D. Review of 2023 2nd Quarter and 3rd Quarter Reports on the Progress of Each Highway Construction Project of $10 million or More as Required by A.C.A. 27-65-1… 3:21
Rex Vines introduced the quarterly progress reports for all highway construction projects costing $10 million or more, noting that no slide deck was available.
[3:44][3:50]
Senator Hammer and other members questioned the I-30 widening in Saline County, learning that the prime contractor has filed an overtime claim, is subject to liquidated damages, and is being charged roughly $77,750 per day, but the bond has not yet been forfeited and subcontractors appear to be paid.
[4:35][4:46][5:24][5:43][5:54][6:26]
Representative Cindy Crawford asked about the Mazzard Creek (Highway 253-255) project, to which Vines explained two-year utility delays and projected an early-2025 completion.
[6:26][6:53][6:57][7:00][7:24][7:28]
Senator Hammer further probed the Selma County contract’s change orders and bond status, receiving confirmation that the bond has not been forfeited, a new completion target of November 2024 is being considered, and the bonding company will be involved if needed; Representative Bruce Cozart raised concerns about the Sunshine Road project’s utility-related delays, receiving an update that utilities have been relocated, work is progressing, and a full asphalt overlay is planned.
[8:05][8:24][8:27][8:34][8:45][9:07][9:22][9:38][10:31][10:45][11:16][11:49][11:53][11:57][12:08][12:20]
Committee members also sought clarification on funding acronyms (CAP = Connecting to Arkansas; IRP = Interstate Resurfacing Program) and asked for cost-per-mile data on a $13.5 million cable-barrier project, with Vines promising to provide the information later.
[12:34][12:48][12:50][12:59][13:04][13:23][13:40][13:50]
E. Review of January to May 2023 Monthly Updates of the ALC Efficiency Study Recommendations Rules for Implementation [Exhibits E1-E6] - Rex Vines, Deputy Dire… 14:04
Rex Vines presented the January-May 2023 monthly updates on the ALC Efficiency Study recommendations, highlighting new “lunch-and-learn” knowledge-management sessions (Recommendation 4) and the selection of a contractor to publish project status under the portfolio-planning recommendation (Recommendation 3).
[14:10][14:42][15:12][15:30][15:44][16:15]
He also reported that the department has begun using the GovQA platform to log roughly 2,000 public inquiries (Recommendation 4) and is conducting a procurement study of three peer DOTs (Recommendation 5), while noting the approval of a staffing-pool plan that will place about 97 % of appropriated positions into flexible pools and that 76 managers have completed a leadership development program (Recommendations 12-13).
[18:57][19:34][20:00][20:07][20:12][20:20][20:42][21:17][21:53][22:24]
Tom Fisher asked why Washington, Minnesota, and North Carolina were chosen for a project-delivery survey, receiving an explanation of the selection process and intended use of the data; Representative Watson and Representative McAlindon voiced safety concerns on I-30 barriers and Highway 72, with Vines attributing recent traffic backups to broken steel plates in drainage inlets and promising to follow up on the Highway 72 curve issue.
[31:55][32:08][32:15][32:33][32:41][32:46][33:19][33:31][36:14][36:33][36:55][37:17][37:37][38:05]
subcommittee called to order uh ron you got anything you need to share i do not decide to be here thank everyone for being here we've had a had a little bit of a break uh during the session a little a little bit behind on our reports uh but i think rex is going to get us caught up today And if there's no other business, we will begin with C, the Quarterly Land Conveyance Report, Exhibit C. Come on up and introduce yourself, Rex. If you want to say something for the director and let everybody know what's going on. Sure. I'm Rex Vines, the
chief engineer of operations for RDOT. The director is in D.C. this week meeting with our delegation there. So she's asked me to step in and sit in for her here. All right. Thank you and good afternoon. I would like to, before I get started, recognize that Commissioner Holder is here with us today. Ms. Marie Holder is in the audience with us. In your packets, there are three sections, and you'll notice kind of three categories. The first is Exhibit C, as Senator Johnson mentioned, and this is the quarterly report for land conveyances for the first quarter of 2023, as required by Act 1315. I do not have a presentation to go with that, but we would be happy to build any questions. Any
next on the agenda is exhibits D1 and D2, which are the quarterly progress reports for projects of $10 million or more. There are two reports for the second and third quarter of state fiscal year 23. We did not present to this committee during sessions, so this is the first time these have been presented. And I don't have a presentation for these either. I've just, if anyone has any questions regarding these
Hang on. I got to find you. Is that you? All right. That's Mr. Chairman. Is that me? You left? Good again. It's all messed up. All right. Am I recognized
in Saline County. Yes, sir. And I noticed it says behind what you explained why the project is not a pleasant experience. Yes, sir. I agree. I agree. The, just recently in last month, Johnson Brothers piled a claim against the department So we, Johnson Brothers, who is the prime contractor on that position, I apologize. They filed a claim against the department, so as far as causation, we are hesitant to make any comments in this forum. Their claim is over time, so we really can't say a lot of, give a lot of detail. We are meeting with the prime contractor leadership and their surety next week to try to find a way to progress this job faster. Senator Hamlin. Thank you.
And you may have to answer the same way. So with what you just said, have they reached the point to where they forfeited on their bond yet? Are you able to answer that?
No, sir. Not at that point yet. They are in liquidated damages and being charged road user costs. Okay, so they are in liquidated. They are in overtime, yes, sir. Is that the $77,000 a day? That's $77,750 a day. Okay, and do you know that all the subs are being paid and they're being kept? To our knowledge, they are at this point, yes. How would you not know that they're being paid? They would report to us normally. The subs will report to us if they don't get paid.
Okay, all right, thank you. Yes, sir. Representative Crawford. Thank you, Mr. Chair. On page 49, also, you guys are behind on Highway 253-255. Do you have any information on that and its completion date? Page
okay. That's the, there was, yes, ma'am, I'm very familiar with that job. There were some significant utility delays. The project was not able to even start for two years because the utilities were not getting out of the way for us to start until, I mean, it was two years after the contract had let. So the contractor has just begun work, I think, last fall. Do
uh should be let me find the job my numbers are different than yours okay it's early 25 that should be the spring of 25. early 25 yes ma'am thank you thank
thank you Mr. Chair I'm going to go back to Selene County for a minute I'm looking at page 18 and the contract bid amount 187 current contract amount 189 which that would mean that there were some add-ons that they were allowed for is that
added to the all right contract today we paid him 124 and the amount remaining 65 if if they have forfeited their bond just explain to me processes for how with the balance that they have remaining they forfeited their bond is there is there a new finish
date new complete date the when it when we say it forfeits the bond that just means bonding companies required to finish the project okay so they would have to hire a construction contractor to come in and finish the contractor. We would at that point get a new baseline to establish a completion date. So it's kind of at this point the completion date is scheduled for I believe November of 24th with the current contractor but they have not forfeited the bond yet. Okay. But the bonding company has taken over? Well we're meeting with the bonding company. We have not gone to that stage.
So now the new completion date, because I was asked about this this last week, because we got that new school out there, and so now the new completion date is November of 24? Yes, sir. That's what their current schedule is showing. And how do you go selecting the new contractor so we know we get somebody that can get it
the bonding agent. Okay. Mr. Chairman, I am not at all a member of this committee, but that's my neck of the woods. down there. Once they have that meeting, would the chair consider adding this specific item back on or it'll be in the report or when will this
Okay. I'd just like it to be an item of interest specifically, please. And I appreciate all the departments do know. It's a hard spot. We're in a bad way. Making the best of a bad situation. but open communication would be
you, Senator. Representative Kozak. Thank you, Mr. Chair. Mr. Beisel here. Yes, sir. Garland County. We've had a project on, we call it Sunshine Road. I believe that's 227 or 222 out there by Lake Hamilton School between 70 West and 270 West. that has been in repair zone for over a year. They've been doing a widening and a resurface or something. We do not really know what they're going to do to that road, but it's not really good what's been happening. It's been three years since they started that project and got pushed off of it. Barrels and banners set on the side of the road for a long time. Can you tell me what the situation is on that road and what's going to happen with it eventually?
Yes, sir. That project was also delayed significantly by utilities that were in the way, and they have recently, I believe, got all the utilities relocated. They ran into a lot of really poor dirt. The hill country is scattered with really bad dirt for building roads, so that slowed the progress down even when they had areas to work, but they have picked up the pace, and I believe they're moving forward now, and for C, I don't recall the estimated completion date, but I know they started making progress, at least I was
you know that? Yes, it will be. We'll, after they get the safety aspects done, they'll do a full overlay of the, at least the sections, that's a select section process, but at least those sections will
have a full overlay. people off as long as I can, and they want to know answers, but I tell people in my district that we are very lucky in Garland County and in Arkansas to have really good roads, and Garland County is really blessed with what y'all have done for us over there, so to be patient, but they just want to know what's going to happen and kind of when it's going to be, so I thank you for
your answers. Thank you, sir. Thank you, Mr. Chair. Representative Wright. Thank you, Mr. Chairman. There's a couple of acronyms on here that I'm just not familiar with. When it describes the funding for a particular project, it'll say federal, state, and then CAP and IRP.
CAP is our Connecting to Arkansas program. Okay. And then IRP is Interstate Resurfacing. Resurfacing, or Rehab, Rehabilitation Program. Okay, thank you. And then what are
half cent that expires this month. And then the temporary half cent was what paid for the cap. And the IRP, I believe, was by bonding. Okay. All right. Thank you. Senator Payton.
Thank you, Mr. Chair. So on page 55, it's got a $13.5 million project for cable barriers in the median. It doesn't say how many miles that covers. Can you give us kind of how much per mile it costs to do those cable barriers? I can't get
E. Thank you, Mr. Chairman. Again, the next, if you look, exhibits E1 through E5, our monthly progress reports for the ALC efficiency study recommendation. You'll notice again that we've got five here because we did not meet during session. And these reports are cumulative in nature. So the May 2023, I believe it's labeled monthly May, is the most current report that we have. And I would like to, with the chair's permission, just highlight a few things that have significant changes have been made since our last report to this committee. So I will be referring to page numbers throughout this, and they're all going to be your very last section, the very last May monthly, or monthly May. E5. E5. So all the page numbers I'm referring to will be in E5.
Oh, they have a June. Okay. Okay. Well, then E5. Okay, on page four, recommendation number four, under organizational structure categories, it said that we should strengthen knowledge management in anticipation of increased retirement. And since that, we have begun just recently having monthly series lunch and learn sessions with subject matter experts in order to share knowledge across the agency. Moving on to page 6, which is recommendation number 3. Under portfolio planning category, it said we should publish status of construction projects and maintenance activities. We have selected a contractor or consultant to begin this process. We have been negotiating the contract. finally reached the negotiated contract we will be going out for public comment on that contract and then bringing it back before this committee for approval so we're moving
Let me go ahead and get it now. Okay, Senator Chesterfield. Dealing with it. Thank you, Mr. Vines, for being here. I remember when we were dealing with a study of what you should and should not do. Let me compliment you first on having completed some of the recommendations from the subcommittee and the study that was performed by the national group. One of the things that we talked about was that we would tell people about people who weren't doing a good job. Am I correct in that? Yes, ma'am. I believe so. Okay, if my memory serves me correctly. We do know that we have not been served well by the contractor that has that contract between Benton and the Hot Springs exit. So are we waiting for the litigation to end before we just say publicly they have done a lousy job? Or can we say that and you can't? I would prefer you say that. Okay, they've done a lousy job. And so I'm going to say it because I don't want you to say it, but any time a project has gone on that long and has not reached the level of completion that I believe it should have, I can say I think for myself and maybe others that they have not done the job They should have so as we go through this process and we continue this process of evade process of evaluation Dealing with the recommendations from the previous committee We need to be looking at making sure When we can as a body that folks know these folks do not do as they say they're going to do and You don't have to say I agree, but if you're not it'll be okay. Yes, ma'am. Thank you. Mr. Chair. Yes, ma'am. Thank you So
I know that was part of the deal is to for an evaluation for those contractors Yes, sir. Is that that that is a work in progress. Yes, sir. That's still a work in progress
Yes, thank you. Yes, sir. Go ahead Recommendation 4 on page 9, under the portfolio planning category, it said we should implement a platform that tracks all stakeholder inquiries to resolution. The department staff has began using what is currently called GovQA, which is a database it collects and we started using that internally so we are taking calls or emails or whatever and we're inputting it into this system and tracking it into resolution and that's part of this so we are currently we have taken in 2,000 entries from the public and input in the system we're still working out some of the bugs before we go completely live with it but we're getting very close on that one. Okay, the next. Out
nature that we can take care of quickly. All right, recommendation number five on page 11. Under procurement category said we should implement efficiencies in procurement and purchasing. We have surveyed state DOTs or departments of transportation across the country and based on responses provided we have selected three DOTs to go into more detail on their project delivery systems or selection processes. We have held interviews with Minnesota DOT and Washington DOT based on their responses and have determined and how to determine the methods of project delivery they use, each one. The information gained from these interviews will be used to help guide us as we develop process of project delivery selections. And then lastly on my part that I would have prepared on recommendations 12 and 13 on page 29. Under people capabilities categories, the recommendation said that we should ensure staff can develop in their careers at the department and improve staff capabilities to align with current and future organizational needs. State fiscal year 20 and 2024-2025, we submitted a plan to expand the existing pools and add additional pools for employees. Our budget proposal was approved and enacted, which means approximately 97 percent of our appropriated positions will be pooled. This gives us much greater flexibility in providing more opportunity for our employees to advance in their careers and stay within budget constraints. and furthermore we have a total of 76 managers who have been have completed the leadership development program and have more scheduled
not a huge uh change to date our our largest um retention areas or entry-level positions and have a lot of turnover there thank you yes sir that mr chairman that completes my report we have to answer any more questions
mr chair mr vines as we talk about turnover which is more entry level than any place ourselves. Are we able to give our staff over at DOT raises that are commensurate with
their experience in education? Yes, ma'am. We have a policy that allows us to increase entry-level salaries for exceptionally well-qualified applicants. We have recently, with the direction of director tutor and approval of commission approved regional raises that allows areas where we have trouble hiring the little rock metro area the northwest arkansas area where there's a lot of job competition we've increased those salaries and then in areas where our employees are working in multi-lane high-speed freeway systems we've increased their pay to help compensate for the
the more dangerous work they're doing? Well, one of the issues that I brought up with the director was the subjective criteria that is being used in many places to determine whether or not an individual is meritorious. And I had suggested that we create a more objective evaluation predicated on days at work, educational, whatever, but to make it more objective. Have we changed at all how we are dealing with determining what is meritorious and what is not?
Well, you told me that a couple of years ago, so I'm just concerned because our staff is being evaluated on sometimes the whims of the individuals in charge of their particular division. And that's always troubling to me that we don't have an objective criteria that says if you do this, this, and this, no matter where you are, you are going to get the raise that you deserve rather than my boss likes me because of this and therefore that individual gets the raise. So it's still a concern of mine because I think we need to be more objective in our criteria for not only Department of Transportation workers, but all of our workers so that they know exactly what they need to do in order
to report on? Mr. Vines, I wonder if the commission had any reports or anything or any concerns on funding uh during session we we i guess took care of our match federal funding still coming through as families it's supposed to yes any concerns there and the other thing and if you don't have it now is fine but i'd i'd like to have in a future report if we could uh because i can't remember the details on like the casino money they they've done quite well through covid and Have we hit that where it got to a percentage and some of it goes to roads?
Have we ever got any of that? Yes, sir. We get that at the beginning of the fiscal year. And, yes, we have been receiving that. We have not had any funding issues. Part of the reason Director Tudor is in D.C. is we did not get some grants that we had applied for through the federal government, and they just were going up to get a debrief, you know why. But otherwise, funding, all the funding mechanisms are working. Good deal. Thank you. Yes, sir. Thank you, Mr. Chair.
Representative Hawke. Thank you, Mr. Chairman. I just wanted to go on record because I said ahead of the meeting, I really want to thank you, Mr. Vines, but also your new associate return to DOT, Michelle Davenport, that you stole from BLR. She was really a great person to work with here at BLR and surely made, I'm sure, many of us, myself included, just a great person to work with. And I'm glad that you have her at DOT. So I just wanted to congratulate you on that.
Mr. Chairman. Rick, first of all, I've served on this committee for many, many years. And I'm not complaining because I'm well aware of the number of miles we have in this state to surface and the number of people we have versus other states. And I'm also aware of the influx of people we have coming in from other states moving into rural areas in Arkansas. So one of the most frequent complaints I get is not the primary roads, but it's the secondary roads. The little branches that branch off and go to Scranton or go to Cecil, and they are absolutely falling apart. I know I drive them. Just when I get the complaints, I go and drive. And they really are. Some of them are becoming hazardous. They've still got the little concrete barriers where water goes under. and two two trucks can't cross at the same time without hitting
to these these secondary roads well that's the the primary function of our maintenance area headquarters and our district maintenance divisions is to take care of those we're we're spending 75 approximately on pavement preservation on primary system which allows freeze them up to work on those secondary routes but as we've mentioned we have a shortage of employees and and we have um kept up with some but there are others admittedly that are just woefully far behind and we our anticipation is that as as we continue to spend the money on our primary network and get it in good condition and we can then turn and focus more attention with construction work on these secondary routes and these lower volume
headed in well i've seen spots where they're patched and you know temporarily fixed where you can maybe get the people to calm down a little bit but there's really not been any major i mean i haven't seen a lot of major overlays or construction in those secondary, and some of them go to cities that are 2,000, 1,500, 500. Yes, sir. And I was just curious as to how much emphasis is placed on these secondary roads versus the primary routes that people travel every day. Yes, sir. But I appreciate what you
do. Yes, sir. Thank you. You're welcome. Senator Payton. Thank you, Mr. Chair. Mr. Vines, this is recommendation number five on page 11. I'm just curious what drove us to choose Washington, Minnesota, and North Carolina as the examples, and what type of questions are we posing to them, or is there something in their program that's similar to ours that drove us to those decisions, or what?
I would like to, if the Chair's permission, call someone up to help me with that. I was not directly involved in that part, so I'd like to call some morning up
My name is Tom Fisher. I'm the Alternative Project Delivery Administrator for the department. Okay, if you could slow down just a little bit and tell me what you are again. My name is Tom Fisher. I am the Alternative Project Delivery Administrator for the department. Okay, can you maybe help solve my curiosity as to why we chose Washington, Minnesota, and North Carolina as our examples, and what type of information are we trying to glean from them? Yes, sir. So we sent out a survey to various DOTs and received 22 responses from our peer agencies. From those 22 responses, we selected North Carolina, Washington, and Minnesota DOT because they seemed to fit the attributes that we were looking for for our program and our tool to be able to develop a project selection tool. Okay, well, pardon my ignorance, but can you explain a little bit more about what we're trying to find out from them? Yes, sir. So, under our program, we would take projects that are estimated to be $10 million or more, and we would use a workshop to determine what type of delivery method we would use for a project, whether it be design-bid-build, which is our traditional method that we use for probably 95% of our projects. And we also have design-build projects, which is the 30-crossing project, the I-30 through Little Rock and North Little Rock. We also have the construction manager general contractor delivery method, or the CMGC, which is the project that's on Highway 10, on Highway Cantrell, that's currently wrapping up. And then our other method is the progressive design-build project. So basically, we're asking these three states how they make their determinations and how they arrive at their evaluation of the projects, and we're trying to model ourselves after that, or what? That's correct. Well, we took the attributes that they did and kind of modeled it to fit our needs. We're not mimicking theirs. We want to lean on their process to kind of see what processes they used that we liked, what processes they used that we didn't feel meet our needs, and then from that, develop our own project selection tool.
Okay. Thank you. Thank you, Mr. Chair. Representative Watson. Thank you, Mr. Chair. Mr. Vines, I wasn't sure whether I was going to bring this up or not. A little commute that I had this morning from Hope to the Capitol wound up taking me three hours and 18 minutes. I want to focus in on the I-30 with the concrete concrete barriers on each side if you will just visualize for just a minute eastbound northbound whatever you want to call it before you get into the Bryant Benton area it's just a thought I've worked that area before what I'm looking at right now is some more possibly. We don't want too much signage, but especially when the traffic is slowing down. I don't know. I have not had a report. That's not my job anymore, but I just wonder if there were any major accidents through that area today. That was unbelievable. That was unbelievable, dangerous. Again, concrete barriers on both sides. Law enforcement could not respond. They sure cannot work radar in there because it's so many miles you go through there You cannot do a traffic stop But I'm really really really I've always had a nightmare about getting rear-ended And I made sure several times that I use my full ways to warn the the truckers behind me My point is yes, it's inconvenience. That's part of it. That's part of prosperity But when it comes to the major safety part, that's where you know I just want to visit, just to give you some thoughts on there. Is there any more? There is signage. There is some signage, but is there anything else maybe more clear as far as the motorists go to warn them? Three days ago, there was three motorcycles right in the middle of that on the left side, and I thought it was a major accident. I think they had motor problems. It's a wonder all three of these did not get run over. It was unbelievable. When I drove up there, I looked to my left lane. It was luckily, it was kind of like parting the sea, and everybody kind of was being behaved and got in the
right lane. Any thoughts on that? Yes, sir. We have this morning. What caused that backup was the drop inlets that were there for permanent drainage have metal. The steel plates in the right lane, yes. Two of the steel plates had broken loose to traffic, and they were repairing those emergency repairs. where traffic didn't drop off into one of the drop inlets and that's what caused that delay this morning but yes sir we can look at see if there's a way we can add some signage we do publish this on our iDrive Arkansas and we encourage that but sometimes it's too late of all time my iDrive was not working
I deleted it and brought it back but anyway anyway that I didn't want to want to not say anything about this because I mean this morning could absolutely have been a major major chain reaction accident and I appreciate y'all yes sir thank you thank you thank you
chairman first I want to just commend y'all I had the opportunity to attend a couple of your north-south corridor meetings up in Northwest Arkansas and a lot of interested participants there, but the people who attended from RDOT were very patient and very well informed. So I just want to commend your office for that. Second, on Highway 72, up in kind of the Bentonville-Centerton area, there between Teter Black and 102B, we've had a lot of accidents of that same curve, right? About six or seven so far this year, taking out the guardrails, including one death there. I spoke with Ms. Tudor, who spoke with Steve Frisbee, I believe, and is supposed to be looking into that. I wanted to see if you just had, it's been a week or so, I wanted to see if you had any update on that issue at all. No, ma'am, I do not, but
That'd be great. Thank you. Yes, ma'am. Is there any other questions from members? Seeing none, are you? I'm done. Done. Is there any other business? Seeing none, we are adjourned. Thank you.
D. Review of 2023 2nd Quarter and 3rd Quarter Reports on the Progress of Each Highway Construction Project of $10 million or More as Required by A.C.A. 27-65-107(a)(19) [Exhibits D1-D2] - Rex Vines, Deputy Director and Chief Engineer, ARDOT
3:21 - 14:0450 segments9 speakers2 documents
Rex Vines introduced the quarterly progress reports for all highway construction projects costing $10 million or more, noting that no slide deck was available.
[3:44][3:50]
Senator Hammer and other members questioned the I-30 widening in Saline County, learning that the prime contractor has filed an overtime claim, is subject to liquidated damages, and is being charged roughly $77,750 per day, but the bond has not yet been forfeited and subcontractors appear to be paid.
[4:35][4:46][5:24][5:43][5:54][6:26]
Representative Cindy Crawford asked about the Mazzard Creek (Highway 253-255) project, to which Vines explained two-year utility delays and projected an early-2025 completion.
[6:26][6:53][6:57][7:00][7:24][7:28]
Senator Hammer further probed the Selma County contract’s change orders and bond status, receiving confirmation that the bond has not been forfeited, a new completion target of November 2024 is being considered, and the bonding company will be involved if needed; Representative Bruce Cozart raised concerns about the Sunshine Road project’s utility-related delays, receiving an update that utilities have been relocated, work is progressing, and a full asphalt overlay is planned.
[8:05][8:24][8:27][8:34][8:45][9:07][9:22][9:38][10:31][10:45][11:16][11:49][11:53][11:57][12:08][12:20]
Committee members also sought clarification on funding acronyms (CAP = Connecting to Arkansas; IRP = Interstate Resurfacing Program) and asked for cost-per-mile data on a $13.5 million cable-barrier project, with Vines promising to provide the information later.
[12:34][12:48][12:50][12:59][13:04][13:23][13:40][13:50]
E. Review of January to May 2023 Monthly Updates of the ALC Efficiency Study Recommendations Rules for Implementation [Exhibits E1-E6] - Rex Vines, Deputy Director and Chief Engineer, ARDOT
14:04 - 38:2379 segments14 speakers2 documents
Rex Vines presented the January-May 2023 monthly updates on the ALC Efficiency Study recommendations, highlighting new “lunch-and-learn” knowledge-management sessions (Recommendation 4) and the selection of a contractor to publish project status under the portfolio-planning recommendation (Recommendation 3).
[14:10][14:42][15:12][15:30][15:44][16:15]
He also reported that the department has begun using the GovQA platform to log roughly 2,000 public inquiries (Recommendation 4) and is conducting a procurement study of three peer DOTs (Recommendation 5), while noting the approval of a staffing-pool plan that will place about 97 % of appropriated positions into flexible pools and that 76 managers have completed a leadership development program (Recommendations 12-13).
[18:57][19:34][20:00][20:07][20:12][20:20][20:42][21:17][21:53][22:24]
Tom Fisher asked why Washington, Minnesota, and North Carolina were chosen for a project-delivery survey, receiving an explanation of the selection process and intended use of the data; Representative Watson and Representative McAlindon voiced safety concerns on I-30 barriers and Highway 72, with Vines attributing recent traffic backups to broken steel plates in drainage inlets and promising to follow up on the Highway 72 curve issue.
[31:55][32:08][32:15][32:33][32:41][32:46][33:19][33:31][36:14][36:33][36:55][37:17][37:37][38:05]