a competitive procurement process to third-party operators. Our initial priority for eligible locations, we'd fill gaps in the charging network on the interstates and designated alternative fuel corridors. We will establish a pass-fail criteria around the minimum compliance requirements and a bonding agreement, as well as additional scored criteria to select final awardees. the blue dots on this map are existing nevy compliant charging stations the pink areas indicate a 25 mile driving distance from each of those stations this map shows 11 gap segments on arkansas's interstates and designated alternative fuel corridors that are not nevy compliant at this time several gaps segments are more than 50 miles and therefore will need at least two electric vehicle charging stations to span those gaps. The locations directly along our borders could ultimately be served by stations located in neighboring states. Our next steps include the development of the competitive procurement program, publication for requests for proposals, review of the applications, making awards, Executing the contracts and then ongoing program management including development of the next annual plan The timing on all of this still remains uncertain until the federal rules are finalized Possibly as late as next summer Once that occurs, we'll have we will need to incorporate those final rules into our competitive procurement program This slide is just showing that we are working right now on those scoring criteria that I mentioned earlier that will be used in our application process. The basic framework includes the minimum criteria based on program requirements and objectives. These criteria would be evaluated on a pass-fail basis. If an applicant doesn't meet those minimum criteria, then their application would not be considered any further. Beyond these minimum criteria, there will be some number of additional criteria that may address issues such as the specifics of a site, economic development factors, costs, and others. Having the pass-fail portion is almost certain, while the rest is still very much open to discussion and evaluation. As mentioned earlier, we are continuing in our efforts to reach out to the general public and engage them. As part of those efforts, we have developed this map-based survey tool. This map displays the current gaps in the charging station network, and we are encouraging any interested parties to use this tool to provide comments or concerns about the locations along the gaps that are of interest to them. The map-based survey tool is accessible from computers and mobile devices and is located on our website at www.rdot.gov/evplan. Based on the information from the top ten EV charging station companies, we're currently estimating that the average cost for one of the charging stations will be $1,000,000. This includes utility site make ready upgrades, hardware installation and everything needed to activate the EV charging station. At $1,000,000 per site, Arkansas will have sufficient NEVI fiscal year 22 and fiscal year 23 funds to build out approximately 23 locations. We anticipate this leaving a large amount of funding to build out other key routes of significance and additional Arkansas saw EV charging station priorities. Thank you again for the opportunity to share this information with you. The website here again on the slide is currently available and the email address is also active if you would like to sign up to receive regular information from us or provide any input feel free to send it to that address and chairman I'd be glad to respond to any questions if if you would like.
you, Mr. Chairman. Do you have any long-range plans for anything past 25 or 50 miles? I mean, like if someone leaves, say, Jonesboro on their way to Little Rock and it's 135, 40 miles, what do they do in that kind of situation, sir? Do they have to break it up? recharge in between that ride? Well the the requirements for this program is for
a charging station to be located every 50 miles. So for a trip the distance that you mentioned they should have access to at least one possibly two of the DC fast chargers. But if they are running low on a charge then yes they would need to stop somewhere and recharge their vehicle. Yes sir follow-up sir Please well and plus you
have that time frame that you're stopping to get all that done I mean now if you fill up in Jonesboro and you come down here You know you do it one time and get back to Jonesboro with without another fill up. Yes, sir
So so that that's why we're looking at some additional criteria beyond just the minimum Criteria in the application process. We want to see what other types of amenities may be available either at the Excuse me specific location where the chargers will be will be at or Nearby where someone could get their vehicle charging and then maybe walk in short distance across a parking lot or something like that And have access to some other amenities
Thank you. Thank you, sir. Yes, sir Springer you recommend Good morning. Thank you, Mr. Chair. My question is with respect to communication of the this program other than persons going to the RDOT website What other actions have been taken by your department in order to communicate this to the general
public? Well, we of course we did have the online session or the virtual session when we were developing the initial plan As I mentioned we have the map survey tool that is posted online We've been making these presentations to several committees as well as some community groups around the state. So at this point, those are the
other community groups that you've communicated this to? Well, and I said community groups. We've been to Northwest Arkansas. They've had several meetings related to electric vehicles. We did a presentation for the, I'm sorry, I'm trying to remember the name, Arkansas's electric co-ops, basically.
Final question, Mr. Chair. So maybe since we have the chart of the areas where they're going to be, maybe you can focus in on those areas for the line that you showed us earlier where those locations are, just a suggestion. Yes. Yes, ma'am. Communities in those areas. Yes, ma'am. Okay, thank you. Representative Bryant, do you recognize?
Thank you, Mr. Chair. Whenever we figure out who the partners are going to be, the owner-operators are going to be, and we award funding to them, is all the funding that they're going to be receiving their responsibility to do their own large-scale, their own engineering, or is the state going to kind of focalize some of that so we're not having 50 stations throughout the state that are all different,
different equipment, things like that? There are specific requirements within the legislation and, well, in the guidance and in the draft legislation at this point, or I say legislation rules, excuse me, and the draft rules at this point that let the owner-operators know and the charging equipment manufacturers know what requirements have to be met. So the department will not be doing any design work for these applicants. That's, they know their, they know their business. We're not in that business. So our responsibility is going to be overseeing the program, being sure that all of the requirements have been met and that we locate these stations in order to fill these gaps, as well as trying to be sure that they provide the types of amenities that the public might want
to have available. Okay, and final question is, is there anything in the program that limits how much per kilowatt hour that the owner can charge to an EV
participant? There's not anything in the rules related to how much is charged, but my understanding is, of course, that we'll still have to go through the rate commission to determine how much the charging station operators will be paying. But then it's pretty much market prices at that point. Okay, thank you. Representative
you go into a little bit more detail on kind of the interplay between RDOT and the private sector on this? I guess you mentioned that y'all are not going to be in the business of owning or operating the EV station. So I'm guessing you approve the applicants and all of that. Can you just go into a little bit more detail on what that process looks like?
I can tell you what we have up to this point. We're still in the process of developing that. But at this point, as I said before, there will be a request for proposals that will describe the program, have the requirements in line with the federal rules and regulations. There will be an application there for them to fill out. We'll have the minimum requirements that they will have to indicate that they meet those in order to continue through the application process. Then there will be some additional criteria. We don't know at this point exactly what those will be. It could be something along the lines of please identify the types of amenities that would be available either at your location or adjacent to your location. Some of these charging stations we envision, you know, we all know we have them at Walmarts now, but there are other types of businesses, convenience stores, as an example, retail outlets that we anticipate will have charging stations as well. So for the applicant to identify what those amenities are would help us to choose between two competing applicants, as an example. One of the main things we're going to be watching for, though, is for that location, will it fill the gap that we have in our system now? Because that's what we have to achieve in compliance with the federal regulations. And, again, our goal is to achieve that fully built-out status as quickly
folks be able to apply? So at this point, we're anticipating final rules sometime between spring of 23 and late summer of 23. We have to have those final rules so that we can compare that to our draft. Competitive process be sure that we're in compliance with all of those rules Then we can go out with a request for proposals Take in those applications through the review selection process Then we'll have to enter into contracts with each of those owner operators we're anticipating somewhere between 12 and 24 months for them to get a station installed and operational that's highly dependent on our supply chain issues plus we're seeing a ramp up in the private sector already to install these facilities so the charging station manufacturers are already um you know seeing a increase in demand and then the outcome of the legislation or the rules on the buy america waiver will also have an effect on that so at this point We, from today, we could be looking at two to two and a half years before the first charging stations are
Mine's not a question, mine's more of a comment. In my area, there is a bank of charging stations that have been put in. I would like to see personally as a requirement for these stations that they not be put into a low area because this bank of charging stations, when it rains, becomes a lake around them and it creates a little bit of a serious safety issue for the people who are charging. And so that's just my comment. Thank you,
sir. Thank you, Mr. Chair. Hopefully, last question. I appreciate your comments with respect to the equity considerations, and I appreciate that. And then the communication to the different areas of the state. So you indicated that you would be having conversations with the different cooperatives across the state. For the record, can you identify the cooperatives around the state that will be taking place? Name the one can you name the corporatist if not then if you would share that information with us I don't want to put you on the spot for you to okay Attest this is not a test. I just want to make sure that all the all this the entire state is covered and has the opportunity
Right, right So I don't know the names of all the cooperatives and what I was referring to was a previous presentation that we made to that group. It was an overarching group of the electric utility providers in the state, not specific community groups. So, as you can imagine, getting around the entire state to have in-person meetings, which of course is the way we did it not too long ago, but with the time frame that we have been working with, that's a big challenge. That's why we have decided to use the virtual platforms and provide access to anyone that wants to interact with us relating to the program. Well, I appreciate that. The question is, but how do you
communicate that? Some folks may not have the access to, they may not know that they can go to the website and see that. So the question is, how do you communicate to them and let them know that that's available to them on the website? because that has been a problem in other meetings that I've attended, where people are not aware that they can go to your website and see certain things. Thank you. Yes, ma'am.
Any other questions for the committee? Seeing none, Brad, appreciate your presentation. Thank you, Chairman. I appreciate your opportunity. I don't answer all the questions, so we appreciate that. Okay. Before we go any further, I forgot to recognize my vice chair. Any, do you have any comment or anything this morning? You're fine. Don't usually recognize dignitaries in the audience, but we've got Ms. Prissy Hickerson with us today, former highway commissioner and former chairman of this committee, which I was vice chair. Wave at them. Say, see how good looking you are. There you are. Thank you. It's good to see you back. Okay. We'll move on then to, I had a question about I-69 that hopefully I'm wanting to move along a lot faster than it's going to move, I know, but Ms. Tudor is here to give us a little update on that. So, Ms. Laurie,
if you will, you have the floor. Okay, thank you. So, good morning, everyone. I'll just give you a quick update on the history and then where we're at as far as implementing the projects. In 1991, the I-69 corridor was identified as a congressionally designated high-priority corridor. It's a very significant freight and trade corridor, and it's about 2,700 miles from the Gulf of Mexico to Canada. The total cost to build out the 2,700-mile corridor is between $35 and $40 billion. There's 900 miles that are currently operational of that corridor. If you look at what's going on in Arkansas, this shows you that what they've done is they've divided that corridor up into what they call segments of independent utility. And what that means is if that particular segment is built, it can be fully operational. In Arkansas, we have four segments of independent utility for the I-69 corridor. They include the Mississippi River crossing. They include the segment between US 65 North from McGee over to Highway 82 in El Dorado. And then it picks up in El Dorado there and goes south towards Streetport, Louisiana. Then we also have a segment of independent utility, which is the 530 connector, part of which has already been built. Overall, we have about 42 miles open to traffic for the I-69 corridor in Arkansas. So the 184 miles of Interstate 69 and the Interstate 69 connector is $4.1 billion in Arkansas for a fully built-out interstate. Would you repeat that?
did you say? $4.1 billion for a fully built-out interstate in Arkansas, four lanes. Now, we've done around 40 miles of the connector. It's two lanes of the Ultimate Four. We bought right away for four lanes, but we only built the two lanes. Then we've also built the eastern segment of the Monticello Bypass that's open to traffic. We recently led to contract the two lanes of the Ultimate Four from Monticello over to Highway 278. As you can see on this map, it's colored in red. We just recently opened that to traffic. We'll be having a groundbreaking on that soon. We'll let you know about that, Representative Holcomb. We'll want you there. And then the second one, we'll pick up there at 278 and go over to McGee. That's scheduled for 2025, and we'll be building two lanes of that ultimate four lanes. The environmental documents are approved for the entire corridor in Arkansas, and for the Great River Bridge or the Mississippi River Bridge over there near Arkansas City, we've already purchased the right-of-way for that segment. But because of the expense of building that bridge, and until we get funding in place, we won't start construction of that until we know we can completely build that segment out. As you're aware, in November of 2020, Arkansas approved taking the word temporary off the half-cent sales tax revenue for highways, and prior to the vote, we showed them what we would do as far as capital and congestion relief projects across the state for the next 20 years. The funding for this half-cent sales tax in these projects begins to be available in July 2023 and it included 150 million for interstate 69 to continue the progress that we've been making we're in the process of prioritizing that funding for future projects and we'll be doing a lot of public outreach and those types of things to figure out what what we'll do next but the money's there and we'll be continuing our progress on I-69. This picture is an artist's rendering of the future Great River Bridge, so I'll stop there and open it up for any questions you might have. Any questions, committee? All right. Looks like that was an
easy one for you. I appreciate the update. Okay. Hopefully, I'll see that in my lifetime. Thank you for your presentation. You're welcome. Okay, without objection, we are going to move item E up and hear it next, and it's not going to be a very long presentation, and then we'll hear item D last, so Representative Christensen, if you're ready, if you'll bring your presenters up, have them introduce herself, you may begin.
second. Good morning, members. Can you hear me clearly now? Clearly. We have a handout sheet that was passed out to each of you that discusses a little historical overview of Amtrak and its service in the state of Arkansas. So that, if you've had time to read it, will give you a little background on where we are and why we're here, and also is something to take away to think about and realize where we're going to expand the role of passenger service in rail in the state of Arkansas. It is my honor to bring forward Mr. Derek James and Mr. Ishmael Cuevas from Amtrak's governmental affairs and they will give you a presentation explaining where we are, what our proposals are in the state of Arkansas, which one would include expanding signage and other things around the state and implementing a stop in northeast Arkansas in Bald Knob. There has not been a stop in northeast Arkansas since 1996 when the city of Newport renovated its depot and ousted Amtrak from that facility. So without further ado, I would like to turn it over to Derek James and Ishmael Cuevas from Amtrak and give them a warm Arkansas welcome and show them a little southern hospitality down here in the natural state if you would. Gentlemen, if you will
There you go. You're all right. How's that? Excellent. Thank you, Mr. Chairman. Thank you for the fine introduction, Representative Christensen. My name is Derek James, Director of Government Affairs for Amtrak. Hello, good morning. My name is Eshmael Cuevas, Government Affairs for Amtrak as well. Thank you. We'll keep this brief. This is really just an opportunity for us to introduce and to talk to you a little bit about what we do and what the potential is for improving mobility for the citizens of Arkansas. Again, my name is Derek. We are glad to be here with you in the Capitol today, just a few blocks from our station down the hill at Union Station, which we have served since 1974. Amtrak was created by Congress with a mission to preserve quality passenger rail service connecting the nation. For the first 140 years of railroading in America, passenger and freight train service was provided by the nation's investor-owned railroad companies. But changing technology, public policy, and shift in traveler preferences and options decimated the passenger side of their business, making it uneconomical to provide. The private freight railroads began piling up millions of dollars in deficits on the passenger side of their ledgers and many railroads actually began to declare bankruptcy and threatened to take the entire industry down. This is back in the 60s. Rather than nationalize the industry like many European railroads did, Congress and the administration at the time created a quasi-public corporation that would relieve the railroads of their financial burden, yet preserve some service to build upon. There have been some successful high-speed services introduced on railroads in our peer nations and the public and the policymakers were intrigued the agreement with the railroads to relieve them of the regulatory requirement of providing passenger service was that they would provide access to their facilities by the new operator that Congress created and that's us Amtrak next slide from the beginning we've grown to provide service over a 21,000 mile network to 500 communities in 46 states and three provinces. In the last year before the pandemic, we provided 32 and a half million trips on our system and earned 3.3 billion dollars in revenue and almost for the first time ever we almost broke even on operations covering 99% of our operating costs. Then we know what happened after that. Next slide. Of course the pandemic caused ridership to plummet. We were able to keep the system intact thanks to 4.7 billion in relief over several COVID bills enacted by Congress in both the Trump and the Biden administrations. Ridership has begun to recover, a steady recovery, where we are now at 80% of pre-pandemic trips, but because of a lack of equipment and the difficulty of hiring mechanical employees, we don't expect to be back to those pre-COVID levels until fiscal year 24. operating ratio did decline from 99% to 72%, but our mission is to provide valuable service to the public at the least cost to the taxpayer. It'll take time, it'll take investments in the system and a continuing pivot by us to address the changes in travel demand before we could return to those levels that we saw in fiscal year 19. Next slide. The investment we seek will allow Amtrak to become a more relevant travel option for Americans. We have plans to add new routes, more trains, and more stations to serve more people. If you can go to the image with the map. The black lines on this map represent the Amtrak routes of today. This is our vision for corridor development. We call it Amtrak Connects Us. The golden overlays, which you can see say between Oklahoma City and Fort Worth, or between LA and San Diego, those are routes that we presently operate service on but we want to increase the service and then the blue lines are routes that we would like to add new service our Amtrak connects us plan calls for 39 new routes 25 improved routes with more frequencies and service to 160 new places in the country we want to double our ridership from the 32 million we carried in fiscal year 19 to 64 million in the next 20 years last year's bipartisan infrastructure law included 66 billion dollars in advanced funding over five years for investments in the nation's railroads. The funds will be distributed in direct grants to us at Amtrak and to competitive grants that the states can apply for to invest in passenger and freight rail projects to improve both passenger and freight rail in your state. At Amtrak, we're going to use those grants to rebuild tunnels and bridges where we own the infrastructure, upgrade stations and technology, and to buy new trains, locomotives, and passenger cars. The new trains and upgraded stations are what our Arkansas customers will see. The federal grants will go to states and sub-state entities that work with Amtrak and other passenger providers on improvements and expansion projects. 17 billion is available for states like Arkansas to compete for if they would like to participate. The new locomotors and passenger cars and station upgrades are already coming online. Expect to see more of that. We'll soon be issuing a solicitation for new coaches, sleepers, and diners to re-equip our daily service through Arkansas, the Texas Eagle. Next slide. Before new cars can come online though, it's our responsibility to maximize revenue. Again, we want to get that operating ratio back up. That means taking steps coming out of the pandemic to make our trains more appealing to customers. We've been upgrading stations on top of projects to improve ADA accessibility. We've been adding new lighting, smooth level boarding platforms, signage, railings, parking, and renovated restrooms to make a great first impression for our passengers and serve as a welcoming front door in the communities that we serve. The legacy cars that we have, some of them dating back to the 70s, will be going through an interior refresh with new seats, carpets, curtains, and restrooms. Our food service offerings are now fresher with healthier sandwiches, salads, and beverages, and we've continued to upgrade our technology with flexible customer-facing digital options to make and change reservations, check train status, and communicate with us directly. Although Amtrak brought passenger service back to Arkansas in 1974, as Representative Christensen mentioned, after a three-year absence, we restored service over the former Mopac route, connecting Walnut Ridge, Little Rock, Malvern, and Texarkana to the rest of the national network. In 2013, with great local celebration, we added station stop at Hope because of local desire and expect to receive an official actually we just got an official request from the mayor of Bald Knob with lots of support from some of you to add a new station at Bald Knob so we're going to begin the process of that. We've hired an architectural and engineering firm that are advancing designs for major station upgrades at Walnut Ridge, Malvern, and Arkadelphia and we'll be constructing an attractive new station on the Arkansas side of Texarkana to help jump start redeveloping their downtown. Our station will join projects like the Grimm Hotel renovation in showing the potential of that city. In all, we'll spend more than $12 million on station upgrades in Arkansas in the next three years. 26 Arkansas residents, as a matter of fact, work for Amtrak with a payroll of $2.8 million annually. And last, next slide. I just wanted to give you a brief snapshot of Arkansas and the nation where we have been and where we would like to go there are items you could help us with one thing I've noticed is I travel around the state that your state highways are missing pathfinders or trailblazers telling motorists where to exit for the train station I see signs for airports but not for train stations please consider directing the highway and transportation department to include this valuable traveler information as a matter of fact I think we have a meeting set up with our dot this afternoon to discuss this very issue so also short of adding new train service many states use their federal 5311 bus rural transit funds to subsidize connecting coach service from rural areas to the nearest Amtrak station, broadening community's connection to the larger transportation network. We know many Americans do not have reliable access to their own vehicle, are too young or too old to drive, yet still deserve the freedom and mobility that the rest of us enjoy. Our mission is mobility. Where we offer such connecting bus services nationwide and elsewhere, Amtrak offers through ticketing between the destinations and every station on the Amtrak network, so planning and purchase is seamless to the customer. We have 500 train stations, but through these interline bus arranges, we serve 400 more rural communities across the country. And the last slide, thanks. So lastly, regarding improvements to our rural long-distance network, the service that we operate here in Arkansas is part of our long-distance network. Congress has directed the federal government to study and determine the value and feasibility of adding new routes or improving existing routes with more frequencies. The 15 long-distance routes are unique in our system and that the federal government provides us an annual grant to continue these services despite their operating losses. Congress deems these routes critical to rural connectivity and wants to see more routes if possible. The FRA is beginning a study to look at all the pre-existing routes that may have been discontinued back to 1970 before Amtrak existed. Public involvement and stakeholder engagement will be part of their outreach. A report will be issued to Congress a year from now. Amtrak encourages you to engage with the FRA if there are service additions that should include Arkansas. And I thank you for your time and would certainly be pleased to answer any questions.
Derek, I rode the train. I like riding trains. I rode a couple times to St. Louis and one question I had is there is there any security provided on the train y'all have a police officer on board security man
open nature of rail travel is such that we can't aren't able to provide TSA style service like you do at airports but oh we have a police department at Amtrak and they work with TSA to do random screening so we'll come to a station and randomly screened. We also now, like the airlines do, we get the name and the birth date of everybody who's traveling on the train so we can do background checks prior to folks boarding so we know who is on the train. And from time to time we will have Amtrak police who are riding the train. That was more or less
what I was referring to, those who are riding the train. I rode at night and of course I just rode in a regular passenger car and I didn't take anything to help me sleep because I wanted to, but I realized I wasn't going to sleep because there was probably, I don't know how many was in the car. It was full, but everyone in there was snowing. So there was no sleep, but it was a good ride. Do we have any questions from committee members
want you to get a sleeping car. Okay. Thank you. All right. Before we move on to item D, let me remind you, if you're here and you want to speak in reference to item D, if your name's not on the agenda list, be sure and sign up for testimony so we can have that down. And all right, Representative Flowers, are you ready? Okay. Without objection, we will adopt the ISP for study and hear discussion. Hearing no objection, we'll move forward. Representative Flowers, come forward.
Chairman. Colleagues, I've filed this, what was House Bill 1631 as an independent study because there is a lot of confusing and competing, or there was a lot of compute confusing and competing discussion not only during our committee hearing but just out in the stratosphere and I think that you'll hear some of that discussion today and I think that what is and should be before us now and moving forward is how we address some of the safety concerns that came to me and I'm sure many of you as as well as just the ear of our constituents, especially in smaller cities and small towns, having to deal with blocked railroad crossings. So I'd like to open up, before I ask for us to hear from those who came to speak today, I just wanted to point out that I have a railroad in my district. I love the trains. I have grown up and have been an adult riding trains. And I'm also very aware, as you all are, that the railroad is an incredibly important component of our transportation system and our economy. And so my focus in bringing this bill forward in the first place and bringing it to study is to figure out how we can address the problems that exist in a way that is least harmful to our railroad companies, but that also address the incredibly important issues that affect our constituents, be they individuals or our businesses. And the two things that I'll ask you all to think about if they haven't come to your districts are, you know, as a result of the train lengthening, and that hasn't just happened in Arkansas, that poses a difference in just the time that it takes a train to get past a crossing. but also creates some dynamics whereby sometimes that crossing is actually blocked for hours. We've heard about some of those issues and complaints. And then, of course, when that happens, especially in a small city and rural area where that is the crossing that affords police and other public safety officials to address emergencies, that then becomes a problem and sometimes life-threatening. So that's why we're here. That's why we're talking about these issues. And I really appreciate everyone from all sides for coming today. And with that, Mr. Chairman, I would like to invite the witnesses as they are listed. And I think there are some substitutions today to join me at the podium to speak to their concerns and whatever presentations they have.
them introduce yourself. Sure. Let's bring Mr. Gerald Sale first. today he has with him Mr. Jeff McKenzie and I believe he went over there and signed in and he will Mr. McKenzie will replace Mr. Stallings or they'll they'll talk about who wasn't able to come I know that there were some issues but if we could bring those two up and we can start
We'll try to be brief. Go ahead and introduce yourself, please. My name is Gerald Sale. I'm the legislative director for the state of Arkansas. Gerald, your mic's not up close enough. My name is Gerald Sale. I'm the state legislative director for the state of Arkansas for Smart Transportation, representing rail crews in the state of Arkansas. Jeff McKenzie,
representing the Brotherhood of Locomotive, Engineering, Training and Union. I'd like to thank the chairman and the committee for allowing us to speak today. You may proceed.
I think one of the issues we run into concerning rail regulation in the state of Arkansas, and one of the arguments that we run up against all the time is whether or not the state has the right to regulate rail traffic through the state of Arkansas. So I'll put together this quick piece for you guys, just to lay a couple of things out. First here, I know all of you take an oath to the Arkansas Constitution, and Arkansas Constitution states that the General Assembly shall pass laws to correct abuses and prevent unjust discrimination and excessive charges by railroads. I would say, hopefully by the time we're finished here today, we'll understand that this is an egregious abuse by the railroads themselves placed upon our communities. And hopefully you'll understand it's your right as the General Assembly to possibly come up with a remedy. Also, we'll go further that 49 U.S. Code 20106 grants states the right to adopt or continue and enforce law regulations in order to railroad safety and security. Well, this is a safety issue. I think the carriers are concerned about the economic impact, and it's not our worries here. We don't want to adversely affect the carriers themselves. I'm a UP employee. My counterpart here is a Union Pacific employee. We want them to do well, but we don't feel like they should do well at the cost of safety, especially for the communities of our state. I'm sure a lot of the arguments you'll hear today as well, not to speculate, will concern the Interstate Commerce Commission. The Interstate Commerce Commission was put together, and it has the right to regulate railroads. They are correct, but it's to regulate railroads on economic issues. The Federal Railroad Safety Act of 1970 grants regulation of the railroads based on the Federal Railroad Safety Act. And one of the other arguments we hear quite often is that we should kick the can down the road, we should let the federal government take care of this. Well, if we kick the can back to the federal government and they kick the can back to us, where does that leave Arkansans? That's our main concern. And this is from a letter, the GAO did a report with the Department of Transportation concerning train length as trains have grown over the past years. Now, this gentleman that I have quoted here is a Trump appointee, and he's kicked the can down to the states, to you guys. And what he says is that, you know, a federal one-size-fits-all approach is not the best way to report every specific issue. Well, the infrastructure is different in every state. It makes perfect sense. A western state, when you're running across Arizona probably doesn't have the density in areas that we have in Arkansas and this is something that affects not only cities like Little Rock but it affects rural communities as well and I put this together here at the end just as an example currently we have over 250 laws regulating the railroads on on the state record right now so how can we argue that the states don't have the right you don't have the right to regulate the railroads when it's obvious that since our founding as far as our constitution goes up through the years we've regulated the railroad when needed to when it's needed to be regulated both for service and also for safety when it comes to our citizen room now i'll put together a small handout for you here about train length just to cover a few of the problems. And just so you know, Jeff and I hired out together, as we'd say, on the railroad. Jeff is an engineer. I'm a conductor. We're pushing 20 years on the railroad, so we have a little bit of experience. We're not just a couple of paid lobbyists or lawyers up here. Of course, you can probably already tell that. But to sell a point, we're here because we're concerned of what we see daily on the railroad. And if you'll look on page two, I did a layout of the railroads of the state of Arkansas. And I went ahead on mine and I highlighted Union Pacific. And the reason I did this is the train length issue is an issue that we've seen really affects the short lines quite as much as the class ones. The class ones have adopted this theory of running extra long trains. And the reason I highlighted UP is not because we both work for UP, but I highlighted UP because, as you can see by this, as far as Class I railroads in the state, they're really the big game in town. You know, BNSF, KCS go in and out of the state on the corners, but if we're really going to look at how it affects the state of Arkansas, I think Union Pacific paints a good picture. So it's not to pick on them, but it's just because of the abundance of mileage that they have compared to the others. So on page three, if we look at it, I want to talk to you for a second about infrastructure. That's where our main concerns is. In the laws we've looked at in the past, they weren't as written or designed to hurt the carriers at all. We actually tried to be as reasonable as we could be. At the time when we started looking at this and started gaining concern, the 8,500 length that we were asking for was bigger than the average size train running across Arkansas. Since then, unfortunately, we've started to see trains grow two to three miles long and sometimes longer. They're even taking trains that used to be our longest, which would be, on average, a coal train. That's about the longest train you'd see. And what they're doing is they're putting two coal trains together and hauling them across the state. And what we run into with that is, where I get into the infrastructure, is the majority of our tracks in the state, when two trains are running in opposite directions, they have to make a meet, what we would call a meet. Now, when they make a meet, one train pulls into a siding. And the timing is paramount, of course, but what happens when the infrastructure won't fit the trains that they're running now, all the trains have to back up and wait. If there's one siding that a 10,000-foot train can fit into, then every train will have to wait until that 10,000-foot train hits that siding. So all the trains are staged and backed up, causing blockage. And the other issue is, when they won't fit, where does the 16,000-foot train fit, period? You know, as a crew, we would run together constantly, and we'd normally run on the same runs once you establish enough seniority. So we would know where 8,000-foot train would fit. So if traffic gets backed up, we would know we could fit in this area and stay off of any municipality crossings. We could stay off farmer crossings. But the problem gets where you have trains twice as long. There's not as many opportunities to lay back and stay off people's crossings. And just the example, and like I said, not to pick on Union Pacific, but we have around 90 sidings in the state of Arkansas. Now, the 8,500 length that we're looking at, this is one of the reasons we came up with that length, is it would fit the, it's bigger than what the average cold train was. But also, 8,500 feet would fit in half of the sidings for Union Pacific in the state of Arkansas. So every other siding, we could make a meet. But what happens when you go beyond that limit, let's say we go to a 10,000-foot train, then we can only make meets in 12 sidings in the state of Arkansas, Denonite. And if you go up to a 12,000-foot train, then you're going to be able to make a meet in one siding in the whole state, in the Pacific Alliance. And, guys, we're seeing now where, what's probably, Jeff, what's the largest train that you've run as an engineer? 16 000 feet i mean we're seeing six 14 16 000 feet the largest one i've seen in the state's been 18 000 feet so far so if a 12 000 foot train only fit in one siding in the state where are these trains going to fit so this is a printout on page four this is when i first started getting armed this is this is is Union Pacific self-imposed, it's a network planning map, and this is their self-imposed length restrictions. And what I've done here is I zoomed in on the North Little Rock area and the directions that our tracks travel out. And if you'll look, the self-imposed limitation before they adopted running longer trains, you know, west of Fort Smith was 7,600 feet. You know, north to Missouri is 8,000 feet. South to Louisiana is 8,000 feet. To Texas was 8,000 feet. This was their self-imposed limitation because it was what fit in the infrastructure. And they did that to try, in my opinion, to try to alleviate the pressure, not only placed on us as crews and the dangers that will occur when you grow trains twice as long, but also on the general public. Now, as we stated before, there is no limit on the length of trains run in the state, self-opposed by the railroads. Page 5, just talk about a few things that happen with longer trains. Jeff can speak to this. You only have so much power in a train. When you double the length of the train, you double the weight of the train. So getting stopped becomes an issue. Getting started becomes an issue. If you want to talk
about that for a second. I'd also like to add, the longer they are, the heavier they are, the more likely they are to break. Because you have buff forces, draft forces that come in with your cars, because each one will have a little bit of movement in them. The more cars you put on them, the more movement you have throughout a whole entire train, which would equal several hundred feet on a several thousand foot long train. So, like I said, the bigger and the heavier, the more likely you are to tear one up, break it, which causes delays over crossings because you can't move them when they're tore up until they're fixed. It causes communication problems with your conductor as he walks back there to fix your train. It causes like a ripple effect with the longer trains and the consequences they have. Yeah, and just below that,
you'll see staging, and that's what happens, what I was talking about earlier. When all the trains are waiting, it's like a traffic jam to make a meet, or if they're building a larger train in the yard, to be able to get into the yard because everything is staged back waiting to service one train. Just one train can affect, if you have one train that's 16,000 foot and you have 20 trains that are 6,000 foot, that one train can end up having all the trains stop
No, he's not. I apologize for that. Our office had officers coming down, but our officers ended up coming down with something else called COVID. Okay. All right. Thank you. All right. Go ahead. Proceed. Okay. No problem. Page
six, I mean, I know it's a plethora of issues, but we have radio communication signals with the rear train. I'm sure everyone here can remember seeing the cabooses back in the day, and you had crews that would ride in the caboose for communication purposes, also to tie breaks and cut trains and do other things. Now, that was replaced in the mid-80s, and it was replaced with either an EOT, which is just a small box on the end of the train that would radio communicate with the front of the train, or you might see a locomotive back there to help push the train. As the trains grow longer, we lose communication with that. Now, if you lose communication with that, you often have to slow down, And that's going to create even more staging issues if you have a train that has to run below prescribed speed. We also cover, just below that, have run into issues. We run across detectors. Part of not having a caboose where we could stop and have enough crews to inspect trains, the railroad invested in their infrastructure at this time, and they put in radio detectors. So we'll go over, they'll check for dragging equipment. They may check for hot wheels. And it will radio to us that everything is okay. But if we can't hear that, and often you can't, especially with a train at this length, then we also have to slow down. And in some cases, if we're carrying hazardous material, we may have to stop and inspect the train. And to what Jeff was talking about there on page 7, when we're talking about locomotives and train length, it's important to keep in mind that our braking systems were invented in the 1870s. This air brake system, on Amtrak, they have electronic brakes, which is great, and we've asked for that from the federal government for years. They chose not to grant that to us. But we're dealing with reconstruction-era technology here, and it's also technology that wasn't intended to have a train that was 16,000 feet long. And what you run into with that when you run air, as my colleague here was saying, have all that slack so it can equal to quite a bit bit of area so we have airlines that run through airlines can leak when it's that long which will cause you to have air issues on your train they can actually the couplers can come undone because of because of the length and also when it's cold weather that's when we start having issues we're going to have more brake issues because we're having to feel a longer line of air and as the cold weather comes out once you stop and you start to try to as we would say pump up the air on your train to get your brakes release it can take forever on a longer train compared to shorter train not only does it affect the application the brakes but it affects recovering the brake system once they've been applied you know as Jeff spoke about - these trains were designed the knuckles were designed to break the weakest point on a train is the knuckle where they clip together it's almost like two hands going together now when they were designed to break that's the reason for that is you want that piece to break it's easy for me as a conductor to get off walk back radio ahead and replace that knuckle and we can get on the move but the problem is the knuckles weren't designed to haul 16,000 feet they were designed to haul six or seven thousand feet and none of those changes have been made either my colleague here too was talking if you look on page 8 the negative effects of running a long train and we have a few diagrams there if you want to talk about the way those work Jeff
and appreciate that page 8 here I was talking about the buff and draft forces, the cars, basically like whenever you have them going downhill or with a distributive power, you want to push them together to hold them together. Well, like you have a different train territory, you might go over two or three different hills at the same time, where you have buff and draft going on in your train, all different areas. Well, that just kind of chaos back there, basically. You can't keep it stretched out because you don't have enough power too long because you're draped over hills. You can't keep them bunched up same reason to keep it held together so buff and draft forces greatly increased with the longer the train is basically because you're just spread out over such a far distance that you you're not all uphill you're not all downhill you might be draped over two or three hills at the same time and with draft forces you break buff forces you can push a car out to derail it i mean a lot of issues can happen with these oars yeah
it shows there on the buckling you can tell what he's talking about with the momentum coming in we call that a run-in just so as as it runs in it can cause buckling it cause cars to derail but the same thing when you have a run out it can either cause a break into the resistance or or it can cause a derailment too think of it straightening all of a sudden in a curve or buckling together in a curve you know jackknifing is is basically the same thing and the forces are doubled when we double the size of the train and the weakness is doubled when we double the size of the train you have twice as many weak points along with twice as much weight and I spoke to this earlier we're running the issues now that we're building these trains these long that the yards on page nine the yards weren't designed to build trains this long so what happens let's say here in Little Rock in North Little Rock where there's a train being built as 16,000 feet or Pine Bluff where the train being built at 16,000 feet that train has to hang out onto the main line out of the yard. Well, that means no other trains can run into the yard. So every train has to back up and wait, waiting to get to their home terminal. And that creates a lot of our crossing issues there. So if you're building a train that long and you may have 10 empty tracks here in North Little Rock, well, if you don't have access to turn into those tracks because the main track is occupied, then you're going to end up having a staging effect there too. It's like a giant traffic jam and you know below that this goes into yard and also out on the rail as a conductor but we have FRA required testing and you know you have to you have to check both sides of the train you have to walk both sides of the train so if the trains hanging out of the yard even though there may be a car man it's gonna take him
yes sir thank you quick question I have a coal-fired power plant in my district my house district curiosity is 16,000 feet 16,000 is that normally a coal train that runs across Arkansas 7500 feet every 500 feet would be the
what will happen a lot of the times as they will take a coal train And they may run a load in at 7,500 feet, but they may put two together empties leaving. So we've always serviced. That's the reason why when we looked at the limitation, coal industry, our runs where we come from are a huge coal run coming from the Powder Basin in Wyoming. We didn't want to inflict any pain or any damage on the coal companies themselves or on the railroads because we recognize that's our bread and butter. And that's the reason why when we looked, like Jeff said, normally your average cold train's 7,500 feet long. And that's your loads going in are still that way most of the time. But when they're leaving, they'll double them up to try to pull two at the same time out. You have two empties leaving out of there, and then you're looking at, you know, 16,000 foot at that time. Okay, appreciate it. Thank you. No problem. You know, and this is what Representative Flower spoke about on page 10, just to give you an idea. You know, our main concern, and I can speak to this as a conductor, one of my main concerns, and I represent men and women that I'm concerned about. The general public doesn't really understand what we do. You know, when we block a crossing, they're mad at us. Now, I don't have the authority to go back and cut a crossing contrary to what people think. If we have to ask, we radio to Omaha, Nebraska, and they would give us authority to cut a crossing. Well, a lot of times, they don't want to give us that authority because they're ever optimistic that we're going to get on the move soon. And I understand that. But what concerns me, and just a side note here, we have bulletproof glass on the locomotives for a reason. And what concerns me is, you know, I have a crew sitting in Mayflower, and they have to sit there for four hours because they can't cut the crossing. But then the dispatcher tells them, well, it doesn't look like you're going to move. You can cut the crossing. And then he or she has to go back and cut the crossing there in the public while the public's angry at us. You know, that is a big concern for us, of course. And, you know, the other concern, we work together with the firemen and a lot of other organizations, is we're concerned we're going to run into an issue like they ran into in Louisiana in the last couple of years where it was actually one of our trains. It just happened to be in Louisiana, one of my crews. Cheryl, I'm going to ask you to try to move it along a
little bit. We've got eight other speakers, so we're not trying to cut you off, but we want to move it along. And they're not all here, by the way. Okay.
All right. Thank you. What we worry about is first responders. And they ran into this in Louisiana a couple years back where first responder, a gentleman had a heart attack. They ended up blocked at the crossing. They wouldn't allow them to cut the crossing. This is one of my crews. So they ended up having to air vacuum out. They had to land a helicopter out there in Cane Field, and it ended up, he died on the way to the hospital. You know, that's, these are our main concerns. We shouldn't let Wall Street dictate the safety of Main Street. And that's all I ask. And to finish here, I'd like for you to look at the last page. You know, this started in Arkansas. We were a little bit ahead of the curve looking at this because we could see what the other railroads had done on the East Coast, specifically CSX. But what I will say is if you can see there, we have over 20 states that are running this legislation now. Most of them are in the South. You know, the Western states is not as big of an issue, but the infrastructure issue across the South, it's a huge issue. So I'd just like to
you recognize? Thank you, Mr. Chairman. Let me ask this. I know you got a lot of problems with this, but let's just say that you got a train that's 16, 18, you know, long. This area to the right of where we actually scoot over to let another train through, do you think that if those areas to the right that are kind of the holding areas were adjusted, do you think that that would help?
It wouldn't fix all issues because we have communication issues, some other things I've talked about, but if the infrastructure was designed to fit these trains, it would alleviate a large portion of the issues. Representative
Berry, you recognize? Thank you, Mr. Chairman. So just as it did last year, this remains a FRA issue as far as determination of train length in your chart that you refer to as far as becoming a nationwide issue. All this is saying that it's proposed into committees. It's just like right now. There's nothing being done in any states to change the laws because the federal government has the say over the length of trains. It's just no different than the airways, the waterways, the railways. It's a federal issue. My district, We've never had a problem with training. We've never had a problem with trains breaking down, stopping and blocking intersections in my district or two of the surrounding districts. So my suggestion would be that this be taken to the congressional delegation and you sit down with Senator Cotton, Senator Bozeman, French Hill, and the others and come up with a solution until such time. It really doesn't pertain to the state. And I know if we were by chance to change the law in the state of Arkansas, they're not going to stop that train over in Oklahoma and cut it in half and allow the train to go through the state of Arkansas. It's just not going to happen. But I did have one question. How does this, because both of you are union officials, how does this impact the union? What does the union gain from this? Is it more jobs, more conductors, more trains, higher pay because you've got more conductors? There's something that the union has to gain from this. Well, first off, on your first part
of your question, I would say that plainly, the federal government has kicked it back down to the state. They conducted their own study. The FRA came out. The Department of Transportation came out and said that the states are better suited to do this. Both have the right, and I would love for the FRA to do this. But I think, I would hope that as elected officials for the state of Arkansas, it's your duty not to depend on the federal government to take care of our problems, but to take care of our problems here. As far as what the union gains or doesn't gain, the union gains safety. I'm not allowed to try to propose any legislation that would create jobs. That's not what we work on. We have two different branches of our union, just to let you know. we have a legislative branch which works on safety and sanitation and then we have a contract branch nothing to do with the contract branch they they handle and negotiate how many jobs we have they handle negotiate what type of jobs we have we don't handle that and like you you know I'm I'm an elected official as well by I don't have a district but by my members in the state of Arkansas to represent them and their concerns. And, you know, you spoke to your district, too. You know, my crews run through that district. That's UP lines that run through there. And there's one train track on that whole run, or one siding on the whole run. It's 10,000 feet. It's Mayflower. And Mayflower has had repeated issues. I don't know if that's the district next to you. So much so that they're trying to build an overpass there. But the reporting I've received is the overpass they're building is kind of outside of town, So it really doesn't alleviate the problem of blocking trains and when we talked about staging that's where every train stages now So it's not hitting you I agree because there's no place for them to meet where you are It's it's it's hitting Mayflower because that's
the one place they can meet on a western run Okay, one follow up so The bottom line is that This is a federal issue. It's always been a federal issue. It's not going to be decided in the state of Arkansas This committee is not going to make that decision, and my suggestion would be take it to the feds.
reckon that? Thank you. Just a curiosity question. I come from the aviation world, and nobody, no plane, commercial, passenger, or freight typically leaves an airport without the destination being free and clear at the other side is the trains operate in that same manner where they just dispatch out of Chicago going to San Antonio they know who they're going to come in contact with and for these sighting issues they know and they can stall or they can move trains is that yeah the dispatcher
plans that out I mean he'll show up to work he'll figure out what he has running north what he has running south and try to make a plan So as long as something doesn't break down, and that's where the breakdowns run into or create an issue for us, normally they have a plan laid out for that, but that's where your staging comes in. If your plan limits you to one siding that a train may fit in or no sidings, what type of plan can you put forth in? Okay. And one other question.
Go ahead. And it's just, it deals with one of our statutes, 2312-1006, Operation and Movement of Trains. I'm just curious where we've been at this issue. The State Highway Commission is hereby designated as a sole public body to deal with and is hereby given exclusive jurisdiction over all matters pertaining to the operation and movement of trains within this state, including but not limited to the obstruction of any public highway, road, street, or other railroad crossing or public property. Yes. Have we talked to the State Highway Commission to see if there's any rules or that they want to promulgate?
There's multiple laws on the books that aren't enforced at the State Highway Commission. Like, we have a crossing law on the books that's virtually unenforceable and it's not enforced. You know, I've looked at that and I've provided that just to show that the state has a history of regulating rail throughout the state. And we have not only the jurisdiction, but we have a body that's charged with enforcing the law. That's the reason the laws we've previously written, we hand it over to them. And also, as far as the fines, it would roll back into the Department of Transportation as well for the state. But I don't think that necessarily alleviates, constitutionally, your right to regulate any railroad. Go ahead and
just says the crossing rule is an example. Yeah, it's basically written in an enforceable manner. and the fine on it is pretty small. It's not anything
that would have any teeth. In the research I did, because I was intrigued by this because I like transportation, states such as Oklahoma and Oregon have laws that the states have passed, and every time a jurisdiction writes a citation and it gets challenged in court, the courts have dismissed it, saying the federal will overrule that state law. And so since we're bouncing this ball back and forth, we've had eight years maybe of a friendly administration to the unions and four years of a more management side. Now we're back to more friendly. Obviously with the labor agreement coming to a head, I think it's mostly approved. One of the reasons that they are pushing back the two-man rule to go back out for interim review is because they say these long trains. Do we know why the FRA is not addressing long trains? From
discussions I've had, they're still wanting to study it again after the original GAO study in the Department of Transportation. I can't answer to why they haven't yet. That's why I feel like it leaves us to come up with a solution until they come up with a better solution. Like I said before, I would love for the FRA to come down and solve this issue, and then we can discuss things that aren't as controversial. But unfortunately, they failed to do so, so far.
Representative Springer, recognize for a question. Thank you. I would like to make a comment and then a question. I was in the committee. Good morning again. Morning. I was in the committee when we talked about this last year, and you all made a presentation. And I appreciate the additional information that you've provided to us today regarding this very issue. And I would just like to make this statement that there are no train tracks that are being blocked and having the concerns that you are talking about. But in my surrounding district, I receive many complaints all the time about the problems with the long train. So it is an issue within our state, within my community, within my district. And I definitely think that there's a need for it to be addressed. So I appreciate you all coming here today and making your presentation again And you're pretty adamant about that and I'm I really appreciate your efforts to constantly come back to us and bring this to our attention So I thank you very much for doing so and if there's anything that I can do to assist, please just let me know Thank you. Where's your question? Please contact, would you please contact me and let me know if there's anything that I can do
Flowers, first of all, your opening presentation this morning was well presented and excellent. Mr. Sayle. Thank you. originating and terminating in Arkansas, those that originate and terminate here, are not the subject of this discussion, is that
correct? That's not normally an issue for us. Most of the trains that, well, actually, let me repeat that. Let me answer that a different way. Most of the trains that originate and terminate here are local trains. They service local industries and those normally aren't issues that we would have with those. They're normally a shorter, smaller train And they also normally have three people as far as a crew because there's more work to do So that alleviates some of the other issues where our three freight has two two people on the train But I will say we have a lot of trains that originate here like the terrain I was talking about in Louisiana Was built in Pine Bluff that ended up the gentleman was blocked at the crossing end up losing his life So we have a lot of trains that do originate here that are built in Little Rock built in Pine Bluff Van Buren yard that actually create the issue that we were talking about earlier, where they're so long they won't fit in the yard as they're
being built so they affect every other train. I understand that, but I appreciate your answer on the local trains, what originates and terminates within the state. In your discussions, have you discussed with Union Pacific how they're addressing this capacity problem by lengthening sidings and doing other things that are necessary to mitigate the problems that they recognize as well in long trains? Beyond testimony
and talking after testimony where they talked about plans that they had for maybe changing the infrastructure, no, sir. But I will say, as we all know here, infrastructure hadn't really changed as far as their sightings, you know, in 75, 80 years. And I hope they do change them, but it's not something that would be an
overnight fix would be my concern. Follow-up, Mr. Chairman. Follow-up. As chair of the rail subcommittee, I've probably received more block crossings than anybody else in the state in the last few years since PSR was implemented. I know that our representatives all across the state receive complaints, issues, and problems. So to that extent, I contact RMCC on a regular basis. I will tell you, in the last six months, that has dropped precipitously, as it seems the operational issues are beginning to work themselves out to a degree. I caution that. Higginson and Hensley are two of the areas in the state that have been hot spots along with Jackson 410, Tuckerman, and Jackson 224. And in working with the railroad, we've gotten agreements that specifically have put it in the train rules, the operating rules that say don't block these crossings. I think they're aware of the danger to the public by trains stopping on a crossing and being recruited or whatever, and we see improvements on that on a daily basis. But I think you'll agree that each block crossing, each occupied crossing has unique characteristics, and those are things that are going to have to be worked out on a one-by-one basis to try to make the situation better for all parties concerned. Our job as legislators is to make sure the safety of Arkansans are paramount, not to take sides with labor or management, but to look at what the proper issues are and the best way that we can alleviate those problems. And I agree with Representative Barry that this is an FRA issue. I know they've already brought forward things on crew size and it's my understanding they will visit the train length. So I would encourage you to have more contact with UP on that because I know we have seen an improvement in the block crossings in our communities and particularly the hotspots like Emmett and Jackson County and other places? I would
just say that first I'd have to see the numbers. We need to look at not just block crossing, but how many trains are running during that time. Because as we suffer from inflation, as I'm sure you're aware, and as traffic goes up and down and flows, that's going to be a major factor as far as block trains would be how many cars we're hauling. The other thing I'll speak to that you mentioned, you said it's not your job to side with the union or the carriers. We're not asking you to side
enough to know that I'm a reasonable person. I'm not raw, raw union all the time. I want the carriers to do well, too. But I would say we're not asking you to take our side or their side. We're asking you to take
the public side. All right. Gerald, Jeff, thank you for your testimony. I have no more questions. Representative Flowers, will you call up your next witness,
gonna, I'm gonna let them do their testimony, and I'm gonna let y'all come up last and just finish, uh, when you get ready to testify, so. All right. Who, who, introduce yourself, please,
and Clark Law Firm. I'm representing the Association of Arkansas Railroads. The association consists of the three class one railroads operating across Arkansas. That's the Union Pacific, the NSF, and the Kansas City Southern.
A little closer. Yes, sir. It's like my computer at home. House Bill 1631 seeks to limit the length of trains on interstate railroad lines operating and in the state of Arkansas to 8,500 square feet. Regardless of all of the safety and operational issues that go into a determination of how long the train should be, House Bill 1631 raises the root question, to what extent can states enact laws restricting interstate commerce? And the answer is very simple. They cannot. The issue was decided by the U.S. Supreme Court in 1945. It was a case challenging in Arizona law limiting train links, and the court held that state regulation of train links violates the Commerce Clause of the U.S. Constitution and that states cannot materially restrict the free flow of commerce across state lines. The court, like Representative Berry and Representative Christensen, Note that the practical effect of train length limits in Arkansas is to control train operations beyond the boundaries of the state because it would require breaking up and reassembling trains at state borders. Arizona argued that the regulation was necessary for safety of its residents, which is the same rationale appearing on House Bill 1631. But the court rejected that argument. The court's decision was a categorical statement that any state regulation of train links violates the Commerce Clause and is therefore invalid. This ruling was recognized in the Railroad Safety Act, which states essentially that states may continue to regulate safety issues within their borders, but only to the extent that they do not violate interstate commerce. From a legal point of view, Arkansas cannot stymie railroad's key operational choice of train links. Arkansas cannot limit how many railroad cars can be used on a train. That is a goal beyond the state's reach. Therefore, the Arkansas Railroad Association respectfully asks that you reject the attempts to dictate train links like House Bill 1631 does.
Excuse me. Representative Bryant, you recognize? Thank you, Mr. Chair. Just a question about interstate commerce, just from your legal perspective. When California being a state that is intersecting commercial commerce blocking trucks that are built 2011 or older, 2007 or older, is obviously anything can be challenged through a lawsuit, but is that something that is legal in your opinion?
Well, yes, and as my granddaughter, who's a legal student, says, these are interesting times. and there are attempts from various areas to push the limits, as has been said, to see what states can and can't do. But with regard to train links, the 1945 case is determinative of the issue. The answer, it has to go to the FRA and be determined there. And they are looking at various issues. As you heard, there are a lot of safety and operational issues. and the FRA is looking at all of them and it
takes time. Okay, in saying that, just to follow up, are any of the states that have enacted train lengths or restrictions, I think I watched a federal committee, DeFrazio out of Oregon, said their state did and it got blocked. To your knowledge, are any of those states that have those laws in place challenging that to the Supreme Court? No, I'm not
Representative Ray. Thank you, Mr. Chair. Mr. Benham, I appreciate this brief or statement that you've provided. It's very informative. I'm curious if there are, in addition to the legal arguments on this, are there also what sort of economic considerations are there in terms of the economic impact of a bill like this or a rule like this limiting? That
is one of the issues raised by the GAO letter, and that, too, is something being considered at the federal level. It all goes into just a mass of data that will result ultimately in some regulation. I'm not sure where it's going to be, and I can't answer exactly what impact that will have. Okay. Thank you. Okay, seeing no other questions, Paul appreciates your
impatient. Go ahead. Yes, sir. Thank you. And I will keep this brief. My name is Matthew Stallings. I'm with the Arkansas Professional Firefighters. And our issue here is pretty simple. It's, you know, increased train length means longer time spent at crossings waiting for trains to pass. As emergency responders, it's our job to respond to emergencies with urgency. And, you know, if you have a train that's blocking a crossing for longer, we can't do that. If you're talking about a medical emergency, every second counts. If you're talking about, say, a structure fire, your fire is doubling in size every minute. You know, in an urban setting, we can, you know, maybe dispatch a different unit to go in our place. But if you're talking about, say, a rural area, there might not be another unit. So that's our issue with this. Any questions for me? Thank you, sir. Wait, hold on, hold on.
Sure. Mr. Stallings, could you estimate approximately statewide the number of areas that you would think are problem areas in terms of train crossings? Well, so, I mean,
potentially any area. Any area that there's a crossing and then an emergency on the other side of that area. You know, in an urban area, yes, we could go around. But, like I said, when you're talking about an emergency, like a medical emergency, you're talking about, you know, seconds that count. Especially, you know, trauma, say. And when you're talking about a structure fire, like I said, fire doubles in size
every minute. Sure. I guess, so obviously no one enjoys just sitting at a railroad crossing waiting on a train to pass. And if you're a first responder, you know, that response time is, you know, particularly acute. But so obviously any crossing is an impediment. But with regard to particularly long trains, are there particular areas that are causes of concern, and how many of those are there?
So, like, I'm in Little Rock. You know, we have one place in particular where we, you know, we tend to respond to calls in southwest Little Rock. We use a certain route because, you know, it's our job to be efficient when we move. And we have a certain route that we take to get there. Well, there is a railroad crossing. And so when we get to that crossing, if it's blocked, we're, you know, we're there. You know, we don't generally keep statistics on how often that happens because we, what we would do is say, you know, we're blocked by a crossing, dispatch another unit. But, you know, we keep statistics on our response times, but I don't know that we keep anything that reflects that it was delayed because of a train. Okay, thank you.
Yeah. Any other questions? Representative Bryan? This may not be your question to field, but as the state moves into the AWIN system, the local fire departments, especially ones that, you know, in populated areas, do they have direct communication with the train dispatch through AWINs? No, I mean, we can go
through, like, say if we have an emergency that's happening near a track, we can go through our dispatch and have them contact, you know, whatever the train company is, but we don't generally directly contact them. Any other questions? Okay, thank you. Thank you, sir. Mr. Flowers, do you
have any other? I think that's it. Okay, we've got two others to call up. Drew Tesser, is that correct? And Michael, I'm not going to prop out your name. I missed it last time. Gart, I'll let you tell it when you get up here. Just introduce yourself, gentlemen. You may begin.
Who you're with. It's still morning. Drew Teche, Senior Director of Public Affairs, Union Pacific Railroad. Mr. Chairman, members, I just want to provide just kind of an update from the 21 meeting that we had on this and the extensive hearing. One of the crossings that were brought up were Hensley. It's kind of a good example of how we address some of the issues that we do have on occupied crossings. We know where they are. We work with Representative Christensen and we work with first responders on these issues. Hensley is a road, is a one-way-in, one-way-out neighborhood, horribly, horribly occupied, horribly blocked. We identified that crossing, realized it was an issue. March 2023, that crossing is going to be moved out of the siding that they were talking about. We're building a new siding that they're in the process now going west where it will be completely out of the signal system. So when those train meets that they talk about, now Hensley Road will be out of it. So those are some of the things that we do working with the community, working with the state, working with RDOT. We identify these areas, and we either try to fix them operationally with superintendent orders. Like they mentioned Higginson's, there's a superintendent's order there that says, do not park on these crossings, stop before them. Or we fix them with capacity projects that we do. Looking at the DRDOTS presentation, I saw what their budget was $3.4 billion being spent over 20 years. Pacific spending that, you know, every year on capacity and maintain our tracks and make sure we operate safely. In Arkansas, the last four years, we've spent $600 million, and these are on, you know, safe tracks, technology, and these siding projects that you're talking about. I'm not familiar with above 15,000 foot trains. We run up to 15,000 foot trains, but as was testified to talking about the the coal-fired plant you know if it's too heavy the terrain it's all situational we don't just go let's hook them all up and let's go folks you know we take advantage of efficiencies where we can it was very important during the supply chain crisis because everybody was trying to get employees we were low on crews and you know taking advantage of going up there with one crew at 7,000 feet and hooking on to two of those trains and pulling the empties out helps that coal-fired plant. And that location and throughout, you know, we were struggling getting coal to our electric companies, keeping the power on. We were struggling getting grain to farmers out west to feed the cattle. This period of time, working with Craig Christensen, Arkansas. Operationally, things were tough. Things are running better. We've had an increase in hiring our crews. And just basically, I don't answer any questions y'all may have, but the rail industry, especially Union Pacific, we're here to try to solve problems. We'll meet whenever you want, whoever you want us to meet with. And we have a lot of partners out there. We train a lot of first responders. We got a place in Pueblo, Colorado, where we send, you know, first responders for hazmat training. You know, we're there to solve problems and try to create them. We track them, fix them. Okay, Drew, do you want to
it. Sure. Okay. Representative Springer, you recognize? Good morning. Thank you, Mr. Chair, again. I want to get clarification of what I heard you say. You said that you've identified the areas particularly in the Pulaski County area that there are problems that are Located in this particular because those are my constituents and some of the people live in that area So I want to make sure that I can report back to them what you've stated You've been is it correct that you've indicated that you've set aside monies in order to address the problem particularly the track in Hensley Arkansas and that things are going to be taking place to address that is that what I heard you say hensley arkansas will
be taken care of okay and i will get back with you and give you some more details on it because when i went back to my notes and been doing the research on this i talked to our our capacity team that builds it so we we have we address these issues as we instead of just building a siding and ignoring hensley road we take it into consideration and we engineer it out of the crossing. We're building crossings now or sidings now where we'll go and actually purchase extra right away to build a road. Louisiana says parish, but here county standards for those folks to use to get around our infrastructure. Mr. Chair, follow up.
I want to be specific so I can communicate properly back to my... Okay, so I want to know specifically what's being done. I thought I heard you say that it's going to be like maybe 2023 later in the March 2023
is when that that project's supposed to be completed and done unless there's something that's going to stop it we don't foresee that so that would be some good news for those okay so
the so the project has already started then if it's going to be finished that's a few months away about six months away so it's already started to correct that problem I'm going to be so that's what you hear okay that's what I heard you say. And then you say, what about in the other areas where there have been complaints in Pulaski
County? What's being done there? I don't know all the sections. If you have some other hot spots, I'll gladly work with you. But as Representative Christian said, each crossing has its unique characteristics. Some of them need to be taken care of with capacity projects. There's an opportunity out there that I've been pushing really hard is with RDOT and with communities the federal grade crossing elimination fund those applications used to be very very difficult that money used to go to places like dallas and little rock and population base now you're more your rural communities and they got a lot of other factors in there
that make these these grants accessible more accessible than they were follow up mr chair okay Where is Higginson, Arkansas? Higginson, Arkansas. H-I-G-G-I-N-S-O-N. Higginson. Where is that?
area as well? Since I started my job 17 years ago with Union Pacific, I left Arkansas for a little bit and when I came back I reengaged with Mayor Homsley and We put a superintendent order not to block that crossing and it's
decreased significantly. Okay, and final question. Mr. Chair I'm concerned about these specific areas within in my district compared to other other areas So, are you familiar with one down in the Wrightsville area, Sweet Home area, a track there, as well as a track off of Confederate Boulevard? Are you familiar with those particular areas as well? I don't have the
you, Mr. Chairman. Good morning. My name is Michael Garriga with BNSF Railway. We're based in Fort Worth, Texas. Mr. Chairman, if I may, Representative Bryan asked a question earlier, I might be able to address if that's appropriate at this time. Go ahead. Okay. You had talked about some of the state legislation that had been passed. I believe you mentioned Oregon and Oklahoma. I can speak to the one in Oklahoma. So you had a block crossing bill that was passed, I think, in 2019 that would penalize crews, penalize railroad companies that were occupying those crossings. That legislation was challenged in district court in Oklahoma and ultimately successfully challenged at the appellate level and was recently denied cert by the Supreme Court. That's pretty much precedent now and that legislation was essentially overturned. So just wanted to follow up with that. But my comments will be brief. As it's been pointed out, safety to our employees in our industry, it's paramount, it's paramount at BNSF. If longer trains were such a safety concern, as pointed out by earlier testimony, the FRA, the appropriate Federal Oversight Administration, would be the first in line to seek regulatory action, and they are studying the issue, they continue to study the issue. Certain technologies, such as the use of distributive power. Locomotives have been enabled and allowed railroads to operate our longer trains much more safely. As technology improvement has continued and enabled trains to carry more freight, gradually increased in length. Safety metrics such as accident rates have significantly improved. Thanks to those large investments to upgrade and modernize our rail network, The American rail industry has achieved significant safety improvement metrics across, you know, a number of categories over the last 20 years. I think there was a question about economics. You know, the amount of freight is not going to go down. So whether we restrict the limit of train lengths or not, the amount of freight is going to continue to move, and an increase in the amount of freight is going to continue to occur, and we're going to continue to move the same amount of trains, same amount of freight, but if you restrict that link, it's just going to be more trains hauling the same freight. So I don't think you're going to ultimately solve block crossing issues by eliminating or restricting train links. So freight is going to continue to increase over time, at least that's the hope. You know, given the challenges that the supply chain has seen, the unprecedented supply chain challenge we've had, the lack of availability of crews, you know, it's led to a significant challenge, so we made significant investments back in our network, hiring more people to move more freight. It's just going to increased costs if we start talking about restricting trains, increased costs to the rail industry, and these increased costs will only be passed down to our customers, Customers like Walmart, customers like J.D. Hunt, who happens to also be BNSF's largest customer, your steel plants over in Northeast Arkansas, like Nucor, Big River Steel, the Plum Point Power Plant. The cost of transport, those everyday goods and products will ultimately be passed on to who? The consumer. Energy rates could go up because of the restriction on the movement of coal and energy. And those higher costs are going to impact everyday Arkansas who've already faced, you know, rising costs, rising utility costs. So, like I said, where we've seen unprecedented supply chain challenges, record inflation, do we really want to increase costs of transporting goods so that we can get more crews moving shorter trains? I don't think that's the answer. So, with autonomous trucking, you know, we're going to see that. We're going to see platooning evolving on our highways. You know, in order for the rail industry to remain competitive, we've got to make sure we're able to move freight as efficiently as we possibly can. So, you know, freight restriction would put the rail industry at a competitive disadvantage, and it would put Arkansas at a competitive disadvantage. So, in closing, you know, our industry is safer than it's ever been. Capital investment back in our network has never been more focused on technology, safety, efficiency, reducing those operational costs so that transportation costs and the movement of freight remain stable and rates of our customers remain stable.
you, Michael. Senator Springer. Thank you again, Mr. Chair. One specific question. Who is the person at the federal level that we can make contact with regarding length of trains, the concern that's been voiced here today regarding length of trains? Who is that person at the
I mean, the Federal Railroad Administration is a regulatory agency under our, you know, under the U.S. Department of Transportation, and they are our federal regulators. I understand that. What's the name
questions for committee? Representative Rye. Thank you, Mr. Chairman. Mr. Chairman, I just wonder, you know, being a situation that's actually in the hands of the federal in most situations, is there any way that we could actually feel problems from that transportation subcommittee concerning the problems in Arkansas and have those problems directed to the federal level? Can we do that? Well, I think we're on the right path where
we're at right now. I think we're, you know, I think the union and the company's just going to have to get together in arbitration and work these issues out. That's just my personal opinion, but I appreciate your statement. Any other questions? Jim, do you have anything else to add? Thank you for your testimony. Representative Flowers, you want
to do your closing? Yes, thank you, Mr. Chairman. I want to thank everyone who has stayed to listen and thank everyone who provided information. I really see this study and this hearing as a first step toward gathering information. We tried to address it early on regarding train length, and maybe that's still something that we look at. I would like to remind... my colleagues that we heard from Attorney Benham talk about the 1945 decision which was several decades ago in pursuit of preserving a 1912 law we've heard about infrastructure we've seen charts and graphs about capacity we also know that there are challenges with regard to our first responders there are many many rural areas where there is one railroad and one railroad crossing and I would like to address make two points one as it relates to efficiencies we are living in a time where technology is pushing us forward in light years and some of the results that we see for example in retail is that many of you I'm sure go to now a cash register where you're checking yourself out. And you know where jobs were folks checking you out now you have people fixing those machines. That happens as a result of technology. We've seen how the railroad industry is trying to deal with how many crews are necessary as a result of train lengthening. And that's going to continue to happen. Around the time that we brought this bill you saw fewer crews and fewer people working on these trains and now you see that that has ramped back up but as it relates to cost and what we're doing no one is trying to restrict commerce or restrict trains this is the same number of cars it's the same number of cars it's the same materials that would travel what we're saying is as it relates to the impact to our communities, whether it's hours of waiting time at blocked crossings or whether it's the impact of public safety, it is our job to deal with that. And it may not be placing a limitation. It may be that we worked with the regulatory body while we figure out how we can address this now. We cannot get rid of every block crossing. I think that the response that we've seen in Hensley is appropriate and is great. And I think that our railroads here in this state and other states will continue to address the problems as they come, as they should. But when we as legislators hear from our constituents, whether it's from inconvenience all the way up to safety threats, and we see this as a continuing problem across our state, it is our duty to do something to prevent something from happening. We don't wait until there's an explosion. We have to figure out how do we address those concerns from convenience to safety threats. And if we have unenforceable laws, maybe we figure out ways to better enforce them. Maybe we do work with the feds. But I'll remind you, so this is my second point, I will remind you that I believe it was in 2019, there was a significant threat to one of our major industries. Federal labels, passing laws on federal labels is not our job. As a matter of fact, some of the same federal prohibitions against passing those kinds of laws is something that we knew, and we passed a law out saying that companies could not put rice on their labels, because there was going to be a detriment to one of our major industries. If we see that there's going to be a detriment to our citizenry, and we know that there are issues to our citizenry, it is up to us to make changes, whether it's through regulation, whether it's ramping up existing laws, but we cannot be, we can't just sit on this and say it's a federal law, or hear someone talk about the cost to other industry or to the people when that industry is seeing record profits. And what we're trying to do is say, hey, you guys are expanding these train lengths. So just think about that, please. And let's work together. I'll continue to collect data, and we'll figure out what we should do in this next session. That's what this study is for. It is not to attack an industry. No industry is going to say, hey, come please regulate me. And nobody wants to regulate. But if there's something that we can do to provide safety for our people and to address these severe issues around inconvenience in our small towns, We are a state, we are a small state of mostly small towns. We cannot ignore this. So I really appreciate your attention, and I ask that you continue to work with me, work with both sides on this issue, so that we can serve our people best.
Thank you so much. Thank you, Representative Flowers. Thank you, Committee, for your patience. Thank you, gentlemen, for your testimony and professionalism, the way you conducted yourselves. We appreciate that. Oh,
real quick, Mr. Chair. Yes, ma'am. If I could just ask your indulgence. Great. I have with me one of my, I have three interns this semester, two from UAPB and one from Pine Bluff High, and one is here with me. She came right from her class with ROTC, and if I can ask Tony Antoinette Cunning to
please stand. All right. Thank you. All right. Thank you for being here. Once again, thank you for your patience seeing no other business for the committee today. We stand adjourned.
B. Update Regarding the National Electric Vehicle Infrastructure Formula Program (“NEVI Program”) [Exhibit B] - Brad McCaleb, Transportation Planning and Policy Division Head, Department of Transportation
0:41 - 28:4371 segments12 speakers
Brad McCaleb, Division Engineer for Transportation Planning and Policy at RDOT, presented the NEVI program, noting that Arkansas will receive $54.1 million over five years, that the state will not own or operate charging stations, and that owners must provide a 20 % match to federal funds.
[0:51][1:14][1:47][2:19][2:49][3:21][3:53]
He explained that the NEVI plan was approved by the FHWA in September, described the stakeholder groups, public-virtual session, gap-mapping of interstate corridors, and the development of a competitive procurement framework.
[6:38][7:13][7:47][8:25][8:57][9:32][10:05][10:38][11:12][11:46]
C. Update Regarding Interstate 69 - Lorie Tudor, Director, Department of Transportation
28:43 - 48:2848 segments9 speakers
Lorie Tudor, DOT Director, briefed the committee on the I-69 corridor, stating the total project cost is $35-$40 billion, that 900 miles are already operational nationwide, and that Arkansas contains four “independent utility” segments including the Mississippi River crossing.
[29:10][29:44][30:16]
She reported that about 42 miles are currently open in Arkansas, that $4.1 billion is needed for a full build-out, highlighted recent openings such as the Monticello bypass and upcoming groundbreaking, and noted that further segments await funding.
[30:39][30:42][30:51][31:21][32:02]
Tudor also explained that the half-cent sales-tax fund provides $150 million for I-69, with prioritization and public outreach now underway.
[32:02][32:37][33:09]
D. Adoption and Discussion of Interim Study Proposal 2021-112 by Representative Vivian Flowers – To Regulate Length of a Railroad Train Operated on a Main Line or Branch Line; and to Declare an Emergency [Exhibit D1-D4]
48:28 - 33:511 document
Representative Vivian Flowers opened the hearing by introducing the interim study proposal (House Bill 1631) that would limit train length on Arkansas main-line and branch-line tracks to 8,500 feet, emphasizing safety concerns from blocked crossings in small towns and the need for state-level regulation.
[48:37][48:42][49:19][49:50][50:24][50:57][51:40]
Committee members raised questions about possible infrastructure fixes and the proper jurisdiction, with Rep. Johnny Rye asking whether larger sidings would help, Rep. Stan Berry and others stressing that train-length limits are a federal Commerce-Clause issue, and attorney Paul Benham citing the 1945 Supreme Court decision that states cannot restrict interstate train length.
[1:16:30][1:16:52][1:17:10][1:17:25][1:17:57][1:18:31][1:18:59][1:33:06][1:33:38][1:34:19][1:34:54][1:35:32]
E. Discussion Relating to Passenger Train Service in Arkansas
33:51 - 2:04:34260 segments34 speakers
Representative Craig Christiansen introduced Amtrak officials Derek James and Ishmael Cuevas, who outlined Amtrak’s history, current service in Arkansas, and the “Amtrak Connects Us” vision to add 39 new routes, improve 25 existing ones, and seek $17 billion in federal grants for rail projects.
[34:45][35:16][35:47][35:57][36:17][39:32][40:03][40:34][41:08][41:39][42:13][42:45][43:17]
They detailed planned investments of over $12 million for Arkansas station upgrades, a request for state assistance with highway signage to stations, and the possibility of using rural bus funds to connect communities to Amtrak.
[43:50][44:21][44:55][45:26][45:57][46:09][46:15][46:30]
In the Q&A, the chair asked about onboard security, and the presenters explained Amtrak’s police presence, random TSA-style screenings, and background checks for passengers.
[45:57][46:09][46:15][46:30][46:48][47:03][47:16]