ALC-Highway Commission Review and Advisory Subcommittee
November 13, 2023·10:00 AM·Room B, MAC·1:03:46
VideoTranscript9 documents
Summary
Machine transcript
May contain errors. Verify important quotations against the official video.
About transcript accuracy
Source
Whisper
Model
ggml-large-v3-turbo.bin
Processing date
October 13, 2026
B. Report of Office of Internal Audit Act 671 of 2023 [Exhibit B] 4:17
Ricky Quattlebaum, Director of the Office of Internal Audit, presented the Act 671 2023 internal-audit report, explaining that the assurance component had verified the status of 85 of 90 RDOT implementation rules while five rules required further testing in the next cycle.
[5:54][6:31][7:08][7:43][8:23][8:56]
He also detailed the consulting component, which reviewed internal-control design for four selected RDOT divisions, produced 88 new-control recommendations, 61 language-clarification recommendations, and identified 166 functional controls missing from the department’s self-assessment.
[12:08][12:42][13:15]
Committee members questioned the scope-specifically noting that procurement functions were not audited-and Quattlebaum recommended eliminating the consulting portion because it duplicated RDOT’s own internal-audit efforts.
[14:51][15:18][15:24][15:28][15:36][15:47][15:58]
A motion to eliminate the consulting component was raised but not voted on, with the committee indicating it would revisit the recommendation at a later meeting.
[16:20][16:31][16:39]
C. Report of Quarterly Land Conveyances [Exhibit C] 17:02
Director Lori Tudor briefed the committee on the first-quarter FY 2024 land-conveyance report required by Act 1315, noting four surplus-property sales that had been deemed unnecessary for future highway use.
[19:59][20:35][21:08][21:35]
Senator John Payton queried a specific transaction in which a 2022 purchase of $595,000 was later appraised at $120,000 after road access was removed, confirming that the same appraiser performed both valuations and that the loss of access accounted for the $474,000 reduction.
[22:02][22:22][22:53][22:56][23:07][23:33][23:59][24:05][24:13]
After the discussion, the committee announced that the land-conveyance report had been reviewed and considered.
[24:36][24:49]
E. Report of September to November 2023 Monthly Updates of the ALC Efficiency Study Recommendations Rules for Implementation [Exhibits E1-E3] 26:58
Director Tudor reported on the September-November 2023 monthly updates to the Guidehouse Efficiency Study recommendations, highlighting the publication of a portfolio-planning rule, execution of the Garver LLC contract, establishment of contractor-performance metrics, launch of a pilot with seven projects, and the rollout of the public “Ask RDOT” portal on October 2 2023.
[27:34][28:10][28:43][29:16]
Committee members raised concerns about public awareness of Ask RDOT, prompting Public Information Officer Dave Parker to outline the department’s use of television, newspaper, and social-media outreach, while Rep. Carol Dalby and Rep. Ron McNair asked for additional communication strategies for South Arkansas and non-social-media audiences, receiving assurances that the communications team would expand outreach.
[33:57][34:17][34:24][47:49][48:20][48:54][49:28][49:31][49:49][50:01][50:10][50:18]
Director Tudor presented the Act 789 (Lundstrom) report, summarizing statewide congestion rankings, crash statistics, and county-level maps that identify the top five crash and fatal-crash locations for each of Arkansas’s 75 counties.
[56:37][57:01][57:37][58:10][58:19][58:27][58:47][59:18]
Committee members inquired whether the data had prompted mitigation actions; staff responded that a dedicated safety team continuously monitors crashes and recommends improvement projects, emphasizing that knowledge of the data is the first step toward action.
[1:00:32][1:00:42][1:00:53][1:00:57]
advisory subcommittee to order. Chair sees a quorum, Senator Johnson, I know you've got to leave early with anything you'd like to say before we get started. Senator Johnson's got another meeting he's got to attend also. Looks like first on the agenda we have report of office internal audit from Ricky Quattlebaum. If you'd like to come forward, introduce yourself and tell
Mr. Chair. So we've just got a short presentation to give you... You might want to pull your mic a little closer. So we have a short presentation to summarize the work that we performed in their annual project review. The first slide, if we get this to work, there we go. The first slide you see, I'm not for sure it's working. Is there someone from staff that can help us get this running? So this slide is simply a timeline of events that have occurred since the passage of Act 298 of 2019, and of course that was the act that required the efficiency study of RDOT that was conducted by Guidehouse. Section 2 of that act required the Office of Internal Audit to prepare an annual project review, with the first report being due by October the 1st, 2021. That was subsequently amended by Act 671 of 2021, which pushed the date for the first presentation to October 1st, 2023. So that's the report you have in front of you today. Then in 2022, because of the broad language in the act, we came before this committee with a proposal that the engagement include both an insurance and a consulting component in which this committee approved. So, as I mentioned, the scope of the engagement is a two-fold scope. It includes an assurance component and a consulting component. The assurance component was to provide an independent assessment of the status of RDOC's implementation of the Guide House recommendations, AND THE CONSULTING COMPONENT WAS A REVIEW OF RDOT'S INTERNAL CONTROL DESIGN FOR A SELECTED NUMBER OF RDOT DIVISIONS, AND IT'S IMPORTANT TO NOTE THAT THIS PART OF THE PROJECT WAS CARRIED OUT IN COLLABORATION WITH RDOT'S INTERNAL AUDIT DIVISION. As you know, RDOT, they have 90 action items that's in the form of rules that they devised in order to implement the 13 guide house recommendations. This slide summarizes the status of that implementation as of May 2023. As you can see, they've made significant progress in implementing their rules. WITH 40 OF THE RULES ALREADY COMPLETE, 31 IN PROGRESS, TWO ONGOING, AND 17 YET TO BE STARTED. TO SUMMARIZE THE ASSURANCE COMPONENT OF THE REVIEW, AGAIN, WE WERE TO REVIEW THE DOCUMENTATION AND PERFORM NECESSARY TESTING IN ORDER TO PROVIDE AN OPINION ON THE ADEQUACY OF RDOT'S implementation of their rules, and our conclusion is that we agree with the reported status on 85 of those 90 rules with testing that's yet to be conducted for five of the rules, and we will conduct testing in the next reporting cycle for those five rules, and those five rules are outlined on page 86 in the report. I think it's important to note that although we concur with the implementation status of the 85 rules, that further testing in future reporting cycles may be necessary to ensure that anticipated results are achieved. For the consulting portion of the engagement, again, we were to review the internal control design for a selected number of divisions within RDOT, and then we compared those controls that we reviewed to the department's 2022 control self-assessment. So a control self-assessment is an exercise that's conducted by management once every two years. It utilizes employee feedback from employees that are entrenched in the business processes of the agency, policy, and then it allows management to review those controls and those activities that's in place to prevent, detect, or mitigate the impact of risks that are identified. And then obviously to implement changes or corrective action plans as needed. You know, internal control, or excuse me, the risk assessment is one of the five components of internal control. SO THE FACT THAT RDOT HAS A FORMALIZED PROCESS FOR REVIEWING THEIR CONTROLS AND THEIR RISKS, I THINK IT SPEAKS A LOT TO THE COMMITMENT THAT RDOT HAS TO A STRONG INTERNAL CONTROL ENVIRONMENT. AND THEY ARE TO BE APPLAUDED FOR SUCH. THIS NEXT SLIDE IS SIMPLY A VIEW OF WHAT THE CONTROL SELF-ASSESSMENT TOOL LOOKS LIKE, AND IT CONTAINS MANY PIECES OF INFORMATION, SUCH AS THE ACTIVITY THAT IS BEING REVIEWED, THE MANAGER RESPONSIBLE FOR THE ACTIVITY, THE SPECIFIC OBJECTIVE THAT IS BEING ANALYZED AND THE RISK TO ACHIEVING THAT OBJECTIVE. AND THEN AT THE BOTTOM, YOU'LL SEE THAT THOSE ARE THE INTERNAL CONTROLS IN PLACE TO PREVENT THE RISK OR TO MITIGATE THE RISK. ALONG WITH THAT, IT INCLUDES THE INDIVIDUALS WITHIN THE AGENCY THAT ARE RESPONSIBLE FOR THOSE CONTROLS. SO ON THE LEFT COLUMN OF THIS SLIDE, YOU CAN SEE THE DIVISIONS THAT WE REVIEWED DURING THIS CYCLE OUT OF THE 26 TOTAL DIVISIONS. WE SELECTED FOUR DIVISIONS AND THEN MULTIPLE SECTIONS WITHIN THOSE DIVISIONS. AND THE SUMMARY OF OUR WORK WAS THAT OBVIOUSLY AGAIN WE WERE TO REVIEW THE INTERNAL CONTROL DESIGN AND IT WAS DONE IN COLLABORATION WITH THE ARDOTS INTERNAL AUDIT TEAM. SO WE PREPARED NARRATIVES AND FLOW CHARTS, COMPARED THEM TO EACH OTHER, MADE SURE WE HAD A COMPLETE UNDERSTANDING OF THE KEY BUSINESS PROCESSES WITHIN THOSE DIVISIONS, THEN WE SUBMITTED THAT INFORMATION BACK TO THE DIVISION MANAGEMENT TO MAKE SURE THAT WE HAD A GOOD UNDERSTANDING OF THEIR BUSINESS PROCESSES. THEN WE WENT IN AND LOOKED AT THE CONTROLS BUILT INTO THOSE BUSINESS PROCESSES AND THEN OBVIOUSLY MADE SOME RECOMMENDATIONS. AND THIS SLIDE SUMMARIZES THE RECOMMENDATIONS THAT WERE MADE. SO OVERALL I'D LIKE TO SAY THAT FOR THOSE divisions we reviewed, RDOT has a really strong internal control design. We did make 88 recommendations for including new controls, new risk, and some corrective action plans and to add those into the control self-assessment. We also made 61 recommendations for just adding clarified language to the control self-assessment OR REORGANIZING CERTAIN RISK CONTROLS TO THE ACTIVITIES THAT IS MORE APPROPRIATE. I THINK MORE IMPORTANT TO NOTE FROM THIS SLIDE IS THAT DURING OUR REVIEW OF THE BUSINESS PROCESSES, WE NOTED 166 CONTROLS THAT WERE IN PLACE AND FUNCTIONING WITHIN THE DEPARTMENT THAT JUST HAD NOT BEEN ADDED TO THE CONTROL SELF-ASSESSMENT. SO WE RECOMMENDED THAT THOSE CONTROLS BE ADDED TO THIS ASSESSMENT SO THAT MANAGEMENT WILL HAVE AN OPPORTUNITY TO EVALUATE those controls when they go in in 2024 and then perform their control self-assessment. And finally, as I mentioned, this portion of the engagement was conducted in collaboration with RDOT's internal audit division. That chief auditor that's responsible for the internal audit division, she's a former employee of the office of internal audit, long-term employee, who has a a wealth of internal control knowledge and specifically the CSA process and the CSA tool. As a matter of fact, she played the lead role in developing the tool that's currently used statewide for the control self-assessment process. And she also has three dedicated staff to administer the control self-assessment process at RDOT on a continual basis. And because of that, we do believe that there's a duplication of efforts between what we performed in our engagement to the continuous implementation of the control self-assessment at RDOT. Therefore we would ask this committee to consider eliminating the consulting component of our engagement for the future project evaluations as we go forward. And that concludes my presentation. I'd be glad to answer any questions, and I've got two members for my staff here who worked on the project, and then there's members from R-DOT. Thank you.
Any questions for members? Representative Springer. Good morning. Thank you, Mr. Chair. So as I understand your report, you didn't look at any of the procurement functions within this division, did you? As far as bidding and that sort of thing? No,
we think it's a duplication of efforts, and it would also allow us to utilize our resources more effectively into just zeroing in on the rules that RDOT is implementing and to try to stay on top of those and, again, do some additional testing as the rules are implemented. The control self-assessment portion is very time-consuming, and you have a very adequate staff at RDOT that's currently performing that on a continual basis. So we just think it's probably a duplication of effort for us to come in behind them. Brandon,
but... Yeah. All right. Thank you. Any other questions from the member? Thank you. Thank you. And I guess you understand, but we will probably take that up when we have more members in the committee. Yes, sir. Thank you. Next up, we have Director Tudor with our report Report of quarterly land conveyances. Do all the members have a copy of the PowerPoint? Director's going to use this, kind of put all this together instead of going through all of it, I think. If you'd like to recognize yourself, tell us who
you are and who you're with. Okay, I'm Lori Tudor, Director of the Arkansas Department of Transportation. I have several staff members here with me today, and I'll call them up to the table if needed to answer questions as we go through. Thank you. Our commission, this meeting was kind of set up at the spur of the moment, and they weren't able to attend today, but they send their regrets. I'm sure they're watching virtually somewhere. So to get started, agenda item number C.
Thank you. He originally had it lined up for him. Yeah. There we go. Well, I think it's a fact that it's not the one that he originally put on there. There's a one that he put on there. What was the original one that he got? Let's
okay okay sorry for that delay agenda item C is the report of land conveyances for the first quarter of state fiscal year 2024 and that is from July 1st through September 30th of 2023. Act 1315 of 1997 requires all state agencies to report any conveyance of state property to the Legislative Council within 30 days when which that of the quarter in which that conveyance occurred. The sale or conveyance of these properties, we follow state law to have to make that happen and in your packet you have a transmittal letter you'll have a transmittal letter to Marty guarantee and then an inner office memorandum that is summarizes the land conveyances during that quarter and then that's followed by minute orders and quick claim deeds that provide the details of that land conveyance so I'll give you a minute there were four sales of surplus property in the last quarter and those those surplus properties were determined not necessary for future highway purposes so with that I'll stop and see if there's
first one no that's what i did i think the one so it was october 27th of 22 yeah and paid 595 000 for it that's correct and now we're saying that the appraised value by two appraisers justifies selling it for 120,000 so what was
the appraisal when we bought it the appraisal when we bought it had access to the road but we bought it and we terminated access with the project so the remainder the remnant has no access and the adjacent property owner wanted to buy it but it has no access to the road what type of road is it I don't know can I ask Kevin Wyatt from our right away division he can answer some of the details just seems like a drastic
property please introduce yourself please for the committee Kevin Wyatt division head of right away division for RDOT Okay, so it's a, what was left, this was part of the Springdale bypass that we were buying right away for the Springdale bypass. The control access eliminated access to this five-acre home site, so it would have no access. We had to buy it out because they had no access. The remainder after the purchase was just assemblage value. In other words, it had no access to a public road, so that was the value that the appraiser put on it at the time that it was purchased.
Yes, sir. Is it the same appraiser that appraised it this time for the 120? Yes, it was the same appraisal. It was the same appraisal. So he felt like the
a report of annual expenditures of funding that was provided by Act 416 of 2019. This revenue to RDOT is specifically dedicated to pavement and bridge preservation projects. We're required to report annually how that I give an account of these funds and the projects that it was spent on So you'll have that report in front of you Just as just to verify what it made up at 416 and the funding comes from three sources Motor fuel tax which equates to 3.2 cents per gallon on gas and six cents per gallon on diesel on-road diesel. There is a annual registration fees on electric vehicles and plug-in hybrids. There's also the casino revenue that makes up this money that is used for these projects. It's about 98 million dollars a year that we receive that we put back into system preservation projects which are bridges in pavements. So in your package you'll see, in your packet you'll see this report at 416 report and at the beginning there's a summary and then there's the list of projects and a statewide map, two statewide maps, actually one of projects that were led to contract and projects that were accomplished by state forces and then in your appendix there is a copy of Act 416 for your review so I'll stop there and see if there's any questions
Okay, agenda item E is our monthly submission of progress being made on implementing the recommendations from the Guidehouse Efficiency Review. You have three reports in your packet, one for September, one for October, and one for November. And to aid in your review of these monthly reports, anything that changes or is added is underlined. So you can quickly see the progress that was made without having to read through the whole report. The the reports are grouped by category and each recommendation under that category and the rules associated with each recommendation and the implementation progress. Some of the more notable changes since the last time we met recommend a recommendation number three under the portfolio planning category was published the status of construction projects and maintenance activities in August the proposed contract with Garver LLC was reviewed by this subcommittee and the contract was executed in September so that work is underway recommendation number six under the procurement category implement construction contractor performance measurements we have identified metrics that define quality and desired performance of the prime contractor seven projects have been selected for a pilot application and the contractors were informed of the process and agreed to participate in this pilot all seven jobs are expected to be completed by spring of 2024 and we'll be able to move forward with these with this contractor performance measurement recommendation and finally recommendation number four under the portfolio planning category was to implement a platform that tracks all stakeholder inquiries to resolution on September 22nd 2023 a coming soon video was posted on our social media platform announcing that a new communication tracking tool would soon be available for public use and a week later it was made official, this system was made officially available to the public. Here is the coming soon video that we that we launched to make the public aware that this new system was coming and we have branded our new system "AskRDOT."
So, following that video, a brief instructional video was put out to the public on October 2nd, the day we launched Ask RDOT to the public. Have you ever wondered
what's the latest on a construction project or how to report a pothole? Maybe you feel there should be better highway signage or that maintenance is needed along an interstate. RDOT has a brand new, streamlined way for you to get in touch with us and ask questions. It's called Ask RDOT. Here's how it works in three easy steps. Go to rdot.gov and click the Contact Us tab. There you'll see a link to the customer service portal known as Ask RDOT. Either log in or create a profile if you're new to the system. We promise this isn't the kind of thing that sends you annoying emails all the time. Having an account allows you to log back in and check the status of your inquiry, ask additional questions, and so on. Choose from a drop-down list of categories. Choosing the right category is important because it will ensure your question is directed to the right person to answer it. It's as easy as that! Once you've submitted your inquiry, you'll get an email confirmation with a reference number, which you can use to monitor the status of your inquiry. RDOT allows you to communicate back and forth as necessary until your question is answered. Serving the citizens of Arkansas is a top priority for RDOT. Our intention with Ask RDOT is to make your customer service experience easy, thorough, and timely. We're here for you. So
we made a QR code so that the public could easily access the site and we've shown this at multiple presentations since its launch in the short time this portal has been operational to the public we've received 275 questions in addition to all our normal emails texts and phone calls we are looking forward to better communications with the public through this new service so with that I'll stop and see if there's any questions on any of the progress we've made so far or the AskRDOT. Yeah, we do have one question. Have one
that's available? Well, we've been pushing it out through our social media, through Facebook, Twitter, on our website. When we go to presentations, so far that's been our strategy. There's not anything on media, I
mean TV, anything like that. It's all social media, which is what most everybody uses, but I didn't know where they would get that information to know to do it.
please. Yes, I'm Dave Parker, public information officer, head of communications. In addition to what the director described, we did probably 12 different television interviews with media from here in the Little Rock area, as well as northwest Arkansas, Jonesboro area. probably a half dozen newspaper interviews, that sort of thing, to get the word out in addition to what she's
not looking, I guess. Senator Chesterfield, you have a question? And good morning, Director Tudor and the other gentleman with whom I'm unfamiliar. Good morning. How are you? I happen to travel these particular roads quite often, 5.30 and 30 for various reasons. Excuse me, Senator Flippo is a distraction. Could you tell me what is going on on 5.30? I'm seeing all of this, the trees and all of this stuff being failed. Does that have anything to do with you? Yes.
ma'am. That is special clearing operation that we do to provide site distance for our signs and also to provide more clear zone for motors that may depart the roadway gives them a more room so we're not going to expand 530
that's not what that's about no ma'am okay well let's get to 30 then going toward hot springs could you tell me when is that going to be finished i mean it's been going on since time immemorial so it's
time yes ma'am uh the current uh estimated completion date is about this time next year that's based on the contractor or the other schedule and information they provided to us so how
think 20 2020 I believe there's a if we go on to the next report we've got a we can look at exactly all the information on that project with is that but
I'm saying do we have clawback clauses so that if the entities do not complete the work in the timeframe they have set do we take money from them do we have that in most of our contracts and and I understand from from director Tudor we didn't have
it in this one yeah well we have what we have is a surety a bond and we pay contractors for work performed but then there's liquidated damages and this disincentive pay if you look on page 19 of your report it's let's get to that the highway construction projects 10 million or more yeah so today we have withheld 12.5 million dollars in payments to that contractor because they're in overtime and that's significant okay and it there is very high on this job because so many people are affected it's a huge amount of traffic that flows through there yeah and so once they went into overtime and that was part of the terms of the contract that we would hold withhold road user costs daily until the project was complete and that's an incentive to get it done as quickly as possible so there's not the clawback is i'm not sure it's not really a clawback it's withhold payment okay so so you're just not going to pay it
going forward rather than taking it back later right all right and i guess i'm concerned because i've been on that road too many times when there are accidents and um as we as we traverse that because my home is in hope and then my interest is in hot springs so i'm always interested in us getting that done any more timely fashion did he say what month in 2024 I think right now
November of 2024 is the month that's on their their critical past schedule that they're required to do and keep updated and um you know actually I live in that area and I you know it is a very it's very frustrating and inconvenient and hopefully what we're hoping for small victories I guess but they have been making a lot better progress lately and we're real hopeful that they're going to get traffic over on new pavement early this coming year and once we can open that up and you don't you're not so constricted through there I think the public will feel better driving through there even though it's not completed yet but we're we're pushing as hard as we can they are making progress they've they've put a lot more resources onto the job we're seeing we're seeing better uh we're seeing a lot more being done quickly so i'll let chad talk a little more about it we've been having bi-weekly meetings with the contractor and the upper management of that contractor and just to make sure that they keep on track thank you we don't anticipate doing business with them again do
have a question. Thank you. I will just echo Director Tudor's comments. We have seen better progress recently and have reasonable hope that the timeline for next November is going to hold. All right. Thank
you a question? Yes, sir. Yes, sir. Thank you, Mr. Chair. Ditto, Senator Chesterfield. I was going to ask the same questions that you presented here today because I'm a member of an organization, and we were on our way to Saline County this weekend, several hundred of us, and they were very confused about the section down there and got really lost. Our meeting was somewhat delayed because of that construction, so I appreciate whatever you all can do in order to make sure that that gets taken care of so that we won't have to experience that kind of ordeal in the future thank you yes ma'am we're
you know i will say that we in the highway construction world you have projects that go really well and then you have those like this one that and and at our dot we we want more than anything to have a successful project so we'll keep working hard to get to the end and finish strong. Thank You Chairman, Director Tudor, good
just comment on highway 72 we had a project up in Centerton we had a lot of accidents we'd seen including deaths up that way and I want to compliment your team for coming out I think we used every sign that you have but it is now completely covered and we have seen no accidents in the last six months and I'm so I'm grateful for that as are the neighbors around so thank you for to you and your team for that I wanted to go back to ask our dot if I could show a couple quick questions when was it launched what type of usage have you seen and are you expecting to see when it's fully implemented and everyone's aware of it and then the last question on that is when you have your meetings where like for a proposed construction of roads you have you're kind of listening meetings that you go are you linking ask our dot to the responses to those meetings as well so that those things are connected so
when we have our public meetings are we showing them where to get to ask our dot if they want to use that form right now we have an online way to put your comments in on a a project that are specific for that project but this is so new I don't know if we're being if when we go to those public meetings if we're doing that as well I don't know if that might confuse the attendees to those meetings because we need them to just be specific about commenting on that project and that project alone and that from that public meeting so we can look into that We launched AskRDOT October 2nd, and since then, in my notes, we've had 275 takers. So that's pretty good. We're still getting the message out. And I will say, when we started an internal beta testing where we just had RDOT employees entering into the system back in, I think, in the spring or early summer, We had 6,000 entries into the system based on those phone calls and texts and things that come in, and then our employees were in turn entering them in. So we were kind of trying to track them, even though the public wasn't entering them in. So I'm going to suggest that we're going to expect about, I don't know, 1,000 inquiries a month into that, because we get a tremendous amount of phone calls, texts, and inquiries to the department over all kinds of different issues. Good. Thank you. You're welcome. Rep. Tandy Rice. Thank
you, Mr. Chairman. Director, Lori, let me ask you this. A couple weeks ago in Jonesboro, we had a meeting which was projected of what was going to be done in the next couple of years along that bypass in Jonesboro, Highway 555. And what we've had in the past, if a person was coming from the Bay-Truman area through there on Red Wolf Boulevard, which would be Highway 1 going south, you had a clear direction on going north because you're coming from the south. But if those folks actually were going to go south, there wasn't a road there for them to cut through on. They had to go across the top and back, and it was a very dangerous area. And during that meeting that we had, I noticed that there was an extra lane that's projected to come in for the south, which would be on the other side of the overpass, and it would be going south. Do you have any idea when the work will begin on that one? On that one, I don't
And I appreciate you. Okay. All right. Thank you. Thank you. Representative Bennington. Thank you, Mr. Chair. Hi, Director Tudor. Thank you for being here. I have a question about I-30. Is it
two well we phase two will happen eventually but we don't have that funded or on the books yet i mean it won't be immediate it'll be as time goes by we'll get through with this see how well the traffic moves and how how long you know at some point in the future but we don't know what point
that'll be okay and when you start doing those negotiations or talks can you please let me know about that of course okay and thank you for your staff for doing the projects and in my district my constituents are really happy about that thank you thank you Mr. Chair
thank you for allowing me to ask a question not being a member of the committee Miss Tudor I always appreciate you and all the things you do in Southwest Arkansas and South Arkansas, but in regard to the AskRDOT, and I went back and asked Mr. Parker just a second ago to ask, you had mentioned you were pushing it out and doing the media, TV, newspaper, and everything, Northwest Arkansas, Northeast Arkansas, and Central Arkansas, and I didn't hear anything about South Arkansas, and I have not seen anything, and you know I always keep up really carefully, and we have a highway Commissioner now from who is my constituent and we're very proud to have him on the commission and and really excited about that but you know not not just South Arkansas or Southwest Arkansas my point being those of us who live on the edges of the state sometimes our news media comes out of state like all of our TV stations are from Shreveport Louisiana and not Arkansas we get no Arkansas television stations our newspaper is a Texas side newspaper and I've sent to Mr. Dudley on different times, Gil back there on different times, TxDOT does a great job putting stuff in our newspaper but we don't get anything from RDOT and and I'm not complaining because I think y'all do a great job and I'm really excited about this ask Arkansas ask RDOT what you're going to do but my one request would be for those of us who live in the edges of the state and maybe we are not so connected to Arkansas I hope that the department will put some emphasis on getting information out to us in the hinterlands of Arkansas we'd appreciate it and and hopefully you have a plan to do that yes
ma'am I'm glad you brought that up and we will definitely make a big effort to make sure everybody is kept informed and we've got a great communications team and I'm glad they're here today to hear this and so we'll keep moving forward and we'll do what you've
asked. Also to us folks that are not really social media savvy, it would probably help if we all would share your social media. I mean, I hadn't thought about it, but to get to our constituents, because like I said, I hadn't, where I live, I hadn't heard anything about
Mr. Chairman. Director, I was wondering if you knew or you could tell me who I should talk to to find out the cost of the new cameras that are being put up on 67167. My district pretty much runs through a large portion of that highway, and I didn't know if you could tell me what that was costing and also what the capabilities are as far as can they be used to, like, read license plates, that type of thing. The cost for
but I'll get it for you. Thank you very much. I appreciate it. Thank you, Mr. Chairman. Thank you, Mr. Chair. Director Tudor, as I move toward the fourth quarter of my tenure here in the legislature, I just want to thank you for your service. Your appointment is historic, and you could have failed to live up to the expectations that we have. but we've gone through studies together. You have responded to those requests and made the changes and I just want to say publicly to you thank you so much for always being responsive to those things that we in the legislature sometimes reasonably or unreasonably expect of you and so as I said is one of those persons moving into the fourth quarter of my tenure here I would be remiss if I I did not just say publicly, thank you so very much. Thank you, Senator.
those comments. Rep. 25. Yeah, thank you, Mr. Chair. Director Tudor, looking on page 19, the Highway 70 Severe Street project, and I appreciate you meeting with us locally on this project, several occasions but looking at this today is it possible it's right now is it 163 days of liquidated damages right now is that
right yeah yeah that's correct isn't it I know it's 12 12 million 12 12 million yes that's that's the liquidated damage not liquidated damages that's road user cost
at at the numbers here is it possible to run out of funding on this project because of liquidated damages well yes okay I noticed the project in my opinion been moving considerably better than it has in the past. As I say, I've told you before that we've driven through there and I could load up every worker out there and put them in my car and carry them with me, you know. But it seems like the project has picked up. And I do know that have they filed for have they filed what's the word I'm looking for I think
switch back and forth Good morning I'm Michelle Davenport, Chief Legal Counsel. That's correct. The Johnson brothers filed a claim mid-summer for approximately $38 million worth of days on this particular project. We have answered that in the absolute negative. And additional information, it is in the discovery phases of that project at the moment, but has not progressed past that. Okay.
has been running one to two years on these particular types of construction claims. If there are delays requested by the other side, it can stretch even further than that. Okay, so the project should be completed by the
You're welcome. Thank you, Mr. Chair. Any other questions from the committee? And if there's nothing else, we'll consider the September through November monthly update report review. Go to exhibit F. Okay, so I think
Did we do that? We must have been sleeping. I don't remember. I thought we were still in the room. I was, okay, well. I think we may have got intertwined in conversation. Do you want to go back to F? Yeah, we need to go back long
you. Now, Exhibit G. Okay, G. All right, so last but not least, this is a really nice report that we do for you guys. It's the Act 789 report. And Act 789 of 2019 was sponsored by Robin Lundstrom, so we call it the Lundstrom Report. And it requires the department to submit a report prior to each regular and fiscal legislative session. So this is prior to your fiscal session this year. And the report is organized. There's a glossary of terms. Then there's a list of the 10 most congested routes in urban areas, 10 most congested routes in rural areas, and then by each county, the five locations with the highest crash rates and the five locations with the highest number of fatal crashes. Then it gives a table on expenditure of highway funds per person, state highway mileage per congressional district, expenditure of highway funds for preservation per congressional district but what's really um interesting for you i think that you'll find interesting is in the appendix in the appendix you'll see a statewide map um this is this is appendix b i mean appendix c is a statewide map that shows all the most congested routes both in the rural and urban areas those 10 routes and rural 10
member to look at thank you go ahead and then following that statewide map we have individual county maps that you can look at and see a an illustration of your five most your five highest crash locations in five highest fatal crash locations which are signified by that red dot those are fatal crashes and so for instance clay county this is an example of clay county you can see the uh the segments of their highest crash rates and then the red dots where the the fatal crashes occurred here's Boone County in honor of the chair we have we show the crash rates in the fatal crashes but all the counties are represented there White County and then Hempstead County but all 75 counties are there with that illustration for you to look at so that will be helpful to you as you look at your district and the roads in your district. So I'll stop there and see if there's any questions. This is very helpful. I know,
I don't know about everybody else, but we get asked that a lot, you know, when something happens. Well, how many accidents have been here in that? So this is very helpful. Do we have any
it just us knowing it? No, yes, ma'am. We have a whole team safety section that monitors crashes across the state, recommends improvement projects. I mean, we are very committed to doing all we can to reduce crashes. So
have to know something before you can fix it, don't you? That's right. That's what I thought. That's what my dad always taught me. Clay County is right up next to Missouri. Leah, these crashes all happened during the last 12 months, right? Or this last year? I believe this is the crash
rates. I don't know. I don't know that answer. If it's just for a year or if it's over the last five years, usually we look at that. So you don't know the time frame? No,
I can find out for you. That's okay. Yeah, it's okay. It's no big deal. I was curious about that because, you know, Missouri has legalized the rate crash to marijuana. And I noticed that the states surrounding Colorado had more, the counties that were bordering Colorado into other states had more fatality crashes. I'm looking
I know the answer now. It was right in front of me. These were crashes in 2022. 2022. This is 2022 crash rates and crash locations, so it's just for one year, 2022.
Seeing no other questions, we will consider Exhibit G reviewed. Any other business to come before the committee? If nothing else, we appreciate everybody for being here today and their questions. We are adjourned.
B. Report of Office of Internal Audit Act 671 of 2023 [Exhibit B]
4:17 - 17:0231 segments10 speakers2 documents
Ricky Quattlebaum, Director of the Office of Internal Audit, presented the Act 671 2023 internal-audit report, explaining that the assurance component had verified the status of 85 of 90 RDOT implementation rules while five rules required further testing in the next cycle.
[5:54][6:31][7:08][7:43][8:23][8:56]
He also detailed the consulting component, which reviewed internal-control design for four selected RDOT divisions, produced 88 new-control recommendations, 61 language-clarification recommendations, and identified 166 functional controls missing from the department’s self-assessment.
[12:08][12:42][13:15]
Committee members questioned the scope-specifically noting that procurement functions were not audited-and Quattlebaum recommended eliminating the consulting portion because it duplicated RDOT’s own internal-audit efforts.
[14:51][15:18][15:24][15:28][15:36][15:47][15:58]
A motion to eliminate the consulting component was raised but not voted on, with the committee indicating it would revisit the recommendation at a later meeting.
[16:20][16:31][16:39]
C. Report of Quarterly Land Conveyances [Exhibit C]
17:02 - 25:0424 segments7 speakers1 document
Director Lori Tudor briefed the committee on the first-quarter FY 2024 land-conveyance report required by Act 1315, noting four surplus-property sales that had been deemed unnecessary for future highway use.
[19:59][20:35][21:08][21:35]
Senator John Payton queried a specific transaction in which a 2022 purchase of $595,000 was later appraised at $120,000 after road access was removed, confirming that the same appraiser performed both valuations and that the loss of access accounted for the $474,000 reduction.
[22:02][22:22][22:53][22:56][23:07][23:33][23:59][24:05][24:13]
After the discussion, the committee announced that the land-conveyance report had been reviewed and considered.
[24:36][24:49]
E. Report of September to November 2023 Monthly Updates of the ALC Efficiency Study Recommendations Rules for Implementation [Exhibits E1-E3]
26:58 - 55:41112 segments18 speakers5 documents
Director Tudor reported on the September-November 2023 monthly updates to the Guidehouse Efficiency Study recommendations, highlighting the publication of a portfolio-planning rule, execution of the Garver LLC contract, establishment of contractor-performance metrics, launch of a pilot with seven projects, and the rollout of the public “Ask RDOT” portal on October 2 2023.
[27:34][28:10][28:43][29:16]
Committee members raised concerns about public awareness of Ask RDOT, prompting Public Information Officer Dave Parker to outline the department’s use of television, newspaper, and social-media outreach, while Rep. Carol Dalby and Rep. Ron McNair asked for additional communication strategies for South Arkansas and non-social-media audiences, receiving assurances that the communications team would expand outreach.
[33:57][34:17][34:24][47:49][48:20][48:54][49:28][49:31][49:49][50:01][50:10][50:18]
F. Report of 2024 1st Quarter Report on the Progress of Each Highway Construction Project of $10 million or More as Required by A.C.A. 27-65-107(a)(19) [Exhibit F]
Director Tudor presented the Act 789 (Lundstrom) report, summarizing statewide congestion rankings, crash statistics, and county-level maps that identify the top five crash and fatal-crash locations for each of Arkansas’s 75 counties.
[56:37][57:01][57:37][58:10][58:19][58:27][58:47][59:18]
Committee members inquired whether the data had prompted mitigation actions; staff responded that a dedicated safety team continuously monitors crashes and recommends improvement projects, emphasizing that knowledge of the data is the first step toward action.
[1:00:32][1:00:42][1:00:53][1:00:57]