Associate General Counsel David Curran presented a report on the employment-discrimination lawsuit filed by Professor Brian Mitchell against the University of Arkansas at Little Rock, noting that the case is pending before Judge J. Moody with a motion dismissed and a 50-page brief filed.
[7:27][7:37][8:07]
When Representative Cozart asked for questions, none were offered, and the committee thanked Curran for his report before moving on to the claims-review agenda.
[8:20][8:39]
The committee heard claim 220758 from Hugh Jarrett and Carol Booth requesting reissuance of an outdated $23,037 warrant; the Claims Commission unanimously approved the claim and referred it for inclusion in an appropriations bill.
[9:50]
After no questions were raised, Representative Cozart moved to approve the warrant reissuance, which was seconded and adopted unanimously.
[10:22]
Senator Trent Garner queried the settlement process, and Claims Commission Director Katie Sir clarified that the commission reviews and approves settlement agreements but does not participate in negotiations.
[12:25][12:35][12:45]
Representative Lane Jean moved to affirm the Claims Commission’s ruling on the settlement, a motion that was seconded and carried without opposition.
[13:05][13:14][13:21]
The Claims Commission awarded James Construction Group LLC $910,837.44 for a bridge-project dispute with the Arkansas Department of Transportation, allocating amounts for overhead, deck replacement, flagging costs, liquidated damages, attorney fees, and pre-judgment interest.
[13:37][14:08][14:40]
Senators Bart Hester and Trent Garner questioned the Arkansas Department of Transportation about preventive measures for similar construction issues, and department officials indicated new oversight and engineering leadership to address concrete-pour problems.
[15:26][16:01][16:11][16:35]
During questioning, Senator Garner sought clarification on the unusually high flagging-cost component; the commission explained that the project required 138 additional flagging days beyond the contractor’s original estimate, justifying the $356,883.23 award.
[17:10][17:22][17:45][17:56][18:16][18:19]
Representative Cozart moved to award the James Construction claim, the motion was seconded and adopted unanimously.
[20:24]
The commission also approved a $22,500 reimbursement to Rock City Harvest LLC for a duplicate medical-marijuana license renewal fee, and a motion to approve this award was introduced and seconded pending final vote.
[20:58][21:32]
4. Awarded Claim – Appealed by Respondent a. #191111 Flynco, Inc. v. Arkansas Tech University 21:50
The committee considered Claim #191111, Flinco, Inc. v. Arkansas Tech University, in which the Claims Commission had awarded Flinco $143,752.46-comprising $128,267.12 for the remodel contract, $7,985.34 for insulation, and $7,500 in attorney’s fees-and noted that Arkansas Tech had appealed the award.
[21:54][22:06][22:39]
Arkansas Tech argued it had the contractual right to terminate for alleged fraud and sought to strip the award of the $7,500 attorney fee and the $32,926.46 profit component, reducing the judgment to $103,326, while Flinco contended the award was based on a termination-for-convenience finding that entitled it to both work-performed compensation and profit on unperformed work.
[24:35][24:47][24:58][25:05][25:10][25:23][34:18][34:58][35:34][36:04][43:28][43:35][44:06]
A motion was moved to amend the Commission’s ruling to a reduced total of $110,806.46 (removing profit and attorney fees), seconded, and approved without opposition; a subsequent motion to award the claim was likewise seconded and carried unanimously, finalizing the committee’s decision.
[57:03][57:36][57:45][57:52][58:03][58:14][58:45][59:17][59:34][59:49]
I see a quorum. Glad to have everybody here for this exciting day. Yes, sir. I know. Is she here? Well, I'll just get started with something really, really fun. There's a little blonde sitting on that way back corner over there that got a little older today. Deanne, happy birthday. If there's anybody else, I'd be glad to recognize you. I don't know if there's anybody else that has or not, but anyway, thank y'all. Senator Hester, have you anything you'd like to say? Nope, I'm good. All right, well, let's get started here. We're here today to hear some things on claims review. First off is item C, a litigation oversight report by the agencies. Is Mr. Curran here? I believe he has a report for us. Just state your name and who you're with for the record,
please. I'm David Curran. I'm Associate General Counsel at the University of Arkansas System. And we've been asked to give a report on a lawsuit, Brian Mitchell, against the University of Arkansas at Little Rock. This case involves a history professor at the University of Arkansas at Little Rock. Last summer, he was awarded tenure, promoted, and given a raise. And to our surprise, a couple months later, he filed an employment discrimination lawsuit. We have the cases in federal court. We have a motion dismissed pending in the case for the last two months. It's been assigned to Judge J. Moody, and we are writing a ruling at this time. And we have a 50-page brief out there, which I'm sure a lot of you would love to read, but I would not love to read, but I'll be happy to give you a copy of that if you would like. I'm probably not at liberty to answer a lot of questions given the active nature of the case, but I'll be happy to try if anybody has any
questions. Okay, we do have one question. Representative Fyke. it was wrong you didn't want it okay sorry about that well I guess we do not have any questions so thank you mr. chairman we thank you for your report all right let's go to our claims review item one a reissue us of warrant unpaid bill, item A, which is, let me see here if I get this right. I guess I'll get Ms. Deska to give us a brief description of this. Is that right? Are we on this one? Oh, did I miss something up here? Oh, okay, hold on. I'm skipping ahead of myself. I'm sorry. Remembers, the agenda items D1 through D4 are discussions of the Claim Commission that are being reviewed. Ms. Irby, could you come to the table and identify yourself, please, for the record? Sorry, I got a little bit ahead there. Lunch is calling. Yes, sir. My name is Catherine Irby.
This claim is claim number 220758, Hugh Jarrett and Carol Booth versus the Arkansas Department of Finance and Administration. This claim was filed by Jarrett and Booth requesting reissuance of an outdated warrant in the amount of $23,037 payable to the Arkansas Department of Finance and Administration. The warrant is still outstanding and no duplicate has been issued. The Claims Commission unanimously allowed the claim and referred it for review and placement on an appropriation bill. Ms. Irby, does the Commission have anything to add? Ms. No, sir,
but I'm happy to take any questions. Are there any questions or discussion from the members? Seeing none, do I have a motion to approve this item? I have a motion, second. Second. I have a second. All in favor? Aye. Any opposed? Motion carries. All right, number two, Ms. Deskett, can you give us
a brief description of claim two? This is claim number 200054, Charles E. Cross as appointed administrator of the estate of Connie M. Stokes Cross versus the University of Arkansas for Medical Sciences. Claimant Charles Cross, as administrator of his wife's estate, sought $800,000 in compensation for a medical negligence claim against the University of Arkansas for Medical Sciences. Claimant alleged that his wife, Ms. Stokes Cross, presented to the emergency room with bilateral leg swelling, dyspnea on exertion, and elevated blood pressure. Claimant alleged that he requests that she be treated immediately, but was advised that there was no room. After her vitals were taken, claimant went to his car to retrieve items. When he returned, he found his wife unresponsive in her wheelchair. He alerted the emergency department staff, who were unable to revive her. Claimant argued that UAMS was negligent in allowing Ms. Stokes-Cross to simply wait unattended without any additional care, monitoring, or treatment, and thereby approximately caused her unresponsive condition and death. Respondent UAMS denied liability, affirmatively stating that Mrs. Cross was triaged appropriately and that she had experienced symptoms for weeks prior to presenting at the emergency department. The parties entered into a negotiated settlement agreement, wherein the claim was settled for $225,000. The Claims Commission approved the settlement agreement and referred the award to the General Assembly pursuant to Arkansas Code Annotated Section 1910-215B. Ms. Herbie, do you have anything to add to this? No,
members? And I think I have Senator Garner. Thank you, Mr. Chair. Just educate me on my ignorance over here. So how do these negotiations usually work? Is it typically like any other kind of lawsuit or anything like that with the Claims Commission being involved? Is it done? Is it they make their agreement and then bring it to you all for adjudication? How does that typically work on these kind of negotiated settlements? So
from the Claims Commission perspective, we receive a settlement agreement from the parties. How they go about negotiating it, that I'm not privy to. But in this case, we received a settlement agreement, which the commission reviewed and approved and sent over here. Okay. Just wanted to check on that. Thank you, Mayor. Thank you, sir.
this is claim number two two zero one five three oh I'm sorry I'm on the wrong claim this is claim number one eight one zero seven three James construction group LLC versus the Arkansas Department of Transportation claimant James construction group entered into a contract with respondent Arkansas Department of Transportation for construction of a bridge on Roosevelt Road Little Rock which spanned over the Union Pacific tracks. Claimant sought $1,441,552.02 in damages alleging delays, disruptions, and contract administration irregularities on the part of the respondent. Respondent denied liability and urged dismissal arguing that claimant had been paid per the terms of the contract. Following briefing by both parties and a hearing, the Claims Commission awarded the claimant a total of $910,837.44, which was comprised of $184,659.92 in overhead, $53,475 for the remaining half of deck replacement costs, $356,883.23 in additional flagging costs, $154,000 in reimbursement for improperly assessed liquidated damages, $10,000 in attorney's fees, and 6% pre-judgment interest of $151,819.29. Ms. Arbita, does the Commission have anything to add to this? No, sir, but I'm happy to take any questions. Okay. Members, are there any questions?
to ask some questions of RDOT, if that's possible. Do they have anyone here? Mr. Umeda is on the screen. Yes, sir. Mr. Umeda. So it was probably about a year ago we had a very similar, at least on high-level circumstances, claim where we were doing a bridge deck pour or at least the vertical structure where there was some question on a coal joint. Anyway, it was lots and lots of money that the RDOT ended up having to pay out. Here we are again on somewhat similar circumstances. What are we doing to prevent, you know what I mean, is there a new process in place? If we're going to stop somebody from pouring or claim there's a cold joint, like, when it's costing us millions of dollars, like, I guess I want to say that this seems to be this is the second time in two years where
this is a problem. What are we doing to make sure this isn't a problem anymore? The department is definitely looking at issues with concrete pours. I believe after this incident, they're going to try to have more hands on deck to supervise the pour. We also have a new chief engineer, and I'm sure he's overlooking and seeing these issues, and hopefully we'll come up with some new processes to help prevent some of these issues
Yes, sir. Neither party appealed this award. Okay. Thank you. Senator Garner. Thank you. The conclusion of $356,000, $100,000, excuse me, additional flagging costs, why is that so high? Is it just staffing that they have to do? Why was that amount awarded to that degree? Is it just, I tried to read through some
of the testimony, but it's just extensive. Yes, sir. Give me just one second. Okay, so what the Commission found is that James Construction had budgeted approximately $1,800 per day for railroad flagging expenses and because of the extended amount of time that this project took that that there was an extra 138 working days of flagging costs that james construction could not have anticipated and so they're they initially did a contract with
r dot for x amount of dollars for flagging and other things a day they james argued that r dot made them stay over 100 plus days and then the commission agreed with that that's rewarding that that basically r dot kicked this can down the road and made them incur all these extra costs is that a kind of a summary of
it or is there more to it well i think that the contract just Ended up taking longer and that additional working days had to be added to it And that the claimant had included in its original bid they had bid two hundred and fifty thousand dollars that they had set aside for railroad flagging expenses, but that because the project took so many more working days than Either party originally anticipated that the railroad flagging costs were significantly higher than that
Does that answer your question? Yes, ma'am. Maybe this is the RDOT. I mean, if you contract for X amount of time and they're going to incur all these extra costs, what was the thought process of not trying to negotiate something with them to additional? I mean, why did this make it
like y'all had to throw down on this? Well, the contract is actually between James Construction and the railroad company. The RDOT is not a member or a part of that contract. It's my understanding that the railroad company sort of, they've taken advantage of the situation and sent out more people than necessary. And so additional costs were incurred that way. Fortunately, like I said, the department does not have a contract, cannot tell the railroad company what to do during these jobs. So the department's position was that that's something to be worked out with the railroad company. and not
RDOT. Okay, and how did RDOT become responsible? Was that what the commission found, is they weren't responsible, that this railroad company wasn't responsible, it was actually RDOT's position that they have
to hold? Either or, I guess. Well, so I can say, and the claims commission found that perhaps James Construction and RDOT could pursue the railroad to recover for any alleged overcharges, But to the extent that that claim might be time barred or for some other reason unsuccessful, the commission thought it would be unfair for claimant to have to bear those costs alone.
Okay, thank you. Any other questions? Seeing none, do I have a motion to award this claim? I have a motion. Do I have a second? I have a second. All in favor, say aye. Aye. Any opposed, no. Motion carries. Item B on
number three, please. Ms. Deskin. This is claim number 220153, Rock City Harvest, LLC versus the Arkansas Alcoholic Beverage Control Division. Claimant Rock City Harvest, LLC alleged that it paid the renewal fee for its medical marijuana dispensary license twice. Claimant sought reimbursement of $22,500, which is the amount of a single license renewal fee from ABC. ABC responded admitting that claimant was entitled to reimbursement. The claims commission awarded the claimant $22,500 and referred the claim to the General Assembly for review pursuant to Arkansas Code Annotated Section 1910-215B.
Ms. Erby, do you have anything to add? No, sir, but I'm happy to take any questions. Are there any questions from members? Do I have a motion to approve? I have a motion. I have a second. I have a
second. All in favor say aye. Aye. Any opposed? Motion carries. Item four. Ms. Neskin. This is claim number one nine one one one one, Flinco Incorporated versus Arkansas Tech University. Claimant Flinco Incorporated sought not less than two hundred ninety two thousand eight hundred sixty eight dollars and thirty cents in damages from respondent Arkansas Tech University alleging wrongful termination of two contracts for remodel of the Williamson building and for the installation for the installation of insulation in the Williamson building claimant argued that respondent should not have terminated the contracts and that respondent did not follow the required procedure to terminate the contracts respondent answered denying liability and stating affirmatively that claimants work was negligent following a hearing in this matter the claims Commission may detail factual findings concerning the circumstances of the contract and awarded claimant Flinco a total of one hundred and forty three thousand seven hundred fifty two dollars and forty six cents the award was comprised of one hundred twenty eight dollars one hundred twenty eight thousand two hundred sixty seven dollars and twelve cents in damages related to the remodel contract and seven thousand nine hundred and eighty five thousand thirty dollars and thirty four cents and damages related to the insulation install finally seven thousand five hundred dollars was awarded an attorney fees. Respondent, Arkansas Tech University appeals.
Ms. Irby, do you have anything to add to that? No, sir, but I'm happy to take any questions. All right. Yes, sir. Mr. Chair. Well, if possible, I would like to just hear from Arkansas Tech themselves on why they think this should be appealed at all. I think they are here, sir. It seems like
a bit of a mess, but yeah. All right, do we have a representative from Arkansas Tech that can come forward, please? All right, if you state your name and who you're with, please,
then you're welcome to. Good morning. My name is Thomas Pennington, and I'm the former University Counsel at Arkansas Tech. Good morning. Nice to see you all again. My name is Edward Armstrong, and I am the current University Counsel at Arkansas Tech University. Mr. Chair, you're going to ask me.
Well, I would just like to hear from you guys what specifically has changed since the Claims Commission, or if nothing, what the grounds for your, why are you arguing their results? Thank you,
sir. It's the position of Arkansas Tech that we had the right to terminate the contract, that fraud had been committed, and therefore attorney's fee should not have been awarded. and also we'd ask that the verdict be reduced to not award profit to
If my math is correct, the verdict total was $143,752.46. IF WE REMOVE THE ATTORNEY'S FEES, IT WOULD BE REDUCING IT BY 7500, REDUCING THE PROFIT ON BOTH COUNTS WOULD BE $32,926.46 WHICH WOULD LEAVE $103,326. THANK YOU. Representative Shepard. Thank you, Mr. Chairman. I have just a few
questions that the chair will allow, and then I would like to hear from the contractor as well. So with regard to the, one of the contentions by tech is that there was fraud committed by the contractor. What
was that fraud? Thank you, sir. It was the position of Arkansas Tech University that it was the submission of two false pay applications at the beginning of the contract. Okay. And does
tech, now my understanding is that, and tell me if I'm off base here, but as I read this last night, that those were submitted at the request of representatives of Arkansas Tech who actually asked for the submission of pay applications. and I'm not trying to justify one side or the other because there's no reason to be submitting false applications, but am
do that. Okay, and was that person benefiting personally by the submission? The representative of Arkansas Tech, were they benefiting personally by requesting those pay applications? I'm speculating
at this point, but I think it was, in my opinion, it was an attempt to save his job. And so in that regard, I would answer you as a yes. But do I think that he pocketed any money personally as a result of that? No.
As I understand from the material, it was to try and procure the grant funds that were being used to pay in a timely fashion. And then, finally, it looked like this hinged largely on whether this was a termination for cause or whether it was for convenience. As I understand, TEC is claiming it was a termination for cause, but as I review the material, it seemed that there was some question as to whether TEC specifically identified what that actual, the cause of the termination was.
Am I incorrect about that? That's a very good question. It's our position that the contract allowed us to terminate the contract for neglect or default. Then there are, I think, 14 reasons underneath that. The contract did not require us to specify which of those 14 we were using, but fraud was within those. One more question, if I may. I apologize.
I don't know the answer to this. I'm asking, and I'd like to hear from the contractor. With regard to the distinction between a termination for cause versus a termination for convenience, what is the difference in terms of what the contractor can recover based on whether it was a termination for cause or convenience, or
is there a distinction? The Claims Commission, which had a very thorough opinion, based their decision on termination for convenience, which allowed for the provision of profit in the verdict.
Okay. Thank you. Thank you, Mr. Chair. If I'm listening right, the argument is that y'all terminated for the reason that you did, but was there anything in the contract or anything legally that would give the contractor any coverage if it was because of your employee that initiated the action, if they indeed initiated the action first? That's a good question, sir.
I don't know the answer. Um, I would submit to you though that, um, there were three people that did things wrong in this contract. It was the Arkansas Tech University employee that was terminated, which was our construction manager. It was the construction manager for the construction company that agreed, I'll submit these false invoices, and then the architect, which also agreed to the submission of the false invoices. And when I say agreed, they signed off
on it. Senator, if I may, and thank you, Thomas, for explaining that. I would answer that the contract clearly did not give cover for this. It was a wrongful action for them to submit the invoice. So obviously, even if an employee of ATU suggested that they act outside of the bounds of the law and outside of the contract, the contract wouldn't justify that. So it would be outside of what was permitted under the contract. And I
guess what I'm trying to wrap my mind around is it's okay for you all to terminate the contract on the basis of what you feel the contractor did wrong. But where is the responsibility that you would assume, in fact, that it was one of your employees who did something wrong? And then the follow-up to that would be the actual work that was done, set aside, grant time running out, motivation, all that stuff. Was there actual work done that's represented in the dollar amount that is being requested? Materials, labor, going through the auditing process to make sure the two-by-fours and the labor was all there. does this dollar amount actually represent work done? Even if the grant hadn't run out, it would
have been paid for out of the grant. On the first question, I think Arkansas Tech acted appropriately by terminating the employee after he had taken the actions that he did. And it was pretty quick. I mean, we found out about it and he's terminated within, I'm going to make it up, 72 hours. To answer your second question, the recommendation that we have that would reduce the verdict to $103,326 would compensate Flinco for items awarded by the Claims Commission for unpaid work. There was unpaid work of $53,000 that was awarded in count one and $7,326 in count two. And then the Claims Commission awarded $43,000 in retainage. So when we have a pay application, we retain 10%, and we did not object to the first five pay applications that we paid, setting aside the very first two. So there was a total of $103,326.
Okay, thank you. Thank you, Mr. Chair. Any other questions for ATU? If not, I'm going to see if there's anyone out there from Flinco that wants to come forward. If you would make your way this way, we will let you state basically the reasoning for everything here. I think, Mr. Speaker, did you have a question for the contractor side?
guess my question would be- How is it off? I'm sorry. I thought I had it on. Thank you. Now you're on. So I guess my question would be just a response to any of these points or questions that have been asked. I mean, specifically with regard to this question of whether it was a termination for cause or a termination for convenience, what is the contractor's position on that? And if I assume that in part you would say it's termination for convenience, but what would you point to and help us understand the distinction there and why you believe it's one or the other, or maybe neither? Sure. Excuse me. I'm sorry.
The Claims Commission terminated, decided. Let me back up. I'm sorry. Arkansas Tech purported to terminate the contract for cause. Flinco's position was, A, there was no grounds for termination, and B, the procedure for terminating the contract for cause as set forth in the contract was not followed. The Claims Commission agreed that Arkansas Tech did not follow the procedure in the contract for termination for cause. They made an explicit finding about that. And then they said, okay, but there is a provision in the contract that allows Arkansas Tech to terminate for convenience. Termination for convenience means that they do not have to have a cause. They can do it if they want to, for no reason, probably. So the commission expressly decided that although there was no grounds to terminate the contract for a cause, it could be terminated for convenience. And although Arkansas Tech didn't do that, they could have done that. So they then decided to award damages based on the termination for a convenience provision, which, as Mr. Pennington said, includes payment for work performed, profits lost on work that was not performed, that's basically the contract remedy. The attorney for your remedy is a legal remedy.
Is there a distinction in the process for a termination for cause versus a termination for convenience, aside from having to specifically identify what the cause is? I'm not sure I understood your question. Well, I guess what I'm trying to get at is it kind of sounds like the Claims Commission, while they found that it was not a termination for cause, which was your position, they also kind of gave Arkansas Tech the benefit of the doubt, and instead of saying you didn't follow the contract to terminate at all, we're going to consider it a termination for convenience. In other words, they kind of gave each side something. I'm just wondering, was there an argument that the contract had never been properly terminated and therefore Arkansas Tech should have been held to
the whole thing? That was our case. We took the position that there was no termination for cause and because there had not been an actual termination for convenience that we were entitled to recover damages for basically breach of contract, wrongful termination and breach of contract. The, you know, there's not a lot of rules in my experience about this. Contracts say that this termination for convenience remedy is available in all the state contracts that I know of. And some contracts, and I don't remember what this one says, to be honest, but there are contracts that say that in the event that a contract is wrongfully terminated, then that becomes a termination for convenience. And then the remedy is whatever the termination for a convenience section says. I don't remember if this contract says that or not. But, you know, I think the Claims Commission sort of said, okay, that's what we're going to do. I'm guessing, but I kind of think that's what they did. Did the
This case was done a little differently, I think. At least my experience, the Claims Commission is not that vast, but what we did, this was such a huge mess, and there were so much information and so many people involved and so many documents and so much everything, Mr. Pennington and I. And also, we had the COVID stuff, and it was hard to even have a hearing. So Mr. Pennington and I, with the commission's permission, decided that we would just put it all down on paper. So we took a stack of depositions that high and a stack of documents that high, and we put it all in a big pile and dumped it in the Commission's lap, and I think they read every bit of it because they're quote a lot of the deposition testimony in their decisions, so they reviewed a mountain of information. And that was by agreement between the parties? Yes, Mr. Pennington and I did it by agreement because we couldn't think of another way to do it that would make any sense at all. Thank you. And there were other points raised. I tried to make notes, but if people could ask me questions. I've got another question. Otherwise, I'll try to. Another question coming up. Senator Hammer. Thank
you. Just kind of walk me through the process real quick. So there was the disagreement, and then they approached by terminating for cause before the commission. That was step number one. Is that right?
Yeah. I'm sorry. Everything about this is not easy to explain. There's just nothing about it. You can summarize it in a sentence, but yes. Flinko had a contract. Flinko performed the contract for a while. It got terminated. We made a
happened? Let me give a brief fact summary. Brief will be fine. Thank you. Brief as I can. Flinko entered into a contract with Arkansas Tech in May of whatever year it was, the over-billing incident that Mr. Pennington talked about occurred in May of that year. It was resolved, at least that's our position, and five months went by where we worked on the job from May until the end of October. the beginning of november of that year the the termination for cause letter was issued a few months passed and then we followed our
and the claims commission ruled what the claims commission ruled that the contract my understanding of what this says is the contract was wrongfully terminated. Okay. But the termination for convenience remedy was available to ATU, so they applied damages based on that remedy. Right.
And maybe this is along the lines of the speaker, and that's what I want to get clear. Did the claims commission, through their determination, allow for the contract to then be terminated for convenience? Was that, did they initiate that or did Tech come back and say, okay, we've got that opportunity. I got it. Now we're going to go back and try to terminate it for convenience.
and terminate the contract for convenience. But they didn't. But they didn't. No, Tech, once we got to the Claims Commission, everything was over as far as Planko and Tech was concerned. A side event, after the contract was terminated, the building caught on fire. The contract was never completed, and we had our lawsuit, you know, after that. So once we went to the claims commission, everything happened there. We didn't go back out. One last question,
then, because you brought it up. When the building burned, did Tech get the benefit of the insurance policy, and did they get benefited at the full value of the building as though all this work would have been completed? I don't know the answer. Mr. Chair, could we ask Tech that question,
please? You may. This is the most complicated fact pattern. I apologize. The information that I have is that when the second contractor came in, the building caught on fire after that, that matter has still not been resolved with the insurance companies because there's the university property damage insurance. Okay, let me just shorten it up and just ask
you, are you all asking for the full benefit of the building completed, including the work that Flinko would have done? Is that what you're anticipating getting from the insurance company as though it would have been the full amount with them
you for profit, for work not performed? My understanding of the contract and the award is that the profit number, well, the says that the remedy for termination for convenience is pay for the work that's done, pay for profit on the work that was not done because of the termination for convenience. That's the remedy that's in the contract. So essentially, as Mr. Pennington explained, the award is based on the work Flinko performed that Arkansas Tech admitted was performed and not paid for. There was a dispute about what we did and the commission did not award Flinco damages based on the work we claimed we did but that Arkansas Tech disputed. They just based their award on what Arkansas Tech had already agreed they owed. Plus the profit on the work we did not do. And that's my question. Yes, sir. That's the answer. The 30 some odd thousand dollar number based on what the commission said and the contract says is profit on work that was not performed because of the termination. So there
was fraud. They terminated the contract. Now you want... There's fraud by all parties, tech, Flinco, and the architect. So you want profit for work not performed after the fraud. Let
me try to explain our position because first, well, first, I mean, like I say, it's hard to explain to you this. Flinco did... Nobody even says that Flinco defrauded anybody. Its employee, just like Arkansas... Did the prosecutor say that? I think the prosecutor did. Well, the prosecutor accepted a no-contest plea from Flinco's employee. But just like Arkansas Tech didn't know what its employee was doing, neither did Flinco know what its employee was doing. The facts show, the commission says, when Flinco learned about the problem, they were notified with a letter from Arkansas Tech that said, I forgot the words. There was an overbilling, an overpayment, whatever they called it, end of May. We want our money back. They got the money back the next day. As soon as Flinko knew what had happened, they corrected the problem, period. They didn't know about this. There's evidence in the file that proves they didn't know about this. Arkansas Tech didn't know what their guy was doing either. The architect knew what was going on. He was an independent party. He didn't have to tell anybody anything. But the fact is, the undisputed fact is, is that as soon as Flinco knew what happened, they fixed the problem. They refunded the money. They started over again. And from a legal standpoint, whatever that's worth, Arkansas Tech did not terminate the contract in May. They allowed Flinco to continue performance after they received their refund. That is a waiver of any grounds for termination based on those actions under the law. And so we would go forward until November, and it comes back up again for whatever reason. And here we are. But Flinco was never accused of a crime. Flinco was never involved in any criminal action. Its employee pleaded no contest to the charges that were made against him. Mr. Brownsville, the Arkansas Tech representative, pleaded guilty to the charges against him, and the architect did too, as I recall. We weren't involved in that stuff, but the pleadings are attached to the motion, so the Notice of Appeal, excuse me. But the Finco's position, which we believe was sustained by the Claims Commission, was that it did not commit fraud, and whatever fraud was committed was weighed. So, I mean, I'm sorry for the long-winded answer, but that's our position. We're asking to be paid for the work that we did after all that happened, after all that happened, that we were allowed to perform and then weren't paid for. Yeah,
perform the profit of it. Everybody agrees that you get paid for the work you did. I'm saying, should you get paid for the profit? And I understand your position, right? Your position is you do as a contract, but I'll move on. So my question is,
was a, excuse me, this was a negotiated contract. I don't understand all the ins and outs of the negotiation, but apparently contractors are approved in advance to do work up to a certain value for the university system. This job was fit in that category. Flinko was selected as the contractor to do the job and negotiated a price to do the work within that cap. And that's how it happened.
apologize. Oh, that's fine. I just was curious. I just, I kind of thought this was just a negotiated bid and was not out for a competitive bid with all the other contractors. Okay. I have some more questions over here for you. Let's start
Mine was asked. Representative Shepard. Thank you. So, Senator Hester asked some good questions about what was awarded and what was being paid for. Am I correct? As I read the order, there would have been no basis. There would have been no basis at all for the payment of proceeds for work, for profit, after the fraud. I mean, as we're referring to it, or for any work that hadn't been performed. If Arkansas Tech had followed the contract, had given notice, but the Claims Commission found that they didn't follow the contract and instead almost, I mean, treated it as a termination for convenience, which there probably could be an argument against that. But is that, am I correct about that? Does Arkansas Tech disagree with that? Oh.
Thank you, sir. I think that I would really ask the committee to think about what I'm about to say. The process they said we didn't follow to terminate the contract was to ask the architect, is it okay to terminate the contract? He's the decision maker. He was one of the parties engaged in the false pay application. So when they say that we didn't follow the procedure, I think we followed the procedure in one section of the contract. There's another section they're referencing that they say we didn't follow the procedure. That procedure they're saying we didn't follow was to involve the architect, which we say was, and the architect that pled guilty to falsifying business records. So I don't know that I've answered your question, but. But the architect, the architect was Arkansas Tech's architect.
That's who you retained. That was not, that was not, this wasn't something where you were contracting with both the architect and the contractor jointly or for some type of. You are correct, sir. Well, and then the claims commission found that instead of getting, even giving notice of fraud, that the only thing that was said was notice of neglect and or default. Did Arkansas Tech give notice of the fraud under the contract? It's
our position that when we gave notice of neglect and default that it was included within the 14 provisions under that. We did exactly what the contract required was to give them notice of neglect and default. It doesn't say and specify one of the following. It just says neglect and default. Okay, and then the final
I know the Claims Commission had said, and to your point, that you didn't certify it with the decision maker who was the architect and you're saying that the architect was part of the problem and why would you go to them. Is there, and I'm not, it's unclear from the order, there's a statement that Flinco was not given the opportunity to cure the defect or the default. Is that something that's provided for under the contract for a termination for cause? Is there a right to cure any
from the contract. Excuse me, I'm sorry, my throat's clogging up for reasons I hope aren't associated with what I read in the newspaper. The contract has, Arkansas Tech wrote these contracts, not us. The contract that they wrote says that there are general conditions that are incorporated by reference into the contract. Those general conditions were observed and followed throughout the process of this project. One of those provisions in the general condition specifies a procedure for termination for cause. It requires that an initial decision maker specify the reason for termination. It also says that that notice has to be given seven days before termination. It is our position that the initial decision maker necessarily identifies the reason for termination and the seven days give us an opportunity to cure that reason, whatever it might be. The initial decision maker doesn't have to be the architect. In fact, the words initial decision maker are what that person is called. In this case, the contract that Arkansas Tech had with the architect identified him as the initial decision maker. There is a procedure for changing the initial decision maker if either party doesn't like who it is. If Arkansas Tech doesn't like it or if the architect doesn't want to be it, either way, you can change the initial decision maker. The fact that the architect was involved in the overbilling, I agree. That raises the specter of a conflict. If that's the reason why he's being asked to issue a decision, although five months later, who knows? But the fact is, is that Arkansas Tech could have replaced him with another initial decision maker, an independent decider, to say yes or no or whatever about this. That was not done, and that is what the commission said, that it should have been.
Do you have anything else, Mr. Speaker? No, no. Okay. Senator Hamer. What is the dollar value of the profit that's included after the fraud was committed? Is that to the Claims Commission? I guess. Whoever can answer it. What's the dollar value of the profit to Senator Hester's point a while ago? What's the dollar value of the settlement amount that the commission is proposing after fraud was committed? There was
It is $32,200 roughly as to the remodel contract and about $600 as far as the insulation installs. So we're talking about a little under $33,000. So maybe this is a
question I shouldn't ask but I'll ask anyway. What if we just took that off of the amount that you're proposing and made that the settlement amount that we recommended? Why would that not be a logical way to approach this given the profit that's included in the the settlement amount after the fraud occurred. I get it. Nobody likes what any one of the three parties did, but at the end of the day, is that -- if anybody wants
to respond, if the Chair feels that's a fair question to ask. Senator Hammer, if you'll give me just a second, we're working on something. I figure you might be. Thank you.
Thank you. a testimony back and forth on this. It seems to me as if Flintco performed work up until a certain point in time, but the profit portion of it that they didn't perform the work on, I don't know that they necessarily, if the contract was terminated, they shouldn't necessarily get paid past that point. And so my motion would be to cover the cost of that minus the profit portion, the $32,000, and cover the cost of their attorney's fees. I think the motion is to amend the ruling of the Claims Commission, and that total would
Representative Shepard. So, you know, I think the bottom line to this is that there's, this was a mess. Both sides, whether it should be attributable to them, but or just it was the actions that our employees, you know, have acted in an improper fashion. I guess the thing, the issue I have with the motion is that from what I understand from the Claims Commission's decision and what's been stated here today is the profit would not, had Arkansas Tech followed the letter of the contract, the profit never would have been an issue. There would have been no basis for the award. And that's, you know, that's my concern. It's not as if I don't know that there's a party that is in, should necessarily win or lose here. It looks like the Claims Commission kind of split the baby, so to speak, and, you know, tried to give some award to Flinco, but then at the same time they at least determined that there was a termination for convenience to try and provide the ability to terminate the contract. So, you know, I have mixed feelings on that, but I just wanted to be able to say that on the record, that that's my concern with the situation is that it appears to me that Tech could have followed the letter of the contract, and if we don't follow the letter of the contract, then why do we have the contracts in place? And so that's my concern. Thank you. Any other discussion on the motion?
We have a motion and a second. All in favor, say aye. Aye. Any opposed, no? The no's have it. All right, we're back to the original motion. Do I have a motion to award this claim? I have that motion. I have a second. Any discussion on that motion? Seeing none, all in favor say aye. Aye. Any no's? No. The ayes have it. All right, that's it today, I believe, isn't it? Ladies and gentlemen, that is the show for today. Thank you for coming, and we are adjourned.
Associate General Counsel David Curran presented a report on the employment-discrimination lawsuit filed by Professor Brian Mitchell against the University of Arkansas at Little Rock, noting that the case is pending before Judge J. Moody with a motion dismissed and a 50-page brief filed.
[7:27][7:37][8:07]
When Representative Cozart asked for questions, none were offered, and the committee thanked Curran for his report before moving on to the claims-review agenda.
[8:20][8:39]
1. David Curran, University General Counsel, University of Arkansas System
a. Brian Mitchell v. University of Arkansas System, et al.
D. Claims Review
8:42 - 13:3017 segments6 speakers
The committee heard claim 220758 from Hugh Jarrett and Carol Booth requesting reissuance of an outdated $23,037 warrant; the Claims Commission unanimously approved the claim and referred it for inclusion in an appropriations bill.
[9:50]
After no questions were raised, Representative Cozart moved to approve the warrant reissuance, which was seconded and adopted unanimously.
[10:22]
Senator Trent Garner queried the settlement process, and Claims Commission Director Katie Sir clarified that the commission reviews and approves settlement agreements but does not participate in negotiations.
[12:25][12:35][12:45]
Representative Lane Jean moved to affirm the Claims Commission’s ruling on the settlement, a motion that was seconded and carried without opposition.
[13:05][13:14][13:21]
a. #220758 Hugh Jarratt and Carol Booth v. Arkansas Department of Finance and Administration
2. Negotiated Settlement Agreement
a. # 200054 Charles E. Cross, As Appointed Administrator of the Estate of Connie M. Stokes- Cross v. University of Arkansas for Medical Sciences
3. Awarded Claims
13:30 - 21:5030 segments10 speakers
The Claims Commission awarded James Construction Group LLC $910,837.44 for a bridge-project dispute with the Arkansas Department of Transportation, allocating amounts for overhead, deck replacement, flagging costs, liquidated damages, attorney fees, and pre-judgment interest.
[13:37][14:08][14:40]
Senators Bart Hester and Trent Garner questioned the Arkansas Department of Transportation about preventive measures for similar construction issues, and department officials indicated new oversight and engineering leadership to address concrete-pour problems.
[15:26][16:01][16:11][16:35]
During questioning, Senator Garner sought clarification on the unusually high flagging-cost component; the commission explained that the project required 138 additional flagging days beyond the contractor’s original estimate, justifying the $356,883.23 award.
[17:10][17:22][17:45][17:56][18:16][18:19]
Representative Cozart moved to award the James Construction claim, the motion was seconded and adopted unanimously.
[20:24]
The commission also approved a $22,500 reimbursement to Rock City Harvest LLC for a duplicate medical-marijuana license renewal fee, and a motion to approve this award was introduced and seconded pending final vote.
[20:58][21:32]
a. #181073 James Construction Group, LLC v. Arkansas Department of Transportation
b. # 220153 Rock City Harvest, LLC v. Arkansas Alcoholic Beverage Control Division
4. Awarded Claim – Appealed by Respondent a. #191111 Flynco, Inc. v. Arkansas Tech University
21:50 - 1:00:17132 segments16 speakers
The committee considered Claim #191111, Flinco, Inc. v. Arkansas Tech University, in which the Claims Commission had awarded Flinco $143,752.46-comprising $128,267.12 for the remodel contract, $7,985.34 for insulation, and $7,500 in attorney’s fees-and noted that Arkansas Tech had appealed the award.
[21:54][22:06][22:39]
Arkansas Tech argued it had the contractual right to terminate for alleged fraud and sought to strip the award of the $7,500 attorney fee and the $32,926.46 profit component, reducing the judgment to $103,326, while Flinco contended the award was based on a termination-for-convenience finding that entitled it to both work-performed compensation and profit on unperformed work.
[24:35][24:47][24:58][25:05][25:10][25:23][34:18][34:58][35:34][36:04][43:28][43:35][44:06]
A motion was moved to amend the Commission’s ruling to a reduced total of $110,806.46 (removing profit and attorney fees), seconded, and approved without opposition; a subsequent motion to award the claim was likewise seconded and carried unanimously, finalizing the committee’s decision.
[57:03][57:36][57:45][57:52][58:03][58:14][58:45][59:17][59:34][59:49]