Senator Jonathan Dismang introduced the item and turned the floor to Diane Torres-Porter, legislative attorney for the Bureau of Legislative Research, who presented the constitutional and statutory framework for the General Assembly’s oversight authority over the State Highway Commission under Amendment 42, citing case law such as *Pritchett* and *Parkin* and detailing the Assembly’s power to grant or withdraw duties.
[1:12][1:47][2:18][2:26][2:50][3:24][3:54][4:24][4:54]
Torres-Porter then reviewed prior examples of legislative oversight committees-including Act 605 (2009) for the lottery, Act 1258 (2015) and Act 1500 (2013) for the health-insurance marketplace-and explained that the Assembly could similarly create a committee to oversee implementation of transportation recommendations, noting the current statutory exclusion of the Highway Commission that could be amended.
[6:31][7:03][7:33][8:04][8:35]
In the ensuing discussion, Senators Dismang, Chesterfield and others debated the potential composition and scope of such a committee, raising questions about including non-legislator stakeholders, avoiding micromanagement of the Highway Department, and coordinating with existing transportation committees, but no motion or vote was taken, leaving the matter open for further consideration.
[9:11][9:40][9:49][10:10][10:19][10:22][10:29][10:41][11:15][11:30][11:43][11:47][12:17][12:49][13:21][13:43][13:55][14:25]
During the update, Senator Lance Eads moved to add recommendation three (publish construction and maintenance status) to the draft report; the motion was adopted unanimously after no discussion, with the chair recording an “aye” vote.
[15:31][15:43][15:49][16:05]
Eads subsequently moved to add recommendation four (manage all customer inquiries to resolution) which also passed without opposition, and the chair confirmed the additions before proceeding to the next agenda items.
[16:19][16:24][16:35]
D. Expenditures Recommendation No. 7: Implement project and portfolio planning frameworks (Recommendations Report, pp. 35-40) 16:45
The Guidehouse team, represented by Erin Hutchins and Sauger Gokhale, presented Recommendation 7 to implement project and portfolio planning frameworks, outlining five key findings about fragmented project development, construction monitoring, lack of formal change-order review, missing target costs, and immature budgeting tools.
[18:17][18:46][19:19][19:53][20:27]
They projected roughly $3.8 million in annual savings by applying a 10 % efficiency gain-derived from research on project-management maturity-to the department’s five-year average pre-construction and construction monitoring budget of about $38 million.
[23:22][23:52][24:26][24:57][25:29][36:12][36:39][37:10][37:44][38:15][38:19][38:54]
Senator Terry Rice challenged the assumptions behind the $3.8 million figure, prompting Guidehouse to explain that the estimate rests on a 6 % versus 16 % maturity gap identified in a Project Management Institute study and that no specific state-level data were used.
[35:52][36:02][36:12][36:39][37:10][37:44][38:15][38:19][38:54][39:21][39:27]
E. Expenditures Recommendation No. 8: Implement leading practices in construction project design 1:04:23
The consultant presented three key findings: lack of formal protocols for practical design, under-utilization of value engineering, and insufficient evaluation of engineers’ estimates, noting that RDOT completed only 2.2 value-engineering studies per year with $377,000 savings versus a national average of 3.3 studies and $21 million savings.
[1:04:26][1:05:01][1:05:39][1:06:13][1:06:44]
He estimated that formalizing practical-design frameworks could save roughly $660,000 per project (about 13 % of an average $5.1 million contract) and that raising the value-engineering study rate to the national average could increase savings to between $1 million and $16 million annually.
[1:08:20][1:08:53][1:09:26][1:10:02]
F. Report on progress of each highway and construction project of $10,000,000 or more as required by ACA § 27-65-107(a)(19) 1:46:11
Senators clarified that the 40 % cost-saving and $21.5 million figures referenced in the recommendation were drawn from other states (Washington or Wisconsin) rather than Arkansas, and the chair noted there would be no formal presentation on the quarterly report, moving the discussion back to the recommendation.
[1:47:06][1:47:17][1:47:31][1:47:51][1:47:57][1:48:05]
and take their seats we're going to go ahead and get started. Chair sees a quorum. The first item up, and we've talked about this a couple of times, and is a presentation that we're going to have on the oversight authority, the legislative body, and really what that's going to play into is the creation, I think, of what will be an oversight committee on how these items in report are implemented just to be able to keep tabs on what's happening and that sort of thing and so we do have a presentation by the bureau on that and so i'm going to turn it over to miss porter first or torres porter first but if we could what i would like to do is let you know let's pay attention take some notes make sure we fully understand the comments that she's making today in regards to what the limitations are and then at next meeting what i would like to do is be able to have a discussion to start the framework of that and then the following meeting then is where we'll actually hopefully be able to take a vote on some draft recommendations for the report so we're a little ways off this is a big piece of what I think we're tasked with as far as recommendations and it'll take some time to work through but it's something I think we all need to be engaged in. And with that, I will turn it over.
Good afternoon. Diane Torres-Porter, legislative attorney for the Bureau of Legislative Research. And as discussed in the last meeting, today I'll be giving a presentation over the legislative oversight authority of the General Assembly, specifically the authority to create a committee to oversee the implementation of the recommendations that were agreed upon by the Arkansas Department of Transportation. However, as a bureau employer, I cannot speak for or against any course of action that this subcommittee chooses to take based on the information contained in this presentation. Last fall, I gave a presentation on the constitutional and statutory powers and duties of the State Highway Commission and the General Assembly under Amendment 42. Given the topic of today's presentation, I'd like to briefly review those powers and duties. Amendment 42, also known as the Mack Blackwell Amendment, creates the State Highway Commission. for the purpose of administering the Arkansas Department of Transportation and the powers and duties given to the commission for that purpose come from the General Assembly. The commission has been referred to as an independent constitutional agency and as a result there are misconceptions regarding its power and the power of the General Assembly over the committee of the commission, excuse me. However, the underlying language imposed by law means that the powers and duties given to the commission for the administration of the department come from the General Assembly. Can y'all hear me? Is that better? . Oh, okay. Thank you. That does sound better, okay. The constitutional powers and duties granted to the State Highway Commission under Amendment 42 are those necessary to carry out the laws relating to the department. The commission may also employ officers and employees, appoint the director of highways, and provide the director's duties. Changes to these powers and duties would require a constitutional amendment. Under Amendment 42, the General Assembly has the power to grant or withdraw the powers and duties of the commission, the department, and the director of highways. This assertion is also created, it's also supported by case law. In Pritchett, Arkansas Supreme Court held that a separation of powers violation did not occur when the General Assembly abolished the Transportation Safety Agency and the Transportation Regulatory Board and transferred their duties to the commission and the department stating that the General Assembly has the power to control the agency by its ability to grant powers and authorities or to withdraw them. The General Assembly may also delegate its powers and duties to the State Highway Commission as noted in Parkin, where the court found that the delegation of power to the commission to determine the salary or wage deserved by an individual employee is necessary for the orderly and efficient operation of the department. The General Assembly has set out the powers and duties of the Commission under Statute 2765-107, and these powers and duties include the construction and maintenance of the state highway system and the letting of contracts for that purpose, compliance with federal aid programs, creation of budget requests and expenditure programs, and the administration of special programs run by the department. And I'd like to state once again that the General Assembly may add, amend, or remove these powers and duties. powers and duties. The General Assembly has granted the department jurisdiction over various modes of transportation and those laws governing those modes of transportation can be found throughout the Arkansas code. And again, the General Assembly may add, amend, or remove these powers and duties. With the powers and duties of the commission and the General Assembly in mind, I'll now discuss whether the General Assembly can create an oversight committee to oversee the implementation of the recommendations presented to this subcommittee. In Chafin, the Arkansas Supreme Court recognized that the General Assembly has an important oversight role regarding the functions of state government. And an effective way to investigate the performance of state agencies has been by the creation of an oversight group created to focus on a specific subject or entity. The following are examples of oversight committees created by the General Assembly in recent years. Act 605 of 2009 created the lottery and the Arkansas Lottery Commission Legislative Oversight Committee. That committee was created to monitor the implementation and the operation of the lottery. Act 1258 of 2015 repeals the committee and transfers its duties to the Legislative Council. Legislative Council then created the Lottery Oversight Subcommittee and that subcommittee has referred all matters pertaining to expenditures of lottery proceeds, proposed lottery rules, proposed contracts of $25,000 or more, reports pertaining to the lottery and lottery scholarships, and any and all related lottery matters. Act 1500 of 2013 created the Arkansas Health Insurance Marketplace and the Arkansas Health Insurance Marketplace Legislative Oversight Committee. The committee was created to monitor the creation of the Arkansas Health Insurance Marketplace. Identical acts four and five of the first extraordinary session of 2017, transferred oversight of the committee to legislative council. Legislative council created the Arkansas Health Insurance Marketplace Oversight Subcommittee. And that subcommittees referred all matters pertaining to reports relating to the Arkansas Health Insurance Marketplace and any and all related insurance and marketplace matters. That subcommittee reports its recommendations to the legislative council. When discussing the lottery oversight subcommittee earlier, it was stated that the subcommittee may review and approve proposed lottery rules. The authority to review and approve proposed rules comes from amendment 92, which allows the general assembly to provide for the approval of rules by a legislative committee before the rules go into effect. Statute 10.3309 defines the term state agency in order to implement Amendment 92. The statute intentionally excludes the State Highway Commission and Arkansas Department of Transportation, but the General Assembly may amend that definition to include them. As you can see, the General Assembly has created oversight committees to oversee a specific subject or entity, subject or entity, and the General Assembly may do so in this case as well. However, any specific duties granted to a committee created to oversee the implementation of the recommendations agreed to by the department will have to be looked at on a
case-by-case basis. Thank you. Thank you. Any questions? Yeah, just one quick question. And so most of the committees or the oversight committees that we've looked at are just limited to legislator, I guess, membership. Is it possible for us to formulate an oversight committee that includes other stakeholders? So, for instance, general assembly members, some contractor stakes, some consumer representation, highway department representation, that sort of thing to make sure that when we're discussing these, we've got a good representation of what's going on. And I'll turn it back
over. Matthew Miller with Legislative Research. As Diane said, I think in the end it would come down to comparing the duties that you're wanting to the membership. If you were going to do something as substantive as rule approval or something like that, having non-members on there would look differently than if it was just a recommendation function. You know, contract review may be something that you'd rather have all legislators. So it may depend. If it's more of just an umbrella, high-arching review, that might not present concerns. Thank you. Senator Chesterfield,
think, and that's where I was really going with my question I just had was, yes, we do have some oversight in place right now, whether it be through this committee or a transportation committee, and I'm not looking to dilute those, and I don't think we should dilute those in any way. However, what we're looking at is we've got a report that we're going to generate out of this body that hopefully is going to be approved by the legislature in some form and there needs to be a working group that's going to help these items get implemented and again i don't want to drive it i want there to be a full discussion and i would assume that that that group is going to have to have interest from you know various stakeholders again that that's contractors to our actual drivers and consumers on the road to the highway department to the legislative involvement that way we've got a core group and then we don't get going down one road that only benefits one entity or one stakeholder but one that actually you know when we're coming up with these solutions and implementation is helpful to all parties involved well i guess i'm confused
what we're talking about right now is just in regards to the report. And somehow this report is going to have to be implemented. And if it's only by the oversight of this committee, then that is fine, and that may be the direction that we choose. I do think it's important to have a discussion of what that should look like and who follows up on implementation, who's involved in implementation. I mean, I would argue, and we probably saw it play out a little bit in some of the discussion that we had last week, You know, just because there's recommendations doesn't mean that there's a full understanding of what's being requested or what the ultimate direction should be by all the parties involved. We had a good discussion back and forth with the highway director about call centers and those sorts of things last week because really that's not what we were looking for, but that's how she was interpreting it. And so, in a way, to me, this is what does the vehicle look to continue the conversation to make sure that our final report, if adopted, is implemented to the best interest of all parties involved, not just for the highway department and not just for the legislature and not just for a contractor and not just for the consumer, but for everyone involved.
Well, my great concern is micromanaging. At the end of the day, they're the ones who are going to have to implement. and we get to a point sometimes in the legislative process where micromanaging begins to take place. We've got this committee. We've got a transportation committee. You've got a highway commission. And when we formed this subcommittee, it was not stated that it was to determine how everything was to be implemented. It was to make those recommendations as we make them. But there have to be constraints as it relates to money, to staff, all of that. So I guess I'm concerned now that this committee not become the manager of the highway department. And with that, I'll just be quiet. Thank you. Well, and again, that goes back to
what I think my original point was. I don't want this committee to be the manager of the highway department. I believe that there needs to be buy-in from all interested parties is how we move forward. And so making sure that the highway department has their seat at the table as far as implementation and also making sure, for instance, on the personnel issues that you were looking at our last meeting, that you have a seat at that table to make sure that those two things are in unison or as close to unison as they can be. I'm not sure that that's necessarily micromanaging as much as it is, again, making sure that the outcome that we're geared towards and trying to get to is actually achieved and that we're not talking past each other in the conversation of these recommendations because we've already seen that happen a couple of times even in this meeting and just the brief conversations that we've had with the highway department I think they would also agree have been very helpful on oh that's what direction we were looking to go in and we want to be able to continue that conversation and there's nothing mandating that any type of oversight committee be established. And that may not be part of our final report. Again, I do think it's part of the discussion we should be having. That's the reason we, you know, staff actually came up with the limitations of what that should look like, so that we're having a good, solid conversation on moving forward. Do we have any other questions? All right, seeing none, that's going to take us to the update from the previous meeting, so item C. So we had two recommendations from the previous meeting. First recommendation was to publish construction and maintenance status. Do we have any discussion or questions on that recommendation? All right, seeing none. Senator Reeds? There we go.
the draft report. All right. Thank you, Senator. Members, there's been a motion to add a recommendation three to the draft report. Any discussion on the motion? Seeing none, all those in favor signify by saying aye. Aye. All those opposed? All right. It's been added to the draft report. Recommendation four, manage all customer inquiries to resolution. Is there any Any questions or discussion on the recommendation? All right, seeing none, Senator Eads, you're recognized.
well. There's been a recommendation to add, or there's been a motion to add recommendation four to the draft report. Any questions, comments, discussion? Seeing none, all those in favor signify by saying aye. Aye. All those opposed? All right, motion is passed. And that's gonna move us into the additional recommendations by GuideHouse today. Are we all ready to go?
All right, are we ready? Hey, how are y'all? All right, great. Good afternoon. Thank you, Chair. Thanks, members. I'm Erin Hutchins. I am Director with State and Local Government with
Guidehouse as well. All right. You guys are recognized to present recommendation seven, and then we'll allow RDOT to come up and make some comments in regards
to that recommendation. We'll move on to recommendation eight. Thank you. Thanks again, committee members, for having us present to you virtually our recommendations relating to expenditures for RDOT. Our recommendations are focused on portfolio planning and also some concepts in construction design. Sagar is going to walk you through each of those recommendations. Thank you,
Erin. And so before we get to the first uh recommendation we wanted to like with our previous presentations want to ground ourselves first in some of the key findings that led to both of those recommendations we can start with recommendation uh seven and then we'll come back to recommendation eight but as it relates to this recommendation seven which is to implement project and portfolio planning frameworks the key findings that uh you know really led to this particular recommendation there are five of them were that project development construction and maintenance functions you know present you know by themselves you know some unique resource management uh challenges but also when we take a look at them individually from the construction project development side that some of that some of those developed project development processes may be enhanced through formalized project management tools we'll get into some of the evidence in just a second if we take a look at construction monitoring um we also believe that you know existing project management tools the ones that they're using but some other ones that they could implement may have some broader applications for uh construction staff so not only in terms of you know what governs the activities um that that construction monitoring staff uh actually you know conduct out in the field but also within their offices um and so some existing project management tools might might aid that those activities another finding here is that change orders are not formally reviewed currently at least at the time of the review and when we say that we're talking specifically around analyzing them for trends related to change orders for specific contractors and to help evaluate performance potentially looking for consistency around how change orders are you know not only you know potentially a surface but also approved and then taking a look at if there's any trends associated with change orders for any pay quantity items. And then lastly, I think we've talked about this quite a few times that scheduling and evaluation of maintenance activities again may be improved through the use of not only project management tools but also portfolio management tools. And we've heard I think quite a few times that the department is in the process of acquiring a system to help not only with the portfolio planning there but also the project management so some of the supporting evidence as it relates to these findings and we'll talk about this as we get into the recommendations too is that the department uh budgets approximately 40 million dollars per year for some of those project development activities uh and also for construction monitoring but you know mechanisms to to match you know their portfolio of projects in that are identified in the stip with budgets and resources uh to the extent that those exist are homegrown and in some cases are non-existent so to give you an example you know taking the projects and then translating them into the resources and staff being used to actually conduct some of the roadway design activities maybe some of the right-of-way activities those systems are are homegrown as well as the systems then for actually actively monitoring the activities of and the performance of folks they're actually conducting those those activities Also, there aren't any target costs associated with, you know, executing some of those pre-construction and construction monitoring or any maintenance activities. Those target costs don't necessarily exist. So, you know, potentially without that, it's really hard then to identify potential efficiencies without that target existing. And the idea being is to the extent that a project management and portfolio management system exists, then you could potentially identify target costs in those areas and then think about potentially how you can optimize those. So that's an overview of some of the key findings and supporting evidence for recommendation seven. We can talk about that recommendation now and we'll come back a little bit later to some of the key findings and supporting evidence for recommendation eight. i just have to move this a little zoom window around so our uh uh recommendation seven uh as i mentioned before is about implementing project and portfolio planning uh framework so as i mentioned you know the the systems that that exist right now uh are you know very in maturity so the the level to which they're translating their list of projects into actual resource and budget requirements and then actively, you know, the systems that they use to actively manage those activities, you know, vary in maturity between pre-construction, construction, and maintenance. And enhancing those systems may allow the department to more effectively budget, plan, execute, and then ultimately communicate on those construction activities and maintenance projects as well and and we believe uh you know from a directional standpoint that having a more mature project management uh framework may allow the department to realize around you know approximately 3.8 million dollars in in annual savings specifically within the pre-construction uh and construction phases uh of a project and and you know we provide a little bit more detail around how we you know estimated this sort of directional uh savings amount uh in the appendix of this presentation also in the recommendation report but at a high level um you know the the way we kind of you know arrived at this directional number uh was by taking a look at the budget allocated to these these pre-construction activities and these construction monitoring activities that's approximately 38 40 million dollars and then taking a look at some of the leading practices related to potential savings by implementing a more mature project management framework um and identified that there is you know a you know potential um again directional sort of estimate savings at about 10 and so applying that 10 to the actual budget for those activities may yield an approximate savings of about 3.8 million that being said um there are some some considerations here with implementing these types of portfolio and project planning frameworks. One, it's been a required department-wide effort to really unify the different initiatives and assets that they currently have as it relates to portfolio planning and project management. So within pre-construction, they have their own systems. Within construction monitoring, they have their own systems. Maintenance, they have their own systems. And then, frankly, within sort of the administrative branch, there's another set of systems for managing projects. And to the extent that there needs to be some consistency and also a leveraging of resources that already exist, it's going to require department-wide effort. There's also a consideration that, you know, implementing a project management office or a portfolio project management framework will lead to some overhead and, or at least be perceived as leading to some overhead. And there is, you know, some potential overhead there, but ultimately in the long term by implementing such a system and being disciplined about actually utilizing it will lead to some long-term benefits. And then, you know, finally, as with any, you know, significant initiative, there might be some change management that's required and potentially some new IT applications may be required as well. But that really is dependent on the findings from one of the next steps in the implementation roadmap, which we'll talk about in a little bit more detail. And so that implementation roadmap at a very high level is really, you know, centered around four major steps. One, you know, cataloging any existing or in-flight portfolio and project management capabilities and identifying, you know, where the department is right now, where it wants to be, you know, in the future as a target state. So as an example of one of those capabilities, the maintenance management system that the department is looking to procure right now is one of those in-flight capabilities. And it's about identifying potential gaps. So, for example, as it relates to pre-construction resource planning, so taking projects on the STIP and then translating them into needs from a resource and budget standpoint might be a gap that they would want to explore and potentially close. establishing that project management office and governance would be a third step and then ultimately phasing deployment over time developing tools and then training staff and and establishing you know these project management and portfolio planning practices isn't you know isn't necessarily a new activity in fact when we took a look at those comparison group states you know six of them actually utilize project management frameworks or provide some sort of project management training seven of them implement a performance-based maintenance management system you know and then of this uh actually you know beyond the six uh comparison dot's you know caltrans offers probably the most mature project management framework and in the In the bottom right hand, bottom right corner of this particular slide, you'll see a snapshot or a screenshot of their, you know, an overview of their project management framework. And this framework helps them contain their project development pre-construction costs. and and texdot um you know actually has a portfolio management uh system as well where they identify the right portfolio of projects at the right time and make sure you know resources are allocated appropriately given all the competing priorities that you know that department faces and frankly any department of transportation faces and executing on its on its projects and so you know i think one of the the key pieces here in terms of these leading practices is that many of these many of these frameworks already exist and a lot of the supporting infrastructure behind those frameworks also already exist and could potentially be leveraged by the department to the extent that they see value in using that as they're developing but you know potentially developing their own framework and to give an example of that you know Virginia and North Carolina for example have sample templates on their website they're publicly available they make them available to the staff within those departments. And they're both broken down even to sort of the, you know, the very, you know, sort of baseline set of activities for, you know, any one of the, you know, subset of activities in, you know, pre-construction and design. They provide these ready-made templates that people can kind of take off the shelf and customize for their own projects. So a lot of resources already exist that could be leveraged, which would shorten potentially the time it takes to implement this framework. And speaking of which, getting into the implementation roadmap in a little bit more detail, kind of identify this at the high level, at the highest level. But the first step here again would be to catalog those existing portfolio and project management capabilities and identify what that target state could look like. So the first part is really just doing a true catalog of what they currently have in place from a project management and portfolio management standpoint. So, for example, in their IT department, potentially they're building out project management tools and frameworks. They're looking to implement a maintenance or procure a maintenance management system as an in-flight initiative. Within construction, they already have a homegrown and they're looking to revise and update it, but a tool that allows them to project resources for their uh for their construction monitoring staff and and once that catalog's been built then it's really conducting that landscape review of what other dots for example uh are using uh from a project management standpoint but you know you can go certainly go beyond you know what other dots are using but you know frankly you know uh what other dots are using might have hold the greatest relevance um and also the greatest set of tools that the department could potentially um you know leverage to shorten the implementation timeline so they could take a look at wisconsin for example they can take a look at virginia as i mentioned north carolina there are a fair amount of frameworks that already caltrans for example and then from that point it's really identifying those gaps uh in the system and it provided you know some some examples a little bit earlier but also here in this second step so from a pre-construction standpoint is it you know resource and budget planning as it relates to the specific projects that are coming down the pipeline and then specific project management frameworks not only for pre-construction and monitoring those activities all the way through letting of those projects but then on the other side when you get to construction monitoring and then from a maintenance standpoint i think as we talked about potential gaps that exist are actual portfolio planning so determining you know the the level of service targets that they want to hit for the system features then understanding you know what budgets they have available to achieve those potential any potential targets that they identify and then identifying the projects from there and then again it's also resource and budget planning and then project management once those projects have actually been been determined from there potentially creating a project management office or a pmo that essentially will will oversee the design and implementation of any portfolio management and project management frameworks across the department you know specifically in pre-construction construction and maintenance and again you know leveraging you know already existing assets uh in that in that particular uh endeavor so at the time that we were conducting uh this review is our understanding that The IT department potentially was building out a PMO. And so how could that potentially be leveraged? Also, for example, Garver, who is one of the consultants that works directly with the department, provides some targeted project management support. So how could that resource potentially be leveraged again to help with building out this PMO, you know, to the extent that the department adopts this particular recommendation? um but but you know they could potentially again leverage that resource to help you know build that out and having building a
pmo sorry soccer just really quickly building a pmo office doesn't necessarily mean standing up a whole new office and practice and hiring a bunch of people that the department doesn't already have it's really a matter of you know again going back and reorganizing those assets and processes and procedures and when we talk about assets we also mean personnel assets as well. So just really re-evaluating the way in which you structure your resources to have that PMO capability. Thanks, Sarah.
And then the last step there is really phasing deployment to ensure that you can actually implement this over time because to be able to implement this across the entire department is going to take a fair amount of time. And And so phasing it would be helpful. And the first step there, obviously, is prioritizing the deployment. So as an example, project management frameworks might be first phased in at the pre-construction stage and for monitoring construction activities. A second priority could be identifying level of service for maintenance activities and then creating a portfolio planning framework instructor around that. those could be immediate priorities and then the department could potentially move on to other things but again those are those are examples of of what the department could potentially prioritize and then it's really developing those standards and tool sets and formalizing standards and tool sets for project management and portfolio planning and then formalizing the reporting around that and and specifically against you know progress against activities which also would help with some of the customer service recommendations that we had made previously in terms of being able to streamline the acquisition of that information and dissemination of that information at the same time, but also developing standards and tool sets around risk issue management and any change control procedures that might need to happen with those activities. And then at the same time, then being able to train staff members and deploying resources so that ultimately those portfolio planning practices um and portfolio and project management practices are disseminated and then actually implemented uh throughout the department and actually yields the benefits and the values that those you know tool sets and those frameworks are intended to deliver so with that i think we've kind of talked through this particular recommendation and the potential roadmap and and i think we'll turn
questions senator rice you recognize for question thank you could you go over your assumption on the 3.82 million you know like you just mentioned 3.8 million in annual savings how you arrived at that what calculation yeah give me just a second and i can actually navigate
down to our some our appendix where we detail this in a little bit more detail so give me just one second there we go so the first thing that we did was try and articulate and identify what the department's actual budget was as it relates to their costs for pre-construction and construction engineering and right-of-way and utilities and so on and so forth, what their budgets were over fiscal year 2015 to fiscal year 2019. And so we found that the five-year average was approximately $38 million, which is identified right down here. And then, again, based on our review of the department, we made assumption again taking a look at their existing project management tools and frameworks that they had in place um and and made you know sort of a subjective uh you know estimate and and evaluation of where they could be on sort of the maturity uh from a project management standpoint and some of the existing research um and public research that we have found which is identified up here and also referenced in our report, identifies that, you know, an organization with a less mature project management platform, and we would consider, again, based on our review and the tools that the department has as it relates to project management, that the department would have a less mature platform. And an organization that has a less mature platform would realize about a six percent savings per project this is
is that not correct yeah and i'm going to get to the the 10 in just a second however that same research indicates that an organization with an average level of maturity as it relates to project management so potentially a place that rdot could get to saves approximately 16 per project so the difference between that six percent and that sixteen percent is that ten percent so if you take that ten percent then and apply it to the department's budget from a pre-construction you know project design standpoint and that ten percent applied to that 38 million yields approximately a 3.8 million dollar savings
okay and can you name the states that you take your analytical data from that shows that is they have had actual savings of those percentages that you're talking
about our yeah this this doesn't reference any specific state it's it's using a report from particular project management institute and research foundation it isn't a comparative to other states sounds pretty subjective
I should have done it before they came on I would like for the committee to have a updated report of the expenses of the contract overview to date for the next committee meeting of good thank you
will do do we have any other questions all right at this point then we'll ask the highway department to come up and I think they have some comments in regards to recommendation number seven.
Good afternoon everyone. Let me be clear right up front RDOT has a project management framework I promise you that and although Godhouse did not mention it in their in their presentation just now in their findings report back dated March they acknowledge that our dot consistently is able to execute on project development construction and maintenance functions we agree that our systems may not be as sophisticated as others, but they work. RDOT right now we don't have what we call a project management office, but we have people in place that are taking care of those functions. We have a program management division that takes care of the STIP, monitoring the STIP, making sure we spend our federal aid every year, and I'll get into that just a little bit if you'll give me them if you'll give me that a you know privilege we get federal funds every year that we must obligate or will lose them so every year the federal highway says okay Arkansas you get this much money if you don't obligate those funds for construction projects if you don't get those projects ready we're going to take that back and give it to other states so we're under time we're under we're under so many pressures about getting these projects ready and we have to manage our time our money and our projects there's no way around it okay so the majority of these funds that we use from federal highway are for construction and every year for the last for I mean I have been in the department for 36 years and I have been involved with project development and I I will tell you, we have never sent a dollar back to Washington. We have always spent every dollar given to us to the best of our, I mean, we've always done it. There's no, there was no, there was no discussion about it. It's what we're going to do, right? I mean, we're never going to hit the paper and say, Arkansas does not, loses $10 million, loses $50 million. No, that's not going to happen. We're going to make sure it doesn't happen. And let me tell you how much even, we go even further. year states and programs that aren't obligated goes into a big pot of money and it's called August redistribution and not only do we make sure that our projects are developed to spend the money they give us we make sure we have enough projects on the shelf so that we can ask for as much of that money as possible which is gravy it's extra money for the state of Arkansas and since 2000 I had him run me the numbers this morning since 2000 over the last 20 years we've been in a position to ask for additional federal funds in the tune of four hundred and twenty four million dollars over the last twenty years we have gotten four hundred and twenty four million dollars additional for the state of Arkansas because we manage our projects and it really it's really hard to sit and listen to this kind of presentation where they make it sound like you know we don't know what we're doing we know what we're doing I promise you you can trust your highway department that we're taking care of the money and we're getting the projects out there and we're not letting any money go to waste or go back to the federal government okay they mentioned california and texas arkansas has an annual construction budget not counting the half cent sales tax okay don't think about that because i'll get to that in a a minute. But we have an annual construction budget of $440 million. Now that sounds like a lot of money, doesn't it? Guess what California's is? $6 billion. Guess what Texas's is? $5 billion. Of course they need formal, sophisticated project management bells and whistles because they have a heck of a lot more at stake as far as getting a certain number of projects ready. But we can take care of what we're doing the way we're doing it and we do a good job with it with our 440 million when the housing sales tax passed we realized we were under that we were determined that we were going to deliver the promises we made there were 31 projects for two billion dollars over 271 miles I believe is the number 170 miles pardon me so we knew that we you know we didn't have the staff and this was a temporary tax so we hired a consultant to set up a project management office to make sure that we delivered what we promised and i'm happy to say here today that we have we will exceed our promises because by the end of 2021 we'll have every project under construction or completed which is far in advance of the gene 2023 with which we promised so as you can see when we need that extra expertise, when we need extra staff to help us to manage a big program, we bring that in. I mean, we're not sitting up there not delivering what we promised that we're going to do. And I just want you to know that we, I mean, everything up to now has been gravy. It's all been great stuff, and it's going to be better. We're going to measure things, and we're going to have a better website, and we're going to have all that, and that's going to be great. But now we're getting into meat and potatoes. This is what we do this is our main goal is to deliver projects and yes there's always room for improvement and yes we we we embrace continual improvement but I want you to know we do a good job with this
so I just want to make sure I understand where we are in this conversation right now so are you because when I looked at the written response we talked about the establishment of a PMO and maybe being a realistic opportunity, in particular if Issue 1 is approved. Exactly. If Issue 1
what I was understanding a minute ago was already something you have in place would not need to be established. But you're saying if Issue 1 is approved, then this may be a valuable thing for the department to establish or set up. I'm a little bit confused on the posture. And then the other part would be at the end here on the maintenance management system. Again, if I read this paragraph, you're in agreement. with the mms recommendation but then what i'm hearing from you right now is is that you know we're doing it great we're not changing anything so i'm just trying to understand the posture of where we are and we're fixing to go with the conversation because i i when i read this i did
not anticipate this i guess the posture is i listen to god house and their recommendations and how we can everything that we can do better and we can but they never mention what we're doing right but
that they but they did actually in the big report we're at the recommendations part they wouldn't they would not in their recommendations tell you to do things that you're already doing right that wouldn't be a recommendation that was in the report so i i don't i don't want you to take offense because again that i think that gets us in the in the wrong direction what we're here to do is to look at these recommendations and if these recommendations can be helpful which you indicated in your written response they could be, then those are things we need to look at. I don't want to argue about something we should have argued about a few months ago, which was you disagreed with the report or or whatever some of the findings in the report. I think we've already done that. I don't want to spend our time here in this committee doing that. I want to talk about these two recommendations and if these things are going to be value for the department, not we don't like the way the guide house made a presentation today if that's possible i want to i want to look at the
recommendations i'm looking at the recommendations and while there's value in them i want to make sure the committee knows at some point that we are taking care of our business and we ought we do project management we do have a project management framework from this recommendation in the presentation it sounds like we have we don't have that in any in any real form when i think that's where it's
good to actually let's let's have the conversation about that we i think from what i'm hearing from you there are places that it can be improved the the processes that are in place right now and when I read the letter that's what I read and then so how do we improve that and Godhouse was very careful to say over and over again in their research their findings what they saw this is what they saw and so I think they were trying to give you some leeway in that to be able to to you know talk about what you have in place but I don't want us to take a posture where wherever this was fixing to go with that I'm I'm gonna go ahead and turn it over to Senator Rice we'll get back to the response
okay and that's where I was if issue one passes and we do have a new cap to set of congestion and capital relief congestion relief and capital projects major projects that take special effort to guide them through the system then possibly it would be a good thing to look at restructuring how some of our offices work but at this point it's it's a in our opinion it's not it's a waste of taxpayer dollars but issue one hasn't passed yet we're where we are is where we're at today right so this is where I I am as far as defending the department in this regard. Now as far as we keep going back to the maintenance activities. It's well documented that we're trying, we're getting a consultant on board by the end of the year to develop a new maintenance management system that will have all this functionality that they keep thinking that we need and that's been documented so I won't get into that anymore because we're doing that we were in flight of doing that when they went through the review so with that i'll conclude my comments thank
thank you i i'd just like to bring the committee along with me and i say this many times my simple mind but i find out sometimes i'm not the only one that's that way uh and i i commented previously i appreciate guide houses work but one thing i want to point out is some of the things they're presenting to us if you'll hear that they keep saying the highway department is has a program they're they're starting to do that now i can go into any business and find out your good stuff and put it down on paper and say you know here's an idea for you do yeah you're already doing working towards that and and that's some of the stuff we're hearing and i don't expect as the chair says to point out maybe all the good stuff but when i'm turned down a road a lot of times i kind of like to know what's down at the end of that road and as we've gone along with these committee meetings as i've learned that the the term task force or special committee uh it red flags to me what is at the end of what we're doing i want all this good stuff for efficiency and and the things that count but you got to look at the real stuff when you're looking at california and texas has just been said with a five and six billion dollar uh outlay versus what arkansas is doing it's not apples per apples and you can't expect to have the same kind of program you've got to do what makes sense one thing i would like to know mr chair is and you may say it's just up to the termination this committee and that's when i'm speaking to the the committee get in your head what you're fixing to do we know task force gets stacked who's going to pump the task force who's going to do this or do that I don't want us to have as my colleague Senator Chesterfield says micromanaging I do want the highway department to understand there needs to be oversight for taxpayer dollars that's what this committee is doing the transportation committee also does it so I have concern if anybody has an end result that I hadn't figured out yet I want the committee to be mindful of all this as we're going down through this and I'm welcome to stay as long and go as many committee meetings as need to but I'm seeing some concern of some of the terms and language that's used in the report and it does make our highway department to me seem like they're not doing some stuff that I think they're doing thank you thank you
and in one comment on the MMS program that's in flight I mean that that was brought to us by God house they acknowledged there was some very there were some items that were in their efficient their infancy had just began and one of the reasons they make it into the report is because that's great but we also want to make sure that it's followed through with and so if we didn't have it as a part of a flag recommendation if it wasn't brought out by a guide house we wouldn't know it was happening even in an infancy stage at the department and I think it's important that we get to know and follow along and watch it come to you know its conclusion. To me that MMS system is one of the most important components we have and of the more important things I think that you're doing right now in regards to what the legislature has been asking for for several years since the initial general revenue transfer and so I'm glad that it's it's happening I'm glad that it's on track and that we're moving forward but that's that's why something like that makes it into the report Senator or Representative
Davis you're recognized all right thank you Mr. Chairman uh Director Tudor I I thought I debated whether and I'd say anything and I thought it might be to your benefit to just kind of hear how some of this hits us when we hear it. So I don't hear Guidehouse saying that you don't have a project management system. The word they used was immature, I think, and to me all that means is it probably hasn't been updated in a while. It probably could have some expanded or additional components to it, I would encourage you to not be as defensive about that and consider more the metrics that we're using in our project management system. For instance, you spoke repeatedly about making sure we spent all of the federal dollars. I don't have any doubt we can spend all the money but are we doing it in a performance-based manner what are the metrics that we're using in our project management system to determine if they're being managed to the best of our ability whether that's efficiency do we get the most for our dollar that we can not just did we spend it all but what product did we get for the dollar does that make sense so that's what I'm hearing I'm hearing that sure we have a project management system but does it look at the right things are we measuring it based on the best using the best metrics are we getting the most for our dollar that we can and the last thing I would say and this is kind of a personal I'm gonna get on a little bitty soapbox but I don't want to hear that we can't do what California and Texas do our budget smaller but we can be as good as them or better on a scale that fits our budget you know our budget smaller our state's smaller I know you're gonna say we have more highway miles I've heard it a million times but I don't want to hear that we can't do what they can't do what they what they are doing we can do it at least as good as they are we can do it better thank you any
but I would say that I think all this talk about an oversight task force ensuring that we're doing certain things is part of the reason I want to make sure that you understand the rest of the story behind some of these recommendations. Absolutely and I guess one thing
I want to back up and say when we're talking about oversight in my opinion and this committee may not agree with me it's a working group it's it's a it's the same working group that we talked about last committee where you know Senator Chesterfield said she would love to have a conversation with you about personnel and other members have said that they would love to be a part of that conversation it isn't the implementation function but it's to make sure that everybody's on the same page as we're moving forward as the highway department is progressing clearly some of these items are going to have some expense tied to them well because there's an expense tied to them the legislature has to be involved in that conversation too so we can call it whatever you want but and again this whole committee may disagree with me but when I talk about oversight or whatever it may be it's making sure that we are all on the same page as we build this roadmap on out and that is also the time and place in that working group for us to take a look at what you're doing with MMS and make sure that it kind of we're all on the same page of what that means what it's going to look like ultimately and that it is going to get us to the place that we want to be it but again one of the reasons that I wanted us to start the conversation without taking any action for now it'll be two weeks this will be the fourth week actually in the end is because I believe however that structure whatever that looks like is is important and it may just be as simple as this committee again that's a discussion that we need to have as members and one we have start now because I think it's it is a complicated discussion so with that Senator Chesterfield you recognized thank you
mr. chair when we began this process some time ago one of the things that I emphasized was that the report would also provide us those things that this department does well and what I find concerning is I don't see that in the report. And I think many of you may have remembered. Now, if we find something that our department is doing well, let us tell them. State employees do a tremendous job. I think they're overworked, underpaid, and underappreciated, quite frankly. I have no problem in entering into a conversation about what I think should be an objective criteria for rating those employees who rely on that merit system i don't have a problem with that but i do have a problem with the fact that we don't seem to be giving any positive feedback you know you can begin to feel like you're just being beaten up by everything you're doing wrong and you don't get an opportunity to have anybody say to you but we appreciate what you did right and that's what i guess miss chair that's what's troubling me about it it seems and that may not be the intent but i remember very well at the beginning of this process saying to Godhouse, please tell us what our folks are doing well. And I have yet to hear that from them as to what that might be. And that's why I assume she is fighting back. I'd be fighting back too if I felt like everything I was doing is being underappreciated, not simply unappreciated, but underappreciated. I'll say it that way. And I failed to see that in this report. And so that's my concern about it is what have we been doing right because we've got highways that continue to go up, and our highway system looks pretty daggum good when we have the construction. Is it perfect? No. Nothing is. And so I think that's my concern about this whole report is there is no this you can do better, this you're doing very well. And in reports, I just anticipate sometimes that that might happen.
who is that? All right, Senator Johnson, you're recognized. Lori, whenever we met, you were in the planning department, right? That's correct. so whenever guide house says the planning design construction activities of rdot is homegrown or non-existent would you have a background to know whether rdot has a has a has these components we definitely do okay were you the head of that planning department after after that i was the assistant chief engineer
for planning for many years all right i came back from school and i went to the planning department i spent most of my career in the planning side of things so i know if there's one thing i know it's planning and i know that we have had continual work at improving our planning process
all these years Okay, I appreciated that, but I just wanted the members to know that if you were defensive, then it's for good reason, because that was where your heart lies from the time you became an engineer, so thank you, Lori. It is, and I
They do a good job. Understood, and I appreciate your efforts. And I think you will agree with all of us that we can always do better, and we're always going up that ladder. And we're just part of that effort. Thank you, Lori. That's right. Thank you. Thanks,
All right. so hopefully i think my screen refreshed here and we're back at our finding and so we're going to discuss recommendation eight and that is centered around excuse me implementing some leading practices as it relates to construction project design and there were you know three key findings here that really led to this particular recommendation the first one being you know some formal protocols around the use of practical design at least at the time of our review appear to be lacking and just at a high level practical design is really approach around you know construction project design that that's supposed to you know still achieve the objectives of the particular project but optimize that design and potentially find ways of of lowering the cost the second finding is that the department has not taken advantage of the full benefits of value engineering and and you know value engineering is at some level the other side of the coin here and And again, at a high level, it's really a tool to analyze projects and identify some opportunities in that pre-construction phase, but to identify opportunities to potentially reduce cost or even accelerate the schedule. And again, RDOT is implementing value engineering, but again, based on our review, not taking full advantage of that. And then the last finding is that, you know, engineers estimates are not necessarily formally evaluated to identify any future design cost efficiencies. And so some of the supporting evidence there is that, you know, again, even though the department is using an iteration of practical design, at least during our review, there was, you know, sort of an absence of formal documentation. And as a result of that, you know, again, from the standpoint or perspective of our review, ARDOT was unable to show some of the cost savings and sustain some of that critical knowledge management without that formal documentation being in place. As it relates to value engineering, the department does, again, from our review, it did complete 2.2 on average value engineering studies per year and realized the cost savings of about $377,000 since fiscal year 2015. However, that is below the national average. The national average from the data we were taking a look at was about 3.3 value engineering studies per year and approximate savings of about $21 million, which represents about about a 5% savings on a per project basis, whereas RDOT yields about a 0.7% savings. And then finally, as it relates to helping to optimize some of that construction project design work, you know, from our perspective, we understood that the department wasn't necessarily, for example, reviewing change orders that were directly tied to plan emissions and errors, then to be able to sort of translate that back into feedback and potentially update certain aspects of that project design process. And what we saw from the change order data was that there was about $3.1 million on average per year in change orders that were tied directly to plan omissions and errors. So moving on to the recommendation itself. And the recommendation being implementing some of these leading practices are really furthering the implementation of these leading practices. And we recognize that RDOT is implementing, to a certain extent, these project design practices. Some of the lack of formal frameworks to ensure consistent use potentially means that they could be, you know, not realizing the sort of full value of some of those practices. And, you know, by having formal frameworks, they could strengthen some of the institutional knowledge and improve some achievement of any specific system targets that they have around project costs, for example. So our anticipated impact, and again, these are directional, is by adopting a formal framework for practical design, the department could save from a directional standpoint, about $660,000 per project. And this was based on Missouri, for example, saving about 13% in their first year. And the average contract from 2014 to 2019 for RDA was about $5.1 million. And so applying that 13% estimate there would yield about a $660,000 savings. And we're not necessarily saying that the department isn't necessarily realizing some or all of that right now but without that formal documentation and and capturing of the potential cost savings it it's hard to understand whether they are actually yielding a you know cost savings at that level or potentially even beyond it and then as it relates to value engineering uh savings we we you know estimate and again this is directional that the department can save somewhere between one and about $16 million by moving their value engineering process up to potentially where the national average is. So right now where they're at, excluding 2019, there are about 1.75 value engineering studies per year. They bump that up to 3.3. Or if they were able to yield a cost savings rate increase from 0.7 percent to you know five percent or if they did both they could yield somewhere in that region in terms of potential value engineering um savings again there are some considerations here you know not uh not all projects are well suited uh for these approaches so obviously requires some sort of judicious you know application but that's where the formal documentation will play a considerable role. And the recommendation won't necessarily require the creation of new sort of technical practices, but will require at some level formalizing them and potentially expanding them. Right now, as an example of that, value engineering studies are required by the Federal Highway Administration for projects that are greater than 50 million dollars but anything involved with a that involves a bridge for example that threshold is down to 40 million dollars however that's just a federal highway administration requirement that practice could potentially be expanded you know beyond those thresholds if the department so chooses in terms of the implementation roadmap at a high level it's got three you know major steps you know develop those formal frameworks around the formal around the use of, you know, performance-based practical design, potentially conduct value engineering earlier in the design process and potentially more often, and then, you know, evaluate, you know, what that gap is between the original bid amount on a contract and final payment to maybe identify, you know, if there are potential ways to shift the pre-construction project design phase to potentially mitigate some of those change orders and those costs that are sort of felt you know down the road during the construction process. We've talked a little bit about some of the national practices around value engineering in terms of the number of studies so the 3.3 and savings close to 22 million and then we've talked a little bit about you know the different states that you know have realized savings and frankly been able to actually you know capture and then communicate what the savings are by adopting you know formal practical design protocols spending a little bit more time on the on the implementation roadmap again you know as i mentioned earlier uh this isn't necessarily going to require that the department creates you know technical uh you know sort of technical frameworks around it it's really about you know building upon and expanding what the department's already doing so formally those right
so that first part then is, you know, really developing those frameworks. And so, you know, really determining what are the methodologies, what's the timing, what's the frequency for the use of practical design, for the use of value engineering, and then the timing around when, you know, if and when engineers estimates are gonna be compared to final cost to, again, identify those areas in which the pre-construction project development phase could be further refined to yield some cost savings. Federal Highway Administration obviously provides some guidance on that, but again, there's a fair amount that already exists through other DOTs. And then in the second step is really tracking those outcomes and reviewing the trends. So actually conducting the analyses to understand truly capture what are the benefits what are the cost savings what's the return on investment uh from implementing these frameworks like you know practical design value engineering um and then again uh identifying any trends from the the change order data so as an example taking a look at project types that might you know or most likely result in the greatest you know uh level like not only you know volume but also actual magnitude of of change orders due to plan error or admission or even you know the types of projects that potentially have exceeded their timelines or even project types that would benefit from certain you know design solutions so there are some areas in which the you know those that change order information uh and that final contract information could be mined to identify um some some efficiencies within the project development pre-construction phase and then the last piece is just continuing to monitor the implementation of these different policies and then again based on the actual data that's being generated come back and determine if there needs to be any revision either to how they monitor it or revisions to the policies and procedures themselves and then ultimately to the extent that a revision or to a policy or procedure or the way they're monitoring the implementation of these policies and procedures is justified, then actually implementing those revisions and then going through that cycle again. And so with that, I think we can turn it over as we've kind of concluded our discussion here at the roadmap and the recommendation. All right. Thank you. Just one
quick question. I want to make sure I understand, and I think you covered it pretty well in your notes, but it's not that these processes may not be in place. They're just not formalized right now. So it's hard to track to see what's actually materializing because of the processes is that is that fair or could be fair we just won't know until it's formalized so you can actually have something to fall back to to track that's
going to say on the practical design again at the time of our review um i think there was probably the greatest i don't want to say need but um there was just a true you know absence of formal documentation around the use and implementation of you know that particular practice with value engineering um we understood in our review that there is a process in place people have been trained um i think the the potential area for improvement then is expanding the use and also potentially accelerating the timing at which those value engineering studies are conducted to allow greater opportunity for
help clarify? Yes, sir. And answer your question? Yes, ma'am. Representative Davis, you recognized? Thank you, Mr. Chairman. My question is for the consultant. Two questions, really, or one question, one clarification. The question is, can you expand on sort of a definition for practical design is this a formal industry recognized design methodology or is this I'm not familiar with the term I'm a civil engineer to be fair and I'm not familiar with the term so I'm curious you capitalize it in one place so I'm wondering if this is some standard methodology that you're referring to and if not can you be more specific about what you're looking
for when you say practical design so I've it's our understanding that this isn't necessarily a standard approach that uh you know is adopted in exactly the same way from dot to dot every single dot that adopts a this what i would term more of a practical design approach has their own sort of version or iteration of this particular approach and again it's it's supposed to sort of at the front end again from our understanding help the department you know optimize that design procedure still yield those objectives but find ways to potentially reduce cost through the design process so if you go to another dot they might have a different iteration of what this this potentially looks like but it is something that is again from what we understand is an approach that requires some you know exceptions from you know the standard federal highway administration uh design guidelines but they are ultimately approved by the federal highway administration and so they are acceptable so there is some sort of there is
some sort of underlying or base uh methodology considered practical design but obviously every state or every department's going to have their own unique uh you know take on what that looks like probably obviously catered towards their state It doesn't necessarily follow the federal highway standards to a T. Does that make sense? I don't
think it does. You look confused. Yeah, I think you were essentially recapping what Sager was saying, which is that many states have implemented a practical design capability, and each state has some sort of flavor of their own for the thing that you go through a process of reviewing with the federal highway administration uh to get approval to use that that takes those capabilities on project
okay and then clarification if you don't mind on specifically on value engineering we're doing value engineering we're using value engineering but perhaps we're not documenting it to an extent where we can you know formally go back and add up what sort of savings we saw from that and you're suggesting that perhaps we could optimize savings by moving up the timeline of when we implement value engineering in the design process. Is that, am I following
you right? Yeah. So just to clarify there a little bit, you know, the documentation exists and staff are trained within the department for, you know, to conduct value engineering studies. But again, based on our review, our documentary reviews, we understood that that was implemented a little bit later in the process and so you know the further on obviously you get through the design process the the less there is sort of an opportunity to potentially adjust the design to accommodate some of the recommendations so to the extent that that those studies could be accelerated or at least occur earlier in the process would help potentially opt you know enhance the cost savings, but potentially also taking a look at how, you know, that particular practice potentially could be expanded to other projects where it is suitable, or maybe even taking a look at the practice itself to understand, again, where the department potentially is falling short of the national average and understanding if there are some refinements to that particular practice that might bring them closer to the national average on a, you per project savings basis all
right thank you i'm sorry senator chesterfield you recognize thank you mr chair if there is no formal definition of practical design or is there what i'm hearing you say there is no formal iteration of what a practical design looks
like. So there is you know a definition that Federal Highway Administration would align to there isn't necessarily a universal standard practice well I guess every single DOT uses and so what what that allows for is that you know any DOT can potentially customize or configure their use of practical design to their unique circumstance.
that definition for you, neither of us have it right here. Okay. Well, the reason I'm concerned about it is We're looking at this, and since they don't have it, you're saying that they're missing some $21.5 million. And so I need to see how you get from them being able to create their own to, but it's inadequate, and we could save 40% on our project cost and $21.5 million. dollars, how do you compare that to something else that gets you to this point where you can say definitively that this is what would be saved? We can
walk you through the assumptions around the cost savings that we have for this particular recommendation. You don't have to take me down the whole trail, but give me some idea. Sorry, I didn't hear that very. i
me some little chicken hoops along the way if you don't mind sure sure we can do that but i also the the point here is not to say that the department is not doing practical design because they are with what they don't have is formalized procedures that say team this is when we're going to actually implement a practical design approach to this project it's on an ad hoc basis there's not a formalized process or procedure that says this kind of project check always gets practical design check and therefore we can uh you know expect some sort of savings and there's not a measurement on the back side of the project that says we did private practical design it saved us x how do you get
cost savings. Right okay how do you get to like value engineering that has a little bit more data sort of you know national data related to practical design you know we had used for example Missouri as an example of some potential to give you know sort of an idea or a direction around the level of savings by implementing a practical design methodology from what we understood in conducting our leading practice research that they had saved at least in their first year of implementation about 13 per project now taking a look at the annual the average contract amount of you know average project amount about 5.1 million dollars and And I'm taking a look at this anticipated impacts assumption, row one, you know, just simply applying that 13% to that approximate $5.1 million average project cost would yield about $664,000 in savings. Now, again, this is directional in nature, and we provide this at the same time, I think, with the caveat and the recognition that the department might already be saving some of or realizing some of these savings. But I think, as Aaron mentioned, because there isn't necessarily a formal mechanism around trying to capture the savings associated with the department's current use of practical design, One, it's difficult to communicate what the potential savings could be, but then it also can potentially make it difficult to go back and review the actual effectiveness or efficacy of the department's sort of flavor or version of practical design. And so, you know, without that information, it's hard then to potentially suggest some refinements or improvements that would then yield to increased cost savings
over time. Okay, sir. You have said that it is a 40% average project cost savings from practical design, and that there would be $21.5 million in average project cost. That is predicated on something. And you have yet to explain to me what it's predicated on.
number 7 I'm looking at recommendation number 8 implement leading practices in construction project design am I the only one on that page yes okay and you said that there would be a 40 percent average project cost savings and 21.5 million so I'm just trying to figure out how you got that
this was just an again an example and it's sort of a directional example of what the Washington Department of Transportation had yielded in terms of their average you know project cost savings from using their version of practical design based on a sample of 10 projects that we were taking a look at and their average project cost savings were twenty one $1.5 million from that sample of 10 projects. Again, it's just to suggest that there is potentially a considerable amount of savings that could be yielded through having a formal process. We're not necessarily stating that, you know, this would lead to sort of a direct correlation in actual savings at the department on a project basis, not only in a percentage basis, but also in terms of the actual magnitude and the value. So this really has nothing to do with
Well, please excuse me for misreading, and I have one more question, Mr. Chair. could you please tell me, our consultants, does every state participate in the national averages for value engineering studies? Is this something done overall by federal government? The value engineering studies, the national averages, do all states participate in the determination of that? I don't have that information off the top of
Thank you. Senator Johnson, you are recognized. So, not being an engineer, so what I hear is it's a matter of semantics. or terminology and if the if the rdot had said we saved 20 percent through our design efforts then it would be a measurable it would be a measurable thing that that guide house could see and then be acceptable and not make this recommendation so i don't know it just it just seems seems like uh semantics on this one to me uh i mean the practical design and they talked about missouri i know of a couple of projects there's 60 where they used part of their existing two lanes that was there and made a divided four lane so they didn't have to buy those right-of-ways where those two lanes were. So that would be, I'm assuming, an example where they just had to buy the extra right-of-way to design those other two lanes. But that didn't fit everywhere, and they had to go around some places and bypass where they had to buy the whole thing. but there would be savings in that, use of that. So, you know, that would be my understanding of what this design and value engineering would be. Would that be correct, Director? Yes. It's
a process from the day the project is identified to the end, practical design. build the Chevy not the Cadillac you know we're all about practical design in every form and we do reduce those design standards for certain projects based on their functional class their traffic their use so it's it's huge it's a it's a big practical design hits a lot of different areas you're correct it just
seems like uh noting that or or seeing that is is what these guys are talking about in the process that that they didn't see in your documentation even though you practice it across the board you know i guess you use those terms in your i don't know anyway that's i think and that's
the reason i asked the first question too kind of had the same question and so maybe if we can and circle back one more time with him. I think it's the fact that it's not formalized, so it's not uniformly applied, which at all times it can't be uniformly applied, but because it's not formalized, you don't really get to recognize what really worked on this project and how do we apply it to the next that has similarities. I think if I'm understanding right, that's what y'all are saying, that these all can exist, but right now they exist on a case-by-case basis. And if it's formalized and documented, You learn from that formalization and documentation so that you're not repeating the wheel every single time per project. Again, that's what I was trying to ask in my first question. It could exist, but it's not formalized. Am I missing something, or did
we miss something in that conversation? No, you're correct. It really is about the formalization and having the metrics and measurements to be able to make ongoing determinations. I mean, doing the practical design may be great and you may save money, but you don't have a way of actually evaluating and continuing to revise processes and do continual enhancements and improvements to your processes because you're short of document, you know, formalized documentation on those processes and the measurements and metrics that help you determine the success of those processes. So the idea is to, you know, again, create a formal framework for when to use practical design, how to use practical design, how to evaluate it, and then to do continual service improvement to understand that the processes that you've put in place are actually working the way you intended them to and or figure out how to enhance them to make them work better. Chair McKenna. so i
mean i'm not i'm like i said i'm not the engineer andy and other engineers in the room i i can't see an engineer saying value engineering that would be like cheap engineering but i can see an engineer say we're going to over engineer practically so that would be the practical design part of it you know especially whenever you're talking about highway and bridges and safety they're not going to say we did this on the cheap they're going to say they they did it at the most cost effective manner and i don't know any engineer that wouldn't over engineer and and make it cheap and dangerous so i don't want us to get into that but you know i think you know the practical part of it is is is very important am i wrong engineers in the room i don't think anybody would want to say you did cheap engineering
right senator hendron not at all and value engineering just means we we identify what the project is for and we design it in the most economical way possible with the least impacts possible while still meeting the need of the project and in safety is one of those things as far as depends on the speed the amount of traffic there's a lot of things that go into the engineering but we make sure it's always safe and it's the right design for the right project but
you know throughout this conversation I'm a little confused because at one point I thought they said we weren't using practical design and then I determined they were saying that we did can you tell me what you well so I think I've I think
this will be the third time I've asked the question but I think the issue at hand is that there are they're using practical design on a case-by-case basis it is not formalized and so I'm just going to give an example all I can work from examples and so I used to put in sprinklers for my older brother right and we put in sprinklers you learn each time you put in a sprinkler a better way to do it and a more cost-effective way to do it and what's the best head for this particular situation whatever it may be and so you're learning and so you're able to make adjustments get a you know a good product out at a cheaper cost each time you go along but if you have five different engineers and none of it's formalized then one engineer may or not if they're not you know truly associated with it learn from some of the cost saving measures that another one was able to utilize that's the way i understand the importance of the formalization okay i'm with you now and so i think and i think that's what they're saying is because it's not formalized it's very difficult to track number one you can't improve a process on that process time after time after time because it's not being documented formalized this works this doesn't work this is when we should do this this is you know an opportunity to save money on a you know similar project am i missing something and again i don't want to keep belaboring it but i had the same question and this is for god house okay all right So I think that's the way I interpret the whole thing.
Okay. That's correct. All right. That's good because I think from my response, everyone knows that Arkansas, RDOT, practices practical design. We have what we call our 3R standards, which is 3R stands for, I think, rehabilitation, reconstruction, resurfacing. And for projects on lesser roads, if we followed, I mean it's just like in everything else you know you have to look at what the the scope is for the project what's the purpose of the project and so we have lesser design standards for those roads that are lower volume you know narrow with lane widths narrow shoulders there's just all kinds of things to in our practical design processes that minimize, that take care of the need while minimizing cost and impact. Every single project is scoped and it's scoped by our assistant chief of engineer, our assistant chief engineer for design and the design head, the head of our design department, our head of our bridge department. Every project is scoped before it's assigned to an engineer and and they're told what the parameters are for that project based on institutional knowledge, our practical design functions, everything that we do is scoped into that project, and then design begins. Where we fall short, and I will tell you, we have excellent designers. Mike Fugit is here with me today. I'm going to bring him up when we talk about the HCRAS quarterly report and the projects. But they do a great job all the way through the project of making sure we minimize impacts, we meet the purpose and need, and we build the project the way it should be built and design the project the way it should be designed. And so where we're falling short, and obviously we've said through this efficiency review and we're to this point, and we all know where the department falls short. We don't measure, and we're not able to report and defend that we're doing a good job, but we are. We just need to start measuring it, right? That's what we need to do. I talked to the staff about this recommendation. They assure me, and I believe it, that all the way through project development, project design, from environmental all the way to the engineer's estimate, we are looking at how to minimize cost, how to minimize impacts. all of that goes into every project but we're not keeping up with the cost savings every time we make a decision to change the design to save money we don't keep up with that none of that is tracked and we're going to start tracking it so that we can make a presentation to this committee or to the public or to everyone say you know we started off with these projects and because of practical design we save the state X number of dollars we can start tracking that and we will that's where we fall short on so many things because we do a lot of these things we're just not tracking so I will say that I'm glad to hear that they have said that we do use practical design because we do that I hear this if I hear it once I hear it a daily we're building the Chevy not the Cadillac what do we need to do I mean we know we have limited funding we know we have to build the project within scope within budget and we do our best to accomplish that if if you and I you know I guess you can read my response about value engineering value engineering is required by Federal Highway Administration for all projects roadway projects 50 million dollars or above and all bridge projects 40 million dollars and above every state has to do a value engineering study on these projects in this cost range. Arkansas is no different, but as I was talking to Mike about this, he said if we're not doing our job, then they're going to find things during that value engineering study towards the end of the project because they're going to see ways to save money. But if we're doing our job and we're vetting that job all the way through the design process, especially on these big projects, if we're not continually looking for those cost savings and we get to the end of the project and they can find millions of dollars worth of savings, then we haven't done our job as designers. So we do value engineering throughout the whole project, but then there are times when we have to put together a formal team and do a formal study and submit that to Federal Highway just like every other state in the nation. and that's what I think that's what God House is referring to again we don't track that we don't track those decisions but we were going to start and and if anyone would like to know more about our processes I would ask if you wanted Mike to come up here and talk about how we design projects and how we do minimize costs I'd be glad to call him up here if anyone's interested or if not, I'll just conclude my comments.
Okay, thank you. And so to get back to, I think, because when we honed it back down, what we're talking about is it's not formalized. Do you think it will be helpful to formalize those processes so that you can track and it's kind of a learning, I guess, document or program that multiple engineers can take a look at and see what other engineers had success with, whatever it may be? do you think is that something that
you do now we're formalized because we have a process in place we do it with every single project but we don't track it and and then look at you know well this really worked well and maybe this maybe we could apply this in more places that can be done okay but we are formalized in that every project is is goes through the lens of practical design in some form or fashion so does that make sense yeah so the one piece that i think that we're
going to take away from this that could be helpful is just letting it be a learning thing so we understand again back to the example on sprinklers i don't need a three inch pipe i only needed a one inch pipe it worked really well in this project i can save money by installing the one inch pipe and you've got a sign of success in a project you learn from it you keep moving forward been learning and evolving and so we're we are in agreement i think that that that will or could be helpful to the department okay perfect thank you do we have any other questions all right seeing none thank you very much for your time today let me get back to
since I'll, okay. Okay, members, we've heard a presentation on a recommendation seven and eight. Is there an interest to move forward with those recommendations having discussed at the next meeting? Yes. There's an interest. Thank you very much, Representative Davis. There was no public comment, and so at this point we're going to move forward to the quarterly report. Is that what it is? Item F. Yep. Item F on the quarterly report. And with that, we can just go ahead and turn it back over to you, Director, and thank you. And again, thank you, Godhouse, for the presentation.
I think we're good. Thank you. Thank you. Senator Dismayne, may I ask if it would be all right with the committee if I brought up Mike Fugit, our Assistant Chief Engineer of Design? Absolutely. Rex Vines, Assistant Chief for Operations. Can you all just recognize
yourself for the committee at the table? I think we're – do we have enough mics to spread out? We only have two. So I'll share someone to be sharing. All right, thank you
that all of this was Arkansas specific And so when I started talking about the 21 and the 40 percent, that was really talking about Wisconsin. Washington. And I think what if I looked at it.
Well, it said Wisconsin at the bottom. I think it said Washington. And I think what their point was, after they implemented their processes, that was the savings they were able to demonstrate.
Okay. It says at the bottom down here, Wisconsin Department of Transportation on 8. Now, is that Wisconsin or is that Washington? I'm on page 7, the 8th recommendation. I'm not sure. I know on the far right it
it's about the Wisconsin Department of Transportation. The source may be the Washington DOT, but at the bottom it says Wisconsin. So I just wanted to be clear. I thought they were talking about the possible savings in our own state, which is why I was questioning them so closely. But thank you. It was all subjective. Thank you very much. Thanks. All right. And with that, if
do you all want to do it? Well, you'll have to help me here. We're just here to answer questions, right? There's no presentation. It's just, at least that's the way I thought this. It's gone both ways.
The director may make a short presentation on some highlights of what's happening, or we can just open up for questions and move forward. Well, I'm prepared for questions, but not
thank you mr chair i have a bridge that's near the derricks junction that's what we call it the derricks junction it's on highway 71 that has been under construction for several years now and i have constituents ask me every day when will that be finished do you think somebody could get me a timeline of when that will be finished because it's literally the biggest pain in the tail for all of my constituents that have to go to work in Ashdown, Arkansas, that come from DeQueen because that gets so messed up through there. So I would appreciate it if y'all could get me a timeline of when that will be through.
I know. I looked, and it's not in here. I mean, they've been working on it for several years. We'll definitely get that to you. Thank you. Thank you, Mr. Chair.
thank you representative do we have any other questions all right seeing none I think we are good members just want to I guess I think most everybody knows but just keep up chairman McNair in your prayers and then also if you're interested in helping all you just touch base with represent involved again thank you for your time today and consideration and do we have any other business all right seeing none we are adjourned thank you members.
Senator Jonathan Dismang introduced the item and turned the floor to Diane Torres-Porter, legislative attorney for the Bureau of Legislative Research, who presented the constitutional and statutory framework for the General Assembly’s oversight authority over the State Highway Commission under Amendment 42, citing case law such as *Pritchett* and *Parkin* and detailing the Assembly’s power to grant or withdraw duties.
[1:12][1:47][2:18][2:26][2:50][3:24][3:54][4:24][4:54]
Torres-Porter then reviewed prior examples of legislative oversight committees-including Act 605 (2009) for the lottery, Act 1258 (2015) and Act 1500 (2013) for the health-insurance marketplace-and explained that the Assembly could similarly create a committee to oversee implementation of transportation recommendations, noting the current statutory exclusion of the Highway Commission that could be amended.
[6:31][7:03][7:33][8:04][8:35]
In the ensuing discussion, Senators Dismang, Chesterfield and others debated the potential composition and scope of such a committee, raising questions about including non-legislator stakeholders, avoiding micromanagement of the Highway Department, and coordinating with existing transportation committees, but no motion or vote was taken, leaving the matter open for further consideration.
[9:11][9:40][9:49][10:10][10:19][10:22][10:29][10:41][11:15][11:30][11:43][11:47][12:17][12:49][13:21][13:43][13:55][14:25]
During the update, Senator Lance Eads moved to add recommendation three (publish construction and maintenance status) to the draft report; the motion was adopted unanimously after no discussion, with the chair recording an “aye” vote.
[15:31][15:43][15:49][16:05]
Eads subsequently moved to add recommendation four (manage all customer inquiries to resolution) which also passed without opposition, and the chair confirmed the additions before proceeding to the next agenda items.
[16:19][16:24][16:35]
D. Expenditures Recommendation No. 7: Implement project and portfolio planning frameworks (Recommendations Report, pp. 35-40)
16:45 - 1:04:23119 segments10 speakers
The Guidehouse team, represented by Erin Hutchins and Sauger Gokhale, presented Recommendation 7 to implement project and portfolio planning frameworks, outlining five key findings about fragmented project development, construction monitoring, lack of formal change-order review, missing target costs, and immature budgeting tools.
[18:17][18:46][19:19][19:53][20:27]
They projected roughly $3.8 million in annual savings by applying a 10 % efficiency gain-derived from research on project-management maturity-to the department’s five-year average pre-construction and construction monitoring budget of about $38 million.
[23:22][23:52][24:26][24:57][25:29][36:12][36:39][37:10][37:44][38:15][38:19][38:54]
Senator Terry Rice challenged the assumptions behind the $3.8 million figure, prompting Guidehouse to explain that the estimate rests on a 6 % versus 16 % maturity gap identified in a Project Management Institute study and that no specific state-level data were used.
[35:52][36:02][36:12][36:39][37:10][37:44][38:15][38:19][38:54][39:21][39:27]
E. Expenditures Recommendation No. 8: Implement leading practices in construction project design
1:04:23 - 1:46:11120 segments9 speakers
The consultant presented three key findings: lack of formal protocols for practical design, under-utilization of value engineering, and insufficient evaluation of engineers’ estimates, noting that RDOT completed only 2.2 value-engineering studies per year with $377,000 savings versus a national average of 3.3 studies and $21 million savings.
[1:04:26][1:05:01][1:05:39][1:06:13][1:06:44]
He estimated that formalizing practical-design frameworks could save roughly $660,000 per project (about 13 % of an average $5.1 million contract) and that raising the value-engineering study rate to the national average could increase savings to between $1 million and $16 million annually.
[1:08:20][1:08:53][1:09:26][1:10:02]
F. Report on progress of each highway and construction project of $10,000,000 or more as required by ACA § 27-65-107(a)(19)
1:46:11 - 1:50:0721 segments5 speakers
Senators clarified that the 40 % cost-saving and $21.5 million figures referenced in the recommendation were drawn from other states (Washington or Wisconsin) rather than Arkansas, and the chair noted there would be no formal presentation on the quarterly report, moving the discussion back to the recommendation.
[1:47:06][1:47:17][1:47:31][1:47:51][1:47:57][1:48:05]