Said in CommitteeBeta

Exactly as spoken.

ALC - Executive Subcommittee

October 21, 2026 ·8:30 AM ·Room B, MAC ·15:30
Video Transcript 2 documents

Summary

Machine transcript

May contain errors. Verify important quotations against the official video.

About transcript accuracy
Source
SliQ live captions
Model
SliQ live ASR
Processing date
October 21, 2026

B. Consideration of a Waiver Request for Cooperative Purchasing Construction Services: 11:28

Bailey Cotton, director of facilities for the Huntsville School District, presented a waiver request to exceed the $1 million cap by using partnership funding for two roof replacements, outlining the project scope and the vendor already engaged on hail-damage repairs.

Senators and representatives questioned the bidding process, noting that only two bids were received, confirming the vendor’s prior work under insurance claims, and discussed the proposed TPO membrane roof as a more hail-resistant alternative.

Chair Representative Les D. Eaves called the chamber to order a motion to approve the waiver request, which was moved, seconded, and approved unanimously.

Official video page ↗

Transcript

Transcript available Whisper ✓ SliQ live captions ✓ Download .txt
Machine transcript

May contain errors. Verify important quotations against the official video.

About transcript accuracy
Source
SliQ live captions
Model
SliQ live ASR
Processing date
October 21, 2026
good morning members we're going to call the executive subcommittee to order we only have one item on the agenda it is a waiver request for the Huntsville school district Mr. Cotton, you want to come up you can present your request go ahead and introduce yourself and then you can get on with it. Good morning my name is Bailey
▶ Play
Cotton and I'm with the Huntsville school district and I appreciate you guys convening just to meet for us but I'll try to keep it fairly short and brief. I'm sorry I didn't I'm director of facilities for the Huntsville school district if I didn't say that thank you guys for all that you do and and it's one thing to watch online for years and it's another to actually sit in the hot seat. so I appreciate the opportunity I hope you take it easy on me but we we are seeking a tips waiver request for the 1 million cap we are in the we received foundation or partnership funding to replace a roof at one of our schools that is estimated to be over a million dollars and and we have a vendor that we work with currently and they are actively doing work in our district right now replacing some other roofs that are being replaced under insurance from a hailstorm and they are familiar with our facilities and they have done extensive study on our roof assessments and stuff that was part of the partnership funding process and so we are for those reasons and these companies roofing companies that the next step for the partnership funding is that we need to draw up construction documents and architectural drawings to submit to dese for approval and the roofing company will do that for you but they want to they want to work if they're going to go through the effort to to pay for that and do that for you and so that's kind of the reasons the gist of why we're here today right thank you.embers any questions uhsenator
▶ Play
rRo you recognized thank you appreciate you being here today Mr Cotton. how
▶ Play
many beds does your school request how many
▶ Play
Speaker 15 13:01
bi normally we we will accept three bids how many bids did you get on this on this one we had two and I think a scanned through and they had
▶ Play
done work for you before that's satisfactory in in my home schoolalron had terrible ice flooding and and inhail damage multiple things go on they get fixed and then came again and I don't think of've asking any of the schools that came up up with this same thing do they have some better type stuff they're gonna put on there I mean better or different or improved is what I'm trying to say that that will be some type of resistant to some level of hell well yes the the roofs that are being replaced
▶ Play
under hill are asphalt shingle roofs. This roof is is going to be a TPO roof so it it will have a better protection against that what TPO yeah so it is it is just a instead of asphalt shingles it is basically a a a membrane you know a piece of material that they put over it and so it it will not be affected by hall that's
▶ Play
Speaker 19 14:09
got some extra safety to it that's that's why and
▶ Play
during the entrance for these roofs that we are being that are in the process of being replaced right now we did seek multiple bids through that process as well and yes west and
▶ Play
Speaker 21 14:23
northwest Arkansas had has had their share held we did yes
▶ Play
thank you for being here thank you appreciate
▶ Play
Speaker 24 14:33
the time thank you Senator Representative Brooks thank you Mr. chairir thank you for being here
▶ Play
on the the the prior work that was done so they were the low bid on the prior work that they chose things of that is this this current work or the projected work I guess is that all partnership funding is there any school funds that have been set aside for the work the work that's ongoing is insurance
▶ Play
but the the projected work that we're here for today is partnership funding for two roof replacements thank you Mr Chair. thank youpresentative all right members you've heard
▶ Play
the discussion on this side and we have a motion we have a motion to approve we have a 2nd. 2nd all those in favor say aye oppose the ayes have it and it's approved. thank you for coming down sir. thank you for your time have a good day. yes sir. seeing no other business members we are adjourned
▶ Play

Agenda

A. Call to Order

11:01 - 11:28 1 segment 1 speaker

B. Consideration of a Waiver Request for Cooperative Purchasing Construction Services:

11:28 - 15:19 19 segments 9 speakers 1 document

Bailey Cotton, director of facilities for the Huntsville School District, presented a waiver request to exceed the $1 million cap by using partnership funding for two roof replacements, outlining the project scope and the vendor already engaged on hail-damage repairs.

Senators and representatives questioned the bidding process, noting that only two bids were received, confirming the vendor’s prior work under insurance claims, and discussed the proposed TPO membrane roof as a more hail-resistant alternative.

Chair Representative Les D. Eaves called the chamber to order a motion to approve the waiver request, which was moved, seconded, and approved unanimously.

C. Other Business

15:19 - 25:19

D. Adjournment

Speakers

Representative Les D. Eaves Chair Unverified
3 segments
Bailey Cotton Unverified
10 segments
Senator Terry Rice Unverified
3 segments
Speaker 15
1 segment
Speaker 19
1 segment
Speaker 21
1 segment
Speaker 24
1 segment
Representative Keith Brooks Unverified
1 segment